Committee of the Whole · February 03, 2026 · Item 5.1

Internal Audit Work Plan 2026-2028, as outlined in the report titled “Internal Audit Work Plan 2026 – 2028” dated Tuesday February 3, 2026, be approved.

Main motion under the agenda item Internal Audit Work Plan 2026-2028 - 2026-51

Carried (12 to 0)

12 in favour, 0 against — unanimous

This was one of 2 motions on the same item

In the order council took them. A vote makes sense next to the ones around it.

  1. 1/2Main motionInternal Audit Work Plan 2026-2028, as outlined in the report titled “Internal Audit Work Plan 2026 – 2028” dated Tuesday February 3, 2026, be approved.you are hereCarried (12 to 0)
  2. 2/2Main motionOperations Services staff be directed to investigate and report back on winter control and winter maintenance service levels, including potential additional services…Carried (12 to 0)

What was voted on

The motion in its exact words, as recorded in the minutes.

That the Internal Audit Work Plan 2026-2028, as outlined in the report titled “Internal Audit Work Plan 2026 – 2028” dated Tuesday February 3, 2026, be approved.

Moved by Mayor Guthrie, seconded by Councillor Busuttil.

How the room voted

In favour (12)

  • Allt
  • Billings
  • Busuttil
  • Caron
  • Caton
  • Chew
  • Downer
  • Goller
  • Guthrie
  • Hauser
  • Klassen
  • Richardson

Who spoke to it

Robert Jelacic, General Manager, Internal Audit, presented on the Internal Audit Work Plan 2026-2028.

What council was given

The staff reports and correspondence attached to this item. The summaries are written automatically, so you can tell what a document is without opening a ninety-page PDF.

A summary is this site’s description of a document, not the City’s. Open the document before relying on one.

What was said

4,141 words from the meeting recording, transcribed automatically. Times are from the start of the recording.

Read the debate(click to open)

36:20audit i'll turn it over to you robert all right thank you councillor Goller and good afternoon

36:31council and mayor um just want to give you a quick overview of the report without any

36:37formal presentation but uh just to give you a sense of where the report uh some of the things

36:41i want to highlight from the report um so the report presents the 2026 internal audit work plan

36:47and also provides a status update on 2025 activities as well as previewing priorities for

36:53audits in 2027 and beyond the plan supports the city's strategic objectives through improved

36:59governance risk management and internal control evaluations before we get into the details i

37:05wanted to highlight a few things about the process of setting the plan as in prior years the audit

37:10plan was developed using a number of input factors these include feedback from management and council

37:15consideration of emerging trends and results from an internal audit risk assessment utilizing

37:21self assessments completed by all department leaders i also want to sorry excuse me i also want

37:27to assert that all internal audit activity from sitting this plan to executing audits was done

37:33independently and objectively with no undue influence from the management team lastly internal

37:39audit activities do comply with the international internal audit or IIA standards for internal

37:45auditing attachment one of the report lists the 2026 priorities audits that are going to be focused

37:53on uh and these were chosen because of their elevated risk areas and potential governments

37:59improvements in terms of the 2025 audit status update as noted in detachment three four audits

38:07were scheduled two have been completed and two are in progress and are expected to be completed

38:11with the report reports to council in q2226 pre-consulting projects were completed including

38:19enterprise risk management framework advancement as well as an internal departmental compliance

38:24review with the updated IIA standards that became effective for 2025 during 2025 we also

38:35presented the first ERM risk register uh to council and that was done in june of 2025 an update to

38:42this document will be presented in july as part of our continued our commitment to continuous

38:48improvement at the end of each audit we ask clients to complete a customer survey using the

38:53results to identify opportunities to enhance the audit process the benchmark standard is a score of

38:5875 a satisfaction score of 81 was achieved in 2025 executing the audit plan strengthens

39:06strengthens governance accountability and risk management practices for the organization

39:12recommendations made in the audit reports were all accepted by management with action plans plans

39:17in place and followed up by us an internal audit there are sometimes financial implications of

39:22audit findings and these are managed through departmental budgets and council approval

39:27so looking ahead to 2027 and beyond work plan attached in attachment to uh was updated using

39:34the same risk based approach and lastly the internal audit charter remains valid until the end of

39:39current council term it will be updated next year with the uh new term of council

39:44so in conclusion the 2026 internal audit work plan positions the city to proactively manage

39:51risks improve efficiency and maintain compliance with professional standards while supporting

39:55strategic priorities and i'll open up the floor for questions thank you very much for that presentation

40:04i will go to the mayor first he said he wanted to ask a question or move a motion thank you chair

40:10and through you yeah i'm happy i'm happy to move the the work plan for 2026 first uh do we have a

40:17secondary is that councillor was it till that had her hand up okay thank you thank you so yeah just

40:23a couple of questions and then maybe just a little bit of a follow-up um the first one was just a

40:27question on the flow through of the building permits and inspection that's not quite done it's

40:34just kind of moved it moved into 2026 but it will be done in the first uh one or two quarters of this

40:39year i believe am i am i right on that i think so through the chair gollard to you mr. mayor yes

40:44that's correct okay report coming up in may and i was just wondering um is there anything that was

40:50a carryover or anything within your work plan right now where that can kind of scoot to the front of

40:55the line i'm just wondering like or know your plan has to follow the the course that it's on and it

41:02will it will be done when it's done so mr. mayor you referring to that particular audit just that

41:07one yeah just wondering because i know it's it's it's a carryover which we all want to have done

41:12but i'm just wondering like yeah i hope i explained the question right i'm just wondering can it can

41:18be moved moved up and can we get that information sooner than later because if there is anything

41:22within that i'm not not that the other ones aren't important but if there's anything in that one that

41:27does come across as needing some attention i was just wondering about trying to get that done earlier

41:33as quickly as possible so that we can implement the things that we want to have changed sooner

41:38yeah through uh through chair gollard to do uh mr. mayor um that report is actually in its final

41:43winddown phases right now okay that audit work okay so i think leaving it in that may

41:48timeline to have the final report to council is probably advantageous i don't think we can rush

41:53the process okay no no problem because we still have to go through it just a curiosity question so

41:59thank you very much do not rush it thank you okay and then my final one is wouldn't be a surprise

42:04about the winter maintenance one so thank you to staff and to you for acknowledging and putting

42:09this on as a recommendation i don't think anyone's gonna you know second guess that that's something

42:14that maybe we want to have looked at fair enough um but i just want to understand the scope of what

42:20you're doing for a value for money audit compared to what might be and council knows like a secondary

42:28sort of motion that might tie in with uh with where this is going and so when you do a value

42:35for money audit uh you're just looking at the existing policy standards and and how that is

42:42operating compared to it compared to those policies and standards now right nothing out of scope of like

42:50extra engagement or extra options or extra considerations it's just what do we have now

42:58and how is that how is that stacking up against itself am i explaining that okay yes you are

43:05through uh the chair councillor color too yourself mr. mayor yeah absolutely so our audit process does

43:09follow the value for money framework which includes an evaluation of current level of services and

43:15expectation standards to the point of that audit so our audits would not involve adding extra

43:22extra possible work or extra possible resourcing that's needed by the department i think that would

43:27be best served through a more full-sum exercise executed by the particular department in this

43:32case operations to sort of evaluate if that is something that that they're able to do within

43:37their work planning and their opportunity to do that in the near future so you're absolutely right

43:42our audit focus is just on existing sort of standards and practices and we'll assess effectiveness

43:47efficiency and economy to that yep perfect thank you well well stated so if um and i'll you know

43:54obviously i'll table this with my my colleagues to see if there is that that other option

44:01how would you work with how would you scope your work to be because you have a lot of um

44:07blinders in place place for a reason right you're like you're independent right so you want to do

44:13your work but at the same time how could if there was a an added scope on the operation side

44:20can you at least uh align the tabling of that report for council at a certain date you know

44:27down the road in 2026 so it could come together so we get the the internal audit the value for

44:34money audit that shows us how the existing maintenance standards and policies are working

44:40but then the operations can also table their options for what's happening at the same time

44:45and would it at least be done in enough time do you think your audit for um influencing

44:53the next budget if there were any you know impacts to that yeah through uh chair gollard to you

44:59yeah absolutely i mean obviously we haven't had any scoping discussions with the operations team

45:06or even talked about the timeline of the audit but definitely we can work with them and try and

45:13align to make sure that the results of our audit which i think would be beneficial to them in terms

45:18of establishing some baselines on existing services and then using that information to sort of help

45:24and you know at council direction decide if there might be some additional work or focus that

45:30needs to happen on possibly changing or altering or expanding those services so yes we would

45:35definitely work with the operations team to to provide a timeline that works for both of us

45:41i don't know Colleen if you want to i don't think that uh it's up to the chair okay i mean i was

45:47good to ask Colleen a question i mean wc a clock push a question anyways but yeah there's a couple

45:52of other questions but you go ahead so the floor is still yours well i i just because Robert acknowledged

45:59uh wc a clock push i just it saves me asking a question so so why don't you go ahead and say

46:05would you agree with sort of the timelines and the opportunity that would be before us if such a

46:10motion passed then i'll go right back to you chair gollard in case there's questions to the

46:14please go ahead the bco sure thank you for the opportunity so that a couple of things maybe that

46:19would be helpful for context so our operations department is sort of our quarterback for lack

46:24of a better analogy of our winter control efforts but we do have winter control efforts that take

46:27place both within our parks team and within our corporate facilities team so we would want

46:31any review while it would be led by our operations team we would want it to be a fulsome review of

46:35our winter control efforts um and the last time we provided an update to council there was an

46:40information report in uh june 2022 um i think june 17th if anyone wants to go look it up um was the

46:46last time we provided a fulsome update on what our winter control efforts are and at that time

46:51there's also attachments to that report um that anyone can look at because we do have council

46:55approved standards for level of service so council has set out for us and approved what are the

47:00service standards for example um how soon we get to residential sidewalks versus um bus stops versus

47:09streets that sort of thing and so those council approved standards exist um and uh and so uh

47:15the sort of long way around answer would be to say that if there was a desire to change those

47:19levels of service council would need to direct us to change the level of service obviously what you

47:23need from us is a sense of what would that take what would be the costing equipment staffing the

47:28resources that would be needed and so as mr. Jelassica said that would be work that would be

47:33coordinated through our operations department and we could come back to council with a report or

47:38some options for you on what would it take to change those levels of service that are currently

47:43that we're currently always trying to meet um so in answer to the timing question the the one

47:49flag that I do just want to say is that um we it's the same team who does a lot of our reviews

47:53within operations we pulled them off the e-scooter review when council directed us to move the

47:57renovation bylaw our review forward and it is the same staff who would need to do this work and so

48:02we would need to take that away and look at options um in terms of could this wait until after the

48:08renovation bylaw work was done does it need to happen sooner in which case how could we resource

48:13it and so I don't want to give specifics today um just kind of wanted to hear the discussion from

48:18council to see what the sort of direction was and then we'll need to go away and look at how

48:24we either need to adjust our work plans or look at what resourcing we need um because we did hear

48:29from council that the renovation bylaw was a priority um and so we would just need to take

48:33this away and figure out how best to look at that in 2026. Thank you chair and through you and thank

48:41you to uh CAO clock bush for the for that answer there um and and that's that's that's very fair

48:48I think I was told the renovation bylaw would come back may or June so maybe this is something that

48:52happens after that um but I'll I'll go back to the chair to allow if there's any questions on

48:58on the report but as council knows I'd like to move a secondary motion after this one

49:04around the maintenance snow plow issue okay so thank you. Thank you worship I'll go over to

49:10councillor Caron now. Thank you through you uh chair goller my question was um a little broader

49:15rather than specific items on your work plan I just wanted to comment that I really appreciate

49:20the value for money audits I find them very illuminating quite often we find out we're very

49:25efficient sometimes there's always improvements and sometimes um we actually um need more resources

49:31so they're they're very uh important part of us doing our job to the best of our fiduciary ability

49:37so my broader question was um I know in an audit cycle um you can expect that an audit

49:45in any given area would take place every you know seven to ten years we also at a concurrent

49:51policymaking um calendar we have bylaw reviews and I'm wondering if you could just speak to

49:57how we integrate our bylaw reviews with our internal audits and whether they're in all of my

50:05years on council we've never had an internal audit on the same department and the same line item

50:11when when can a department expect to have a review every 15 years uh broader broader question about

50:18the role that you're playing in the in the overall organization um through chair goller to

50:24councillor Caron uh yeah that's a great question and I think part of that speaks to the um the sort of

50:31the sort of time that internal audit has been a function here at the city of golf uh we really

50:36I think started this risk-based approach of a mistake in around 2017 uh and so understanding

50:42that the city is is is large there's a lot of different service areas there's a lot of different

50:46components um and you know quite honestly risks and the emergency emerging risk library or emerging

50:53risk world seems to change regularly and so we try to as much as we try to be proactive a lot of

50:59times I feel like our audits are a little bit reactive as well uh to some of the things that we

51:03should be doing um so I would say it's it's difficult to answer that question in terms of a specific

51:08time period when you know department should expect to to see an internal audit um so it's hard to

51:15say that and again this is why I think we do the annual audit plan setting uh through an avenue

51:20like this uh I know colleagues uh some of my colleagues will do like a five-year audit plan

51:24I think that you know that would be just a little bit too long of a term for us to be able to say

51:28yeah you know what in four years we're going to look at this because there are changes that that

51:32happen um so I think my hope would be that you know once we get through a sort of larger

51:38number of audits and again the ERM framework and policy help in that regard because it helps us to

51:43sort of identify the higher risk areas that we should focus on not only as an organization but

51:48internal audit as a department and so I think that having having gone through the different

51:53processes and functions uh at least as a first crack then we can sort of look to see what type of

51:59you know planning we could do in the future to have some of these repeat audits we also do

52:04counselor have a follow-up process so some of the larger areas that we audit and if we see a lot of

52:10recommendations come out of those we can execute a follow-up audit within a reasonable amount of

52:14time so for example more recently we did a follow-up of the payroll process which with an audit that

52:20was done back in 2017 identified a number of recommendations and so it was felt prudent that

52:24we should put that into our sort of audit plan for a camera year we did that but we did a follow-up

52:29audit within about a five-year window when all of the recommendations were were more or less

52:34completed and so that's something else another tool that we could use to help us sort of move

52:39audits into the the audit sphere if you will and as I always do every year I ask counsel for

52:45their thoughts and opinions on which audits we should execute so certainly I would encourage you

52:49and your colleagues if there's things that you want us to look at let us know what that is

52:54including a possible scope for that and we'll certainly work to add it into the audit plan

52:58depending on the risk assessment that we do. Okay thank you very much and I remember hearing that

53:02there's about 700 distinct services that the organization offers and if you do three to five

53:07a year that could take every 200 years your department gets an audit which of course obviously is

53:12is not good management of our resources so I'm really glad to hear that both regulatory change

53:16and council priorities are helping to steer that work plan so thank you for that. Thank you

53:22Councillor Kerr-on and I'll recognize Councillor Busuttil you're up next. Thank you and through

53:28your chair Goller I think most of my questions were asked by Mayor Guthrie but it's in relation

53:34and thank you to Mr. Jelacic and to your team I know you're a very small team but you're very

53:39effective and really appreciate the work that you do. It's around the scope I'm trying to understand

53:46the continuum of the scope would it include things like communication you know where is the plow

53:53report a problem do you go outside of operations or is operations just the you know hitting the plow

54:01on the road kind of operations? Yes thank you through chair Goller to Councillor Busuttil.

54:10Again we haven't had any detailed scoping discussions yet either internally for us as a

54:14department or with the with the teams that are involved in later maintenance but yes absolutely

54:20we wouldn't limit it to just the pure operations function we would look at the various components

54:25that would be a factor and again we use a risk-based approach so we wouldn't necessarily look at every

54:31single item that might be part of winter control maintenance but we will try to focus in and hone

54:36in on those areas that traditionally have been sort of higher risk in that particular function and I

54:43think certainly you know that sort of customer focus and that complaint dealing with complaints

54:50would be an element that would probably be in the scope of this audit like it is in most of the

54:54audits that we do execute we usually do look at that sort of customer feedback mechanism and

55:00more importantly to us is how those are dealt with and how they're escalated and how they're

55:03sort of action so we would look at that as a as a very strong possibility within the scope of the

55:08winter maintenance audit. Thank you very much. Thank you Councillor Busuttil. Are there any other

55:15questions or comments from my council colleagues? Seeing none I'll turn the floor back to your

55:21worship. Okay that's supplementary okay well thank you very much for this report Mr. Jalasek

55:31we're all very excited to see the work plan for 2026 I really appreciate it I'll call the vote

55:38all those against this report this motion. Seeing none the 2026 work plan is received thank you so

55:51much and with that I'll turn it over to Mayor Guthrie. Okay thank you and it stops the clerks

55:58to throw it up on the screen there for me the secondary motion that ties in with the

56:05value for money audits moved by myself and seconded by Councillor Busuttil that the

56:10operation service staff be directed to investigate and report back on winter control and winter

56:14maintenance service levels including potential additional services that the report back include

56:20financial and resourcing analysis along with the incorporation of community engagement components.

56:25I think I'll just let it stand at that but with a caveat that we've heard from Deputy

56:32CAO Clark Bush that if between now and the end of the month if you're looking at sort of the work

56:37plan and and the scope of you know when to do it and the resourcing and stuff that I'm happy to have

56:44that amend what comes back at the end of the month based on what Deputy CAO Clark Bush says but I'll

56:50let this stand for now as it is. Okay that's it I think everyone wraps it so thank you for that

56:57Mayor Guthrie so far I have questions from Councillor Caron and Councillor Oltt any other

57:01questions on this no okay I'll go over to you go ahead thank you Chair Goller and I guess it's a

57:07question to the mover and I hope it's friendly one of the lines says including one of the things

57:11that isn't included in there is that I think makes a good review is best practice comparison to other

57:18municipalities and I wondered whether that should be included in the review or whether staff would

57:24automatically include that in a review as a matter of process or whether you need direction from

57:29council to include it. Yeah I thought maybe it was maybe captured in the wording that says potential

57:37additional services that those that phrase would allow them to look at best practices but I'm not

57:43sure maybe staff should answer that because if it's required I'm happy to go with you on that.

57:47Please go ahead the PDCO. Through the chair I think we hear the sentiment and we recognize that we

57:53would typically do best practice review anyways but here in this discussion we would certainly include

57:57that. Thank you Councillor Caron I'll go over to Councillor Oltt go ahead Phil. Thank you Chair

58:05Guller actually Mayor Guthrie answered my question in his response. No other questions then to the

58:14motion on the table on the floor then I'll call the vote all those against the motion please raise

58:21your hands. Seeing none it passes unanimously. Thank you Mayor Guthrie and thank you Councillor

58:28Bousatil for bringing that forward. With no other items I will just look to see if there are any

58:35service area announcements I think nothing else besides what we've covered so we're good thank

58:41you so much for coming and for bringing the the audit for 2026. I'll turn this over to Councillor

58:49Caron now. Welcome everyone we are now sitting as the corporate services and offers of the CAO

Automatic transcription is imperfect. Treat quotes as a guide and check the recording before relying on exact wording.

Check this against the City’s official minutes

The motion, the vote and the debate come from the City of Guelph’s published record, reproduced rather than interpreted. The document summaries above are the exception: those words were written for this site.

See the rest of this meeting