Council Planning · January 21, 2025 · Item 6.1
Statutory Public Meeting Report regarding the proposed Official Plan Amendment and proposed Community Planning Permit By-law for the Community Planning Permit System from Infrastructure… be received
Main motion under the agenda item Public Meeting Report Draft Official Plan Amendment and Draft Community Planning Permit By-law - 2025-04
Carried (11 to 0)
11 in favour, 0 against — unanimous
What was voted on
The motion in its exact words, as recorded in the minutes.
That the Statutory Public Meeting Report regarding the proposed Official Plan Amendment and proposed Community Planning Permit By-law for the Community Planning Permit System from Infrastructure, Development and Environment dated January 21, 2025 be received.
Moved by Councillor Busuttil, seconded by Councillor Downer.
How the room voted
In favour (11)
- Allt
- Billings
- Busuttil
- Caron
- Caton
- Chew
- Downer
- Gibson
- Goller
- Guthrie
- O'Rourke
Who spoke to it
Brenna MacKinnon, Project Manager and Justine Giancola, Dillon Consulting, presented the Draft Official Plan Amendment and Draft Community Planning Permit By-law. Council recessed (4:26 p.m.). Council reconvened (4:30 p.m.).
What council was given
The staff reports and correspondence attached to this item. The summaries are written automatically, so you can tell what a document is without opening a ninety-page PDF.
- Public Meeting Report Draft Official Plan Amendment and Draft Community Planning Permit By-law - 2025-04.pdf
Information for a required public meeting on a City-initiated Official Plan amendment and a draft Community Planning Permit By-law, which would combine several planning approvals into one permit process. The pilot would apply in two growth areas, downtown and Stone Road/Edinburgh Road, and is funded through the Housing Accelerator Fund with a goal of 35 affordable units by the end of 2026. Both documents are drafts open to feedback.
- Attachment-1 Draft Official Plan Amendment.pdf
- Attachment-2 Draft Community Planning Permit By-law.pdf
- CPPS Public Meeting Presentation.pdf
- Correspondence - Sonya Ogilvie.pdf
- Correspondence - Matthew Brodie.pdf
- Correspondence - Andrea Bidgood, Guelph Coalition for Active Transportation.pdf
- Correspondence - Scott Frederick.pdf
- Correspondence - Emily Elliott, MHBC Planning.pdf
- Correspondence - Tyler Black, Wellington Dufferin Guelph Public Health.pdf
- Correspondence - Jay Wall.pdf
- Correspondence - Kevin Thompson, SV Law.pdf
A summary is this site’s description of a document, not the City’s. Open the document before relying on one.
What was said
8,301 words from the meeting recording, transcribed automatically. Times are from the start of the recording.
Read the debate(click to open)
41:06and the draft community planning permit by law. And so we're going to have some presentations from
41:13our staff that have been working on this. No delegations signed up in advance, but there is
41:19some correspondence that was attached to the agenda. So this is a unique sort of planning tool
41:27opportunity for the city that other cities have started to use and look into. But we're going to,
41:32as I say, hear from our staff first as a presentation to sort of lay out the groundwork on that.
41:39Get some feedback from us and then staff will take it away from there and come back at another time.
41:45I'll call staff up. I just don't know if I'm going to anybody for opening remarks before we do the
41:50presentation. Nope, we're good to go. All right. So Brenna McKinnon is the project manager and Justine
41:56Giancola. Am I saying that right? Really? Thank you. From Dylan Consulting is here.
42:03We'll just turn it right on over to you. Go right ahead. Thanks.
42:26Good afternoon, Mayor Guthrie, members of council, staff and members of the public.
42:32This is a statutory public meeting on the draft official plan amendment and community planning
42:39community planning permit bylaw for the Stone Road, Edinburgh Road area. And it is a bit of a
42:46mouthful. So we'll keep saying community planning permit system or community planning permit bylaw
42:53rather than truncating it to CPP as we planners tend to truncate and shorten everything.
43:02My name is Brenna McKinnon. I'm a project manager in planning services. I'm joined by a member of
43:07our consulting team for this project, Justine Giancola from Dylan Consulting. And we will be
43:12taking you through the project to date. First, we will be giving you a background on the project
43:19followed by a summary of engagement to date. Next, we'll give you a brief overview of what a CPPS is
43:26and a summary of the benefits of a community planning permit system. Finally, we will discuss
43:31what the next steps are for this project. This project is part of the city's eight commitments
43:46of the Housing Accelerator Fund action plan, which is the 21.4 million dollars granted by the
43:56federal government just, I believe, almost a year ago. The city selected the Stone Road, Edinburgh
44:03area as well as the downtown secondary plan area as areas to help meet its aspirational planning
44:09goal of our housing target of 18,000 units by 2031 as set by the province. In late spring 2024,
44:17the city initiated the community planning permit system pilot project for the downtown Stone Road,
44:23Edinburgh Road areas to help advance this goal. The pilot project has the goal of helping to
44:29achieve the creation of 35 affordable housing units. The project is advancing in two phases
44:36with the current focus on the draft community planning permit bylaw and official plan amendment
44:40for the Stone Road, Edinburgh area that is before you today. The second phase will be the development
44:46of a community planning permit bylaw for the downtown secondary plan area once the downtown
44:52height study is complete. To date, there have been a variety of engagement events, including four
45:05open houses with two held in person, one in October 2024 and one in November 2024 at Priority Part
45:14Public School. There have been two virtual open houses, one on November 21st, 2024 and as late as
45:21last week on January 14th, 2025 via Zoom. We've also been at a variety of pop-up events, including
45:30the Shelldale Center, Guelph Farmers Market and Victoria Road Community Center alongside the housing
45:37affordability strategy pop-up events. In addition, there was also a mapping activity and survey
45:43available on the Have Your Say project page. Feedback we received during these pop-up events and
45:50others included transportation and accessibility, so looking at investing more in bike lanes and
45:57pedestrian spaces, improving transit options and addressing traffic congestion and road safety,
46:04parking and traffic management such as reducing large parking lots for other types of development,
46:11implementing red light cameras and better lane markings and balancing parking needs for all users.
46:16Urban design issues such as reflecting Guelph's character and its qualities, creating unique
46:21spaces that fit the local context, promoting durable high quality building materials and
46:27designing to the human scale. Other items include community involvement in this process, providing
46:35clear information on the costs and benefits of such a program, looking at a shift to multi-use
46:43commercial and residential buildings in the area, repurposing some retail spaces for housing or
46:49community needs, of course looking at affordable housing affordability, developing a diverse
46:57affordable housing type and style and promoting higher density housing and addressing issues with
47:03student rentals. On safety and infrastructure again, looking at improving street designs for
47:10pedestrian and cyclist safety, slowing down traffic for safer streets, ensuring accessibility
47:16for all, and finally on community and public spaces, creating a more walkable main street,
47:24so particularly around Stone Road, with family and pet amenities, increasing green spaces and urban
47:32art and supporting small businesses with pop-up areas, better streets, scapes and landscaping.
47:39I'm going to turn the presentation over to Justine to provide information on what a community
47:45planning permit system is, how the process works, and how a community planning permit system
47:50can benefit the City of Guelph. Thank you, Brenna, and thank you, Mayor and Council, for having me
48:02here today. So a community planning permit system is a land-use planning tool available to municipalities
48:11in Ontario, and it was previously known as Development Permit System, or DPS, and so some
48:19municipalities that have gone forward with this tool continue with that language, Development
48:23Permit System. It is interchangeable with Community Planning Permit System. It offers an
48:29alternative way to regulate land uses within a municipality and can be applied to a very specific
48:36area or to an entire municipality. The current project aims to implement a community planning
48:45permit system specifically for Stone and Edinburgh and then for the downtown area,
48:52and when you do have a community planning permit system, when you desire to use one, you need
48:58official plan amendment that forms the enabling policies, as well as a community planning permit
49:04by-law, which ultimately replaces a municipal zoning by-law for that subject geography.
49:13The tool itself has the ability to streamline development approvals, and one of the ways it
49:18does that is by combining zoning, minor variants, and site plan applications into a single development
49:25application process and a single review. That review period is tied to a 45-day review period
49:34compared to those current separate processes that can be upwards of 180 days.
49:41The system itself is more flexible, so municipalities have been asking for a while to have
49:48the ability to do conditional zoning. This tool provides an ability to do that, where you can
49:54indicate criteria conditions where something may be permitted or a certain standard may apply.
50:04So it does allow some flexibility and support local objectives, such as affordable housing,
50:10sustainable design, and environmental protection. This project will create a new land-use planning
50:16tool for the city, is the first time the city is using this tool and is intended really to accelerate
50:22housing supply while providing predictability and stability for the development approvals.
50:29Completing this work will fulfill a commitment made through the receipt of the Housing Accelerator
50:35Fund. So on the screen you'll see a little bit more about the process, the current process,
50:43those separate concurrent processes versus a community planning permit system on the bottom
50:48half. And when you're using a community planning permit system, the draft community planning
50:55permit by-law, which is now being released and was subject to a number of comments in the
51:03open house last week, defines what is permitted and what development standards are applicable to
51:11the subject area. It's often organized into multiple classes, and so in the draft by-law
51:19we have three classes of applications that help organize how an application may need to be processed
51:28and what support studies could need to be required. So class one is intended to capture
51:35applications that meet all the requirements of the by-law. In this case it would be approved by,
51:42based on the draft by-law by the general manager of planning and building services,
51:46or a delegate, and the application still could have complete application requirements in terms of
51:53some support studies and any conditions of approval could still be added on to that application,
52:01and that would be for all development application classes. A class two captures applications that
52:08generally meet the overall by-law standards but requires some amount of variation within the
52:15staff variation threshold established by the by-law itself. So you might think about this as
52:21similar to the minor variance process, but in this case a class two application would be approved by
52:27the general manager of planning and building services or its delegate and be required to
52:32demonstrate adherence with criteria established by the by-law itself. A class three application
52:39captures all applications that generally meets the by-law standards but requires a variation
52:47that's beyond that class two threshold established by the by-law. And in this case a council or committee
52:53approval would be required. Critical to communicate is that anything that would require an official
53:01plan amendment is outside of the ability, this implements the official plan so it's outside
53:06of the ability to deal with through this, and that building permit is also not part of this process.
53:13And lastly anything that requires subdivision of land is also unimpacted by this process.
53:23In terms of why a community planning permit system for the city of Guelph, Guelph's housing
53:29housing affordability strategy targets 18% or 2,640 units of the new ownership homes to be
53:38affordable based on the provincial bulletin benchmark of 398,000 for an ownership unit
53:45or 1,160 to 1,695 for a rental unit depending on the size number of bedrooms part of me.
53:55To help achieve this the city is looking to streamline the development approvals process
53:59and provide a framework to permit additional density which is where the community planning
54:05permit system can come into place. A community planning permit system is a planning tool that
54:11allows the municipality to facilitate additional heightened density in exchange for what's called
54:20facility services and matters but what you might think of as community benefits such as affordable
54:25housing. In a strategic growth area the tool helps to establish clear yet flexible development rules,
54:34facilitate growth while reducing the likelihood of appeals which in turn supports consistency
54:40in implementation of the vision for the area. It helps speed up development approval timelines
54:47and secure community needs such as affordable housing. Specifically for Stone and Edinburgh area
54:57the plan envisions a compact urban area with vibrant main street affordable housing parks
55:03community spaces and strong transportation connections to support the active transportation
55:09and bus routes aiming for a minimum density of 160 people and jobs per hectare by 2051
55:19and with that I will hand it back to Brenna to go through some of the specific elements of the draft
55:23plan. This is a map that shows the boundaries of the community planning permit bylaw area
55:36as well as the revised boundary of the Stone Road Edinburgh strategic growth area which is why
55:42one of the reasons why we need the Official Plan Amendment. Through the drafting of the Official
55:47Plan Amendment it was determined that a few properties could be redesignated through the
55:52Official Plan Amendment to facilitate and accommodate a broader range of uses particularly
55:57residential. This Official Plan Amendment is attached to the report and is a number of pages.
56:06So just to highlight some of the lands I know I don't have a pointer but that are identified in
56:13the report itself. There are a number of parcels of lands that we have looked at re-designating
56:19through this through this process. So number one the Official Plan Amendment will amend the policies
56:24in the Official Plan to enable the ability to have a development a community planning permit
56:29system. Number two we're looking at changing the boundary of the strategic growth areas identified
56:36in the Official Plan Amendment to include a broader area. Currently it only goes in and around Scottsdale
56:42and we've brought it out to college in the Hanlon and three to the site specific re-designations.
56:49There are a number of institution there are two institutional uses on either side of Torch Lane
56:54that are currently designated for institutional uses and we are looking to consider
57:01amending that designation to permit higher density residential uses on those properties.
57:08There's a facility right now in the Prairie Park Town Home Unit complex that is basically a kind of
57:15a community center. We are looking to re-designate that property to permit some residential higher
57:22density residential uses there as well and there are a number of single detached homes
57:28that front onto College Street that are currently low density residential in the plan
57:34in the current Official Plan and we're looking to re-designate those up to medium density residential.
57:47As Justine said a community planning permit bylaw implements the Official Plan and replaces the
57:54existing zoning bylaw for the area. In Guelph since the Official Plan through OPA 80 and the
58:03Zoning Bylaw Amendment have been recently updated in most cases the community planning permit bylaw
58:09carries forward the existing permissions and uses and setbacks and everything else from that 2023
58:16bylaw. As shown in the figure the area along Stone Road is still mixed use corridor and is aligned
58:24with the City's Official Plan allowing such uses as commercial office retail and medium to high
58:30residential development. The area along Edinburgh and some parcels along Janefield are high density
58:37residential permitting apartment buildings as well as convenience and commercial uses.
58:41The corner of College in Edinburgh is a neighborhood commercial site as per the Official
58:46Plan allowing commercial retail and mixed use residential buildings so a number of these things
58:52aren't changing. There's also parks in open space of course a significant park public park behind
58:58the mall and a small silver of the existing natural heritage system along Edinburgh adjacent to
59:03the University lands that have been carried forward. The remainder of the area is low to medium
59:10density residential permitting a range and height of residential buildings. The feedback received
59:23today and through other engagement activities moving forward will be taken back and reviewed by
59:28staff to be incorporated into the final version of the community planning permit bylaw. Comments
59:34and concerns received and posted with the revised agenda on Friday included such items as providing
59:40adequate bicycle parking infrastructure and public notification of the community planning permit
59:46application. A planning consultant on behalf of a property owner did note some site specific
59:53concerns and we anticipate meeting with the consultant and the property owner to discuss further.
59:59We do request that any additional comments on the draft bylaw and draft Official Plan amendment
1:00:04be submitted to staff no later than January 28th. It is anticipated that the final
1:00:11community planning permit bylaw and Official Plan amendment will be brought to council
1:00:16on April 8th. For any additional comments or questions please feel free to reach out to me.
1:00:23My email is on the screen. Thank you for your time today and we look forward to answering any
1:00:30questions you may have. Great thank you very much to the both of you for your presentation.
1:00:37Just let me confer with the clerk for one moment. I'm just going to choose to do the
1:00:47potential call in for anybody because I know we had no one here signed up but is there anybody in
1:00:53the room that wanted to talk to about this item at all before we move on? No okay but I will put
1:00:59up the number on the screen. It's 519-837-5603 and we'll just leave that up there for three,
1:01:08four minutes or so just to see if anyone wants to call in on this before we turn it back to us
1:01:12to ask questions of staff. Okay thank you. Okay thanks everyone. I'll just call the meeting back
1:04:38to order. We didn't have anybody want to call in on that so it is back to us as a council.
1:04:45As I indicated and as our staff and consultant have indicated it is a motion to receive.
1:04:54May I at least just get that on the floor would that be okay? Councillor Busuttil and Downer
1:04:59will do that part for us. Thank you. So just to confirm this is the moment we've done this before
1:05:06where you're looking for our feedback and it's a takeaway. Okay so let's start. Who's got feedback?
1:05:15I'll start with you Boussatil then Karan. Thank you very much and thank you for the presentation
1:05:21and through the mayor. I'm sure it's my spatial understanding here. I just had a question about
1:05:27it's schedule B the colored map of the area. I'm curious about the two schools that are on
1:05:34the property in that area and the green space that's Park Space so Prairie Park and Rene Goupi.
1:05:43I believe share a park space behind their property and if you I just don't see it in here. I see the
1:05:50yellow that is low density residential. I'm just curious about that if I'm in the wrong place
1:05:55in the wrong street in the wrong area and then I have a follow-up. Through you Mayor Guthrie
1:06:02there is a trail in behind the schools you're correct but I believe it is owned by the school
1:06:07properties and is not a you know a function of the of the city of Guelph's Park system
1:06:12but it is connected there and we can see it and we did hear from the community that they would like
1:06:17that to be enhanced. Thank you and just a clarification because you've then indicated that area as low
1:06:23density residential and so are you suggesting that the school board property is low density
1:06:29residential to be developed? The designation is what is currently in the in the official plan so
1:06:37there's schools typically do have a residential designation on them but their zoning would be
1:06:43institutional. Sorry rather than institutional. Their zoning would be institutional but their
1:06:50designation would be residential. Got it thank you and my second question is earlier in the slide
1:06:54presentation and I know I was asked about this the sorry just lost it the one that shows the what is
1:07:04a CPPS and you've got current approval process and the CPPS process. I'm wondering if in when
1:07:13you do more work on this if there is a third slide that shows about the public process in here if it's
1:07:20impacted if it's not impacted and I know that individuals when they're going through planning
1:07:25processes they don't find out until the very last minute you know what's going on and so on
1:07:30and a little bit concerned just about the Titan time line by the time so from a public engagement
1:07:38for a public information if there should be another slide that is and this is the process and the
1:07:44opportunities for the public to get information to be engaged provide feedback because it's compressed
1:07:51in there. We can certainly take that back just in terms of context upfront engagement
1:08:02when establishing the rules of development is a really important point for public engagement
1:08:07and that is where we're at right now but we can certainly take that back in terms of how to
1:08:11communicate effectively communicate the notification requirements. Thank you just a clarification
1:08:18through the mayor so what you're saying is that the only opportunity is the CPPS policy framework
1:08:24and if I have a residence in the area I'm no longer going to receive a notification saying come out
1:08:29to this meeting or anything like that this is it and the public will only have an opportunity here
1:08:35in this policy framework rather than the on the ground.
1:08:42Through you the mayor so thanks for the follow-up question and to clarify so in terms of the
1:08:49legislative requirements there are no minimum notice requirements within the legislation
1:08:56as it relates to when a community planning permit bylaw is in effect. However the city of Guelph
1:09:05has proposed a number of notice requirements through this bylaw itself that go above and beyond those
1:09:13there's no statutory requirements but the city has gone above and beyond to recommend
1:09:19through the community planning permit bylaw notice requirements which are shown on figure
1:09:26uh I believe it's 1.1 let me just make sure I got the right one here um actually table 1.1
1:09:35which shows the class and the corresponding public notice procedures which we have received some
1:09:42additional feedback on as well. Thank you. Great thank you councillor uh Koran and then Downer.
1:09:51Thank you and thank you for the segue Councillor Bousetil because my feedback
1:09:55was specifically related to table 1.1 um I know that this is just the feedback stage so I'm not
1:10:03making a motion but my feedback is that we for for the class two and class three where it does not
1:10:11exactly conform to the zoning that we've established that we add signage to one of the notice
1:10:18required to the notice requirements I know the city website and is is already on that and that it
1:10:23is above the minimum um but it's not something that people who live in the area would be looking
1:10:29for they wouldn't be going to the city website to see whether or not there's a live application so
1:10:35signage on site and again I don't know if we would specify in the bylaw what that signage looks like
1:10:41I'm not talking about a big zoning amendment sign the big billboards that we put up but some kind
1:10:45of on-site notification that directs people to the city's website. We're looking to break
1:10:53through uh Mayor Guthrie we're looking to bring that back we have done a quick municipal scan to
1:10:58see where other municipalities are in their community planning permit systems and what types
1:11:04of notification and signage go up and it's it's it's sort of variety um and we have heard from
1:11:10members of the public that they would like to see signage on the property so it's something we will
1:11:14consider. Okay great and just for my own clarification um just so that it's on the public record I
1:11:22know that when we zone and we zone for types of residential medium low and high we're not people
1:11:28zoning can you there were some there was some commentary that uh alluded to a certain demographic
1:11:35group in the in the presentation I just want to make sure that we're not people zoning in the work
1:11:40that we're doing today for a certain demographic. No we are not. Thank you Councillor Downer than
1:11:50Guller. Thank you so ditto to the questions around notification I think that I've heard a lot of
1:11:57feedback about that but I was going to ask I know the financial implications are coming with the final
1:12:01report more detail on that but would we be requiring more staff because I'm just assuming that things
1:12:07are going to be moving a bit faster that we're going to need to have the capacity to deal with that.
1:12:11Through the Mayor to Councillor Downer um we don't anticipate a rush on applications okay we think
1:12:20this will be relatively small we already are talking to some developers in the area and have been
1:12:25for a while so we don't believe this will change our our planning process and the um ability for
1:12:30staff to manage the applications that come in over the next 30 years. Okay great so any other
1:12:36thing I would say is like there's um quite a good comprehensive letter from Public Health and I
1:12:42think they've made a lot of very good points um in there that I would like to see taken into
1:12:47consideration I won't highlight which ones they're all generally pretty good thanks.
1:12:54Thank you Guller and then O'Rourke. Thank you through your worship. I wanted a clarification
1:13:08if I could from staff one of the letters mentioned that um four places were not allowed but but I
1:13:13didn't see that in the document so I just wanted to clarify in in this area would a unit with two
1:13:21additional uh with with up to you know like four units in one residential property be allowed?
1:13:30Through you Mayor Guthrie it was really just a timing issue so the uh the notice the appeal
1:13:37period for the four units was still uh still out there prior to the publishing of this uh CPP
1:13:45bylaw so the CPP bylaw will be updated to include the ability to have four units in the in this area.
1:13:53Thank you for that clarification I appreciate that. I also um I just just to second what
1:13:59Councillor Caron said about the the public notices I am interested in seeing those with
1:14:06regards to to the letters that we got many of them talked about bicycle parking spaces.
1:14:13Is this something that you would be looking at to to explore adding those additional larger bicycle
1:14:18parking spaces? Through you Mayor Guthrie it is certainly something we can consider and try and
1:14:25try to address uh currently the uh my understanding is the the parking in general is is still under
1:14:33appeal with the overall comprehensive zoning bylaw so it's it's certainly something that
1:14:40we can talk to GCAT and others about on how to facilitate enhanced bicycle parking and
1:14:45parking infrastructure for the the cargo bikes that they noted. Perfect thank you very much for that
1:14:52and my last question through your worship is about the the two letters that we receive from
1:14:57developers in the in the agenda talking about concerns about whether this would in fact
1:15:05encourage development or not could I just get confirmation from staff you mentioned that you
1:15:09have spoken to some developers so from your perspective are there developers that that do see
1:15:15this as a way to enable more units being being built? Through you the mayor um so we have received
1:15:29a number of a couple letters from developers one was more a home builders builder association one was
1:15:36more representing individual developer interests and as it relates to overall the tool and facilitating
1:15:45growth this is absolutely a tool that we think can streamline development approvals and reduce
1:15:52the efforts on behalf of the development industry. There are a few kind of specific things that were
1:15:58mentioned in both letters would you like me to take that down to a more detailed level and respond to
1:16:05those but maybe maybe not here but maybe when it comes back if we can have a little more information
1:16:10about that to address those concerns I would appreciate it absolutely thank you very much
1:16:16that's it for me your worship thank you councillor O'Rourke thank you mayor Guthrie through you to
1:16:24staff just to piggyback I would actually like to know because that's where I've scrolled down to
1:16:29we're hearing concerns from developers that this adds complexity that they didn't have enough time
1:16:35to go through the the cpp and we're at the stage of consultation so I'm guessing there's time but
1:16:42I'm wondering if you want to respond to the the two letters one from the home builders association
1:16:48and the other from wood development company and and how we're going to work through that because
1:16:52they're the people who are going to build right so how do we make sure that they really believe
1:16:57this will be a streamlined and attractive process thank you for the comment I through you the mayor
1:17:05to start off um Brenda did mention that there will be a number of ongoing one-on-one meetings
1:17:09and so I think um to continue to get to the root of some of the issues and concerns raised um that
1:17:15will be a key step um in terms of some of the the key uh comments around adding complexity
1:17:21um there was a comment around uh a concern around so currently um any development that's 10 units
1:17:27or less is exempt from site plan application and through a community planning permit system
1:17:33there is an ability for the municipality to have development control and take
1:17:40you know letters of credit and and securities for development even if it is 10 units and under
1:17:46so that was one of the things that was raised in terms of concerns um one of the pieces more
1:17:51specifically is around the need for additional studies so as part of the implementation of this
1:17:58new tool um there is an ongoing process to look at um you know this is a change management exercise
1:18:06and there will be a need to update internal processes as well um the official plan does
1:18:13identify complete application requirements and things a municipality may request um the develop
1:18:19the comment was about the need for planning justification reports um I think something
1:18:25that we can take back is um as we look at applicate uh using the tool whether if an
1:18:31application comes in and meets all the requirements under class one do we really need to ask for a
1:18:36planning justification report um or perhaps it can be scoped for those variations in a class two
1:18:43so certainly some of that feedback around how best to implement the tool and make sure that um you
1:18:50know the asks are reasonable um I think there are opportunities for that um there was a second
1:18:56point highlighted around permitted and discretionary uses um and uh to provide context the um current
1:19:04zoning bylaw uh does have a number of instances where um a use um uh does have a condition associated
1:19:12with it and for the purposes of this draft bylaw we wanted to keep things very similar and we carry
1:19:18them all forward um and did identify anything that had a condition um as a discretionary use
1:19:25I think based on the feedback and conversation there there is an opportunity to look back at
1:19:29some of those and say is that extra subjectivity necessary could we in fact make it permitted
1:19:36subject to that same condition um I can provide an example if I'm getting too arbitrary would that
1:19:44be helpful okay um so for example um uh apartment dwelling is is um permitted in your zoning bylaw
1:19:54in a mixed use corridor um it well it's permitted in your um designations in your mixed use corridor
1:20:01and in your current zoning bylaw um we've carried it forward as a de discretionary because um in
1:20:09mixed use corridor it's not permitted on the main floor um we may be able to look back at that and
1:20:16say is that subjectivity necessary or could we in fact say it's permitted just not on the main
1:20:24floor and we don't need to push it to a class two so there might be some opportunities to um kind of
1:20:31as we get into the details of applying this to two sites and having these conversations with
1:20:36specific developments about their interests and their site parameters um to to um uh look at the
1:20:43what is discretionary versus what is permitted and make sure that it is meeting our overall
1:20:48objective of streamlining development approval and clarity okay thanks better for you to square
1:20:56that with them than for me to understand but I am trying to understand and and this has been uh
1:21:00it's been a little bit challenging so through you Mayor Guthrie I'm going to come back to a higher
1:21:04level higher order question um your slide four in the presentation says uh the goal is 35 housing
1:21:11units it only says housing units am I correct to assume we want affordable housing units
1:21:17in this area okay and so why so few of them so 35 were only identified in the housing accelerator
1:21:33fund so that's in the next two years um beyond the two years we expect more but the 35 was uh to the
1:21:40end of 2026 okay that's helpful um and through you Mayor Guthrie I've got a bunch to just sort of
1:21:49download um the feedback yeah so when we did the comprehensive zoning bylaw we had two years like
1:21:57go through and see what was what is can you just give me a high order of what the key differences
1:22:03are between the the community permit plan zone and those changes and the comprehensive zoning
1:22:11bylaw that I thought I had a handle on so what are the big changes um through you the mayor um so we
1:22:21have uh picked so uh there are a few specific subject properties where uh redesignation is proposed
1:22:29and you will find those in your official plan amendment um figure I believe it was two or B
1:22:36let me find that for you you will find those highlighted on figure two of the official plan
1:22:51amendment so those are specific sites where our redesignation is proposed um as relates to the
1:22:58rest of the area um we are implementing um we have picked up your existing zoning standards
1:23:05and put them into a community planning permit bylaw the the fundamental differences here is that
1:23:13in by being able to deal with potential variations through this tool there's an ability for you to
1:23:20say um uh what might be a staff variation so um if you have a front yard setback you can say
1:23:28whether you're going to allow some staff variation in certain circumstances or parameters um so uh
1:23:35on table um 6.1 you'll find permitted and discretionary uses um discretionary use
1:23:50is a term um that is not from your current zoning bylaw that is getting picked up because of that
1:23:55ability to provide flexibility and and um through this tool um on table 6.2 the development standards
1:24:06are um very much exactly as they exist in your current zoning bylaw um the class two staff variation
1:24:13threshold that limit that um is unique to this tool and is um something that you would want to
1:24:19look at and uh and make sure you understand and then the last very important item is the ability to
1:24:26do facility services and matters in exchange for height and density and that you'll find on
1:24:32table 1.2 where we're looking at um uh where some additional height and density could potentially be
1:24:40um uh provided for in exchange for affordable housing units and that is something that you
1:24:45can't do under current zoning bylaw um Brenna was there any other key highlights you can think
1:24:56about facility services and matters a little bit like the old density bonusing yeah so uh or
1:25:02inclusionary zoning in some regards a little bit because uh what we're looking at and uh
1:25:09are working through right now is um a financial analysis we just recently uh initiated that work
1:25:17with with Watson uh associates and and Dillon to determine you know what percentage of those of
1:25:25those residential units that are being proposed that are new would have to be affordable housing
1:25:29units in order to reach that 35 uh units unit goal for instance so uh under the old density
1:25:37bonusing or section 37 of the planning act it was um and Mr. Ormiss developer if you want to have
1:25:44extra extra height you have to provide uh could be affordable housing units could be public art
1:25:51it could be any number of things this is uh facility services and matters relate specifically to
1:25:55height and density so it's a proportional relationship or an exchange for that extra height
1:26:00to get the units or alternatively what we're looking at is is cash and lieu of those affordable
1:26:05housing units that could go into the affordable housing reserve and and look at other lands
1:26:12so through you merga three that's my next question to staff uh is Watson looking at that
1:26:17cash and lieu policy how do we assure ensure it's a robust enough amount uh because we hadn't updated
1:26:24the parkland dedication for 30 years and and we're short in terms of what it costs so
1:26:30what does that cash and lieu policy look like and how do we make sure we have enough
1:26:38through you the mayor uh we have Watson and associates doing some financial analysis currently
1:26:45to explore our development proformas of a couple subject sites um and scenarios within this area
1:26:51and um part of that analysis is to provide guidance and direction on a cash and lieu level that would
1:26:57be appropriate for this area and as soon as that's available we'll be putting it on um the
1:27:02miss pally's website um and and sharing that okay um thank you my next question may i go through
1:27:11through you to staff is the uh plan refers to 601 scott's dale they have an approved development
1:27:18application so does this speed up their process do they look at a new process how does that work
1:27:22when this proposal applies to a property that's currently under development
1:27:30so i believe that may be the only active application we have we do have some that are already along
1:27:36jane field they're in the building permit stage but they already have gone through the zoning
1:27:39process 601 scott's dale's gone through the zoning process and they're in for site plan so i i think
1:27:45they'll be ahead of this process okay terrific um and just a question around um
1:27:53um page 170 line 2 says dwelling units are not permitted in the basement or the first story
1:28:00of a building a lobby amenity space and residential components of live work units are permitted so i'm
1:28:05just wondering why that is my in-laws live in a lovely building in toronto there's a concierge
1:28:11desk there's the you know elevator bank and then there's apartments on that first floor so i'm
1:28:17wondering why we wouldn't allow apartments on the first floor or the basement especially at the
1:28:21grade allowed it so thank you through you the mayor um that is directly carried over from
1:28:29your current zoning bylaw in terms of a requirement force lands within certain areas to facilitate
1:28:37more activated first floor uses such as retail and other non-residential uses and to maintain
1:28:46the commercial function in the long term so i'm given that number of these sites that are
1:28:51muc are entirely commercial today the desire would be to maintain a commercial function
1:28:58for the associated neighborhood and area as well as the residents within that mixed use building
1:29:05in the long term okay thanks and the america if i can just flag a couple other observations
1:29:12i'm going to see clarity separately around uh parking requirements for additional residential
1:29:18dwelling units how the the first one the third one the fourth one work um page 34 of our package
1:29:28it says section 1.4.1 says repeal of existing bylaws within cpp area so i don't know if it should
1:29:34say planning bylaws or all bylaws you may want to take a look at that um i have a concern
1:29:41we'll shock no one about parking uh 5.5 section c says apartment buildings mixed use dwellings
1:29:48with less than 20 dwelling units are not required to provide visitor parking spaces
1:29:53i and that works if it's in a mixed use and there is other spaces where they can be but
1:29:58i have a concern if you have a you know 16 units and zero visitor parking it says in multi-unit
1:30:06buildings with four dwelling units or less if no legal off-street parking space can be provided
1:30:11for the existing dwelling dwelling unit then no parking spaces are required so i understand that
1:30:18in a historic downtown context where there is no parking i'm not sure i understand it in
1:30:25this part of the city where if you're redeveloping a site uh for residential you should be able to
1:30:31provide some on some off-street parking so i i just um a concern about mine has always been to
1:30:38provide enough parking um i don't like maximum widths on garages anywhere in the city i think
1:30:45they should build what uh what is needed and oh last one is a real question it says within the HDR12
1:30:55precinct this is for apartment buildings the definition of a lodging house as defined by
1:31:00this bylaw does not apply and i'm just curious why that is it's a carryover too from from the
1:31:12existing zoning bylaw okay i just didn't understand it the first time around i guess and maric gots
1:31:17from my last question is uh was there a question you expected us to ask that we have not asked
1:31:23and if so what is that question through the mayor thank you for that already long list of questions
1:31:40all right last here i have is councillor Caton please thank you through you mr mayor to staff
1:31:50so this is just a comment i know this is not the biggest part of this um but i was going through uh
1:31:56on i think it's page 85 and then a couple under that in figures 4.7.5 and beyond um i just this is
1:32:08a request to add in some ramps in some of these pictures and i know that we can't enforce them
1:32:14but i think that the more that developers see them in the documents it kind of makes them feel
1:32:19more possible so that we end up getting more accessible options in these medium density areas
1:32:26thanks great thank you okay before we call the vote um i will just quickly ask my questions then
1:32:40um i just want to say i think it's really important that the performers and the financial analysis
1:32:46is getting done you have no idea how many times i hear it doesn't pencil and so you can say well
1:32:54here's the height we think we should have on this land but if it doesn't pencil you're never going
1:32:59to get anything so the financial analysis has to be done to actually start to trigger thoughts of
1:33:08actually oh i can actually now move forward with this because it's starting to pencil so that those
1:33:13types of um that type of information will be very important um you gave a really good example that
1:33:20i was going to bring up about the site plan issue with 10 units or less but how it could be implemented
1:33:27if we had it under this regime i just want to stay as a blanket statement anything anything at all
1:33:35in my view that hinders or adds new regulations is a non-starter for me so if we should not be adding
1:33:45anything to this to these areas that is going to become a hind a hinder or a hurdle where under
1:33:53another regime just on the other side of the road it wouldn't apply so let's try to really think about
1:34:00about about that if we can um the last question i had is when are these types of bylaws reviewed
1:34:09is it a trigger like every five years or or i just don't know if there's something like that i
1:34:17wouldn't mind an answer i'm um well not through you directly to you um fantastic question so um it
1:34:25would be typical that um uh you would want to review it every five years at least um however
1:34:32in talking to and working with other municipalities that have used this tool um because it is a new
1:34:38tool for a municipality um it's not um it is likely that you might have some uh kind of staff um
1:34:46you know minor technical uh adjustments within the first year or two of things that you know need
1:34:52to be tweaked a little bit in terms of implementation um but one thing that um is helpful from uh policy
1:34:59stability perspective is that um there isn't a um there's no ability for a proponent driven
1:35:07amendment to the community planning permit bylaw within the first five years unless there's a
1:35:13council resolution to do so so maybe you could just staff could bring back some flavor on that like
1:35:22do we treat it as a living document that can have some delegated authority on the administrative
1:35:27technical side for updates but also is there flexibility early on if we're seeing that there's
1:35:34a problem that you know staff could bring something to council to say like hey we we need to we need
1:35:41to amend this to make this easier whatever that thing is so um it might be need to have like a hard
1:35:47a hard fast rule that hey every five years we're for sure going to review this in its entirety
1:35:51but also treat it that it's new enough and new with other municipalities that we can also
1:35:57trigger some changes if if we're finding that we need to do that um I will say in some of the
1:36:01research I've done with other communities that have done this some of them have had charts where
1:36:06they've kind of laid out the all the benefits of what what's happened and then the next column
1:36:12over is like oh some of the some of the growing pains like they're they're very transparent about
1:36:16some of the stuff that hasn't exactly worked out or whatever so um if you can even I can try to
1:36:21find that too I think it might have been Peterborough or Waterloo I think it might have been Waterloo
1:36:25I can't remember um that that kind of information might even be good to to put in the final thing
1:36:31just to show where some of the best practices are in some of these other communities that are a little
1:36:35bit ahead of us and then the final question I had was just on I don't mind the what Councillor
1:36:40Caron was saying and even Councillor Boussatill was saying around like engagement with the community
1:36:45or whatever um signage things like that just from an information point of view but but I guess my
1:36:50question is and then what so let's say there's a sign that goes up that says and I know there's the
1:36:56three sort of categories right like level one level two level three so let's say there's a level one
1:37:02or you know category and there's a sign that goes up and then the community drives by walks by
1:37:07bikes by and sees the the thing and then then what like is it it's just for information right it's
1:37:14not for them to be like I object because the whole point of this whole regime the whole point of all
1:37:22this regulation is to actually make things upfront knowing to applicants of exactly where they have
1:37:28to meet and if they meet it they can put a shovel on the ground they can just keep they can keep
1:37:32going so I just want to make sure that you know yes I don't have zero problem with informing people
1:37:38and making sure that people are in the know that's not a problem but it shouldn't also trigger
1:37:44like all of a sudden tactics to delay so am I right in how I'm describing that um yeah so there's
1:37:52no third party appeals for any application that fits within the the bylaw only like if it needs
1:37:59a bylaw a mentor then in an open process again in a class three where something would come to
1:38:06council it would be typical that you would you could take delegations and feedback from members
1:38:12of the public yeah no issue with that level three yeah yeah okay those are there my my only points
1:38:20please just look well you know please just look at it through a lens of this is supposed to make
1:38:24things easier faster very upfront transparent everyone knows the rules of engagement as I would
1:38:32call it um so you know take to heart some of the the feedback that you got I would also just publicly
1:38:39say they're not in the room but maybe they'll listen to this later on um that for those that have
1:38:43been writing in you know I would suggest like this is your moment between now and April much before
1:38:49April to please engage with our planning staff and our consultant and others around some of the
1:38:54issues you might have um I but I think uh I think that there's a reason why this is an available tool
1:39:02there's a reason it's to make things easier so let's please make sure that we that is the end
1:39:07result is a policy that makes things easier um okay with that I'll call the vote is anyone against
1:39:15staff and us receiving this information nobody okay that's great thank you very much for the
1:39:21presentation and the work you're doing that's great um with that we're going to take a break
1:39:28for exactly 55 minutes so um we have one extra item and then that's it it's the 115 Watson Parkway
1:39:37north proposed uh zba file uh as everyone knows that's uh a very important site for
1:39:46counselor Gibson and uh kate so they will certainly be back here for six o'clock
1:39:52for for this one and I hope to see everyone else back here for that one too so we'll take a break
1:39:56and we'll start that item in 55 minutes all right good evening everybody just if I could ask
Automatic transcription is imperfect. Treat quotes as a guide and check the recording before relying on exact wording.
The motion, the vote and the debate come from the City of Guelph’s published record, reproduced rather than interpreted. The document summaries above are the exception: those words were written for this site.