Council Planning · July 14, 2026 · Item 7.2

Urban Design Master Plan (UDMP) for 64 Duke Street “Mid-town Village” Concept Plan in Attachment 1, be supported.

Main motion under the agenda item Proposed Urban Design Master Plan (UDMP) Application for 64 Duke Street - Mid-town Village - 2026-339

Carried (12 to 0)

12 in favour, 0 against — unanimous

What was voted on

The motion in its exact words, as recorded in the minutes.

That the Urban Design Master Plan (UDMP) for 64 Duke Street “Mid-town Village” Concept Plan in Attachment 1, be supported.

Moved by Councillor Klassen, seconded by Councillor Goller.

How the room voted

In favour (12)

  • Allt
  • Billings
  • Busuttil
  • Caron
  • Caton
  • Chew
  • Downer
  • Goller
  • Guthrie
  • Hauser
  • Klassen
  • Richardson

Who spoke to it

Scott Plante, Project Manager, Planning Development, presented on the Proposed Urban Design Master Plan (UDMP) Application for 64 Duke Street - Mid-town Village. The following delegates spoke: Susan Frasson Tim Smith Ian Panabaker Mike Darmon Michelle Bowman Barbara Mann and Scott Frederick The following delegates did not speak: Ken Thompson

What council was given

The staff reports and correspondence attached to this item. The summaries are written automatically, so you can tell what a document is without opening a ninety-page PDF.

A summary is this site’s description of a document, not the City’s. Open the document before relying on one.

What was said

10,833 words from the meeting recording, transcribed automatically. Times are from the start of the recording.

Read the debate(click to open)

6:26:58for 64 Duke Street.

6:27:00And just as a heads up, I did have one delegation, Ken Thompson emailed and mentioned that he

6:27:05was not able to do the delegation just to recognize that.

6:27:10But we have a presentation from Scott, who's going to be our Scott.

6:27:16Is it plant, plant or plantae?

6:27:18I'm going to say.

6:27:20Okay.

6:27:20Plant.

6:27:21Thank you.

6:27:21Who's a project manager with the planning development who's going to do a presentation

6:27:25for us.

6:27:26And then we have one, two, three, four, five, six different delegations.

6:27:33And then it comes back to us to discuss a little bit.

6:27:37Okay.

6:27:37Scott, thank you for coming forward.

6:27:40I'll turn it over to you whenever you're ready.

6:27:42Okay.

6:27:50And respective council's time.

6:27:51I'll keep this presentation short and concise tonight.

6:27:54Good evening, everyone.

6:27:55My name is Scott.

6:27:56I'm a project manager in planning and building services.

6:27:59Thank you for listening in tonight on this important future project in the city of Guelph.

6:28:04The purpose of this report is to seek council support and the urban design master plan for

6:28:10the Midtown Village project.

6:28:12It is noted that council support does not approve any zoning or strict design details

6:28:17tonight as this is a conceptual document that will provide a framework to guide future development

6:28:23applications.

6:28:31The subject properties municipal addresses are 33, 37, 39 and 45 Elizabeth Street,

6:28:3864 Duke Street, 69 here on street and 60 Al Street.

6:28:43The support of this master plan will be required before the applicant submits a formal development

6:28:48application through the city's downtown community planning permit system.

6:28:52Again, the recommendation before you does not approve any zoning, which will be evaluated

6:28:57in detail at a future community planning permit application.

6:29:01An urban design master plan is required to proactively manage large scale growth on the

6:29:11existing industrial lands that will support the arrangement of land uses, infrastructure

6:29:16and public spaces to ensure a high quality of life and environmental sustainability for

6:29:20the neighborhood.

6:29:22Generally, there is a positive public reception in the community and generally this urban design

6:29:28master plan supports the city's growth targets and urban design objectives.

6:29:3339 Elizabeth Street on the north of the site is included within the project area, which is a

6:29:38more recent small land addition to the boundary area of the master plan.

6:29:42The number of proposed dwelling units is estimated at approximately 800 to 875 in total,

6:29:49which on the topic of growth would help the city meet its growth targets.

6:29:53The square footage estimate for commercial space has not yet been specified and the buildings

6:29:57will primarily be residential with opportunities for small scale commercial and community uses

6:30:02serving the neighborhood and ground floor spaces oriented to the public.

6:30:07In the downtown secondary plan land use schedule, the lands are currently designated

6:30:20residential one, residential two, mixed use one and parks designations.

6:30:26In the downtown secondary plan maximum building height schedule, a concept plan includes

6:30:35seven buildings that range in height from two stories to 23 stories with the tallest buildings

6:30:41on this project being located at the center of the site transitioning to lower building

6:30:46heights at the edges. Four stories along Elizabeth Street and three stories along Duke Street.

6:30:51The Guelph Junction Railway runs through the urban design master plan area generally from

6:31:04west to east influencing the phasing of the lands. Since the north parcel is independent

6:31:12from the south parcel in terms of access and servicing, this phase may develop independently

6:31:16at any time once a community planning permit has been approved. Phase two includes the

6:31:22redevelopment of the north parcel with three new buildings. A new vehicular access Elizabeth Lane

6:31:29will be built and the existing access lane to the east will be rebuilt. The northern portion

6:31:34of the park will also be developed in this phase. On the south parcel the work in phase one will

6:31:44see the demolition of the existing warehouse structure while preserving the historic factory

6:31:48building and will see stormwater and sanitary infrastructure to be built within the rail corridor.

6:31:53In phase two the west block will be developed with two large buildings and a pedestrian muse.

6:31:59Land for the enhanced schoolyard is intended to be dedicated to the school board which could

6:32:04commence improvements to the public open space. In phase three the heritage building will be

6:32:08restored and the 16 story residential building will be developed on the east block. Here on lane

6:32:15will be built in its ultimate location and the final improvements at the edge of the enhanced

6:32:20schoolyard can be completed. This phase will conclude with completion of the park including

6:32:25the rail trail extension, construction of a public square and improvements to here on street.

6:32:32The existing zoning bylaw regulations will be enforced in effect until there is a resolution

6:32:45of the appeal of the community planning permit bylaw. The existing under appeal community

6:32:50planning permit regulations are not yet in effect. The existing bylaw regulations will be

6:32:54planned for the next year. These proposed community planning permit system regulations

6:33:01are to be determined at a future community planning permit submission by the applicant.

6:33:11Based on the timeline of the woods projects it is anticipated that the community planning permit

6:33:16bylaw will be in effect when development projects are ready to proceed. Three in-person public open

6:33:23houses have occurred since June 2024 including in November 2024 and June 2025. This public feedback

6:33:31helped to shape the current urban design master plan. If you wish to be notified of any future

6:33:42revisions or decisions on these applications please email planning at gulf.ca. Thank you for

6:33:49listening that is the end of the presentation. Great thank you very much. Well if we have any

6:33:57questions or comments to you we'll get them to you and staff right after okay sounds good.

6:34:04Scott was that your first was it was that your first time at the microphone for us? Really nice to

6:34:14meet you. Is it now this is where I get in trouble how long have you been with the city? Just over a

6:34:25year I'm in trouble thank you. Okay well this you did a great job presenting for us thank you very

6:34:31much that's great. Okay we have several delegations we're looking forward to hearing from you all.

6:34:37Susan Frazen from the wood development group is first actually it looks like we have three from

6:34:44the wood development group so we have Susan Frazen, Tim Smith and Ian Panabaker and are you all coming

6:34:51as a team? Yeah okay no problem okay so yeah this is five minutes not 10 minutes

6:35:07and again you'll hear the chime at the four minute 30 second mark with the warning just before you

6:35:14hit the five minute mark so Susan over to you and every you are ready and thank you so much for

6:35:19joining us. Good evening Honorable Mayor Guthrie and members of council I'm Susan Frazen I'm

6:35:28president of wood development group and it is truly a pleasure to be here tonight to present to

6:35:33our urban design master plan consisting of 64 Duke Street 69 Huron Street a small sliver of Alice

6:35:40Street 33 35 37 39 and 45 Elizabeth Street this is a site that is how do I go back?

6:36:00This is a site that is steep in history for the past well for over 100 years it has been industrial

6:36:08the majority of this site has seen various factories on it over the years

6:36:12but the city recognized the need for residential development in 1990 and re-zoned the site in

6:36:211990 for residential recognizing the contribution that this site had the potential to give to

6:36:28downtown so while you will see that our urban design master plan we've worked on this for four years

6:36:35the reality is that our family has been reimagining this site for the past 36 years

6:36:39and there's been a lot that's changed in 36 years but one of the things that has not changed

6:36:46is the incredible complexity of this site in fact with every year it continues to become

6:36:51more and more complex it's a brownfield site that has a railway that runs right through it

6:36:58it has a private easement on it it has a historical heritage building on it

6:37:04it has an elementary school sitting adjacent to it and most significantly it is a high density

6:37:12residential site that exists in a low-rise residential neighborhood so unless you specialize

6:37:20in brownfield or heritage which we don't most people would take advantage of the high density

6:37:29and heights that the city have given us on this site and sell it to maximize their ROI

6:37:36our family and our staff chose not to we signed up for this challenge because we honestly believe

6:37:42that what we can deliver to this community and to this city on this site is better than anyone else

6:37:51one of the reasons that we believe that is because we've been accumulating properties

6:37:58throughout this neighborhood for the past number of years to ensure that this site touches all four

6:38:08corners all four streets on this block and that will allow us to open up the site to both the

6:38:17community who live there and and rent there and they can access the neighborhood and the downtown

6:38:24through this site but we also wanted to be able to welcome the community into this site because

6:38:30we believe that what we will build here would be very special we'll create new public spaces

6:38:37including a dedication of land to the catholic school board to allow them to increase their

6:38:44play yard and potentially grow that school as the community around them grows we will clean up the

6:38:51site we will green up the site and we will also help to protect their neighborhood from potential

6:38:59floods so we will try and floodproof the neighborhood as well we'll build a mix of housing units

6:39:07in both in size and in type to allow for a broader range of homeowners and tenants to be interested

6:39:16in living here we recognize that you can't you just continue to put up high rise condo

6:39:23buildings and expect that everyone is going to want to live there so we'll be very intentional

6:39:27and very careful about what it is we develop here we restore the historic building on this site to

6:39:34celebrate the history that existed within those walls and we'll do our best to reflect and compliment

6:39:43the character of the ward in the spaces that we create will it be different for sure but different

6:39:52doesn't always mean bad remember that we live in this community and we work in this community

6:39:59and we can be held accountable for what it is that we develop here thank you very much uh Susan

6:40:07any follow-up uh for Susan at this point or did you want to maybe we I can do that or I can let

6:40:14uh Tim and Ian like all from the wood development group speak and then I could do questions to all

6:40:20like to all three so that makes sense okay yeah do you mind if I do that okay perfect so yeah

6:40:25let's do that so uh Tim Smith you're next and then Ian and then and then all three of you can come

6:40:32together and get get ready for questions welcome Tim go ahead thank you Mr. Mayor um members of

6:40:40council pleasure to be here again to talk about this exciting project my name is Tim Smith I'm the

6:40:46planner for the wood development group who has been part of the team let's put this together over

6:40:51the last few years what I'd like to do is kind of build on what Scott outlined in his presentation

6:40:55and some of the things that Susan touched on to describe give you a bit of an overview if I can

6:41:00in five minutes it's a lengthy document uh an overview of the what's in the plan which really is at

6:41:06its heart a concept that has informed a set of guidelines that we expect future development to

6:41:12to adhere to um you see on this slide really just a list of those sort of key elements key

6:41:17features that we see being built on the site as Susan mentioned a mix of housing types different

6:41:24unit sizes townhouses some embedded into the base of the buildings we're restoring converting that

6:41:30historic factory building doesn't look like much today but believe me underneath that and once you

6:41:35open up the windows it's going to be quite fantastic we'll be adding two stories to that for more

6:41:40housing um a new neighborhood park uh expanded schoolyard for the sacred heart school which I'll

6:41:47talk about in a moment other public open spaces and as you heard from Scott there will be opportunities

6:41:52for some small-scale commercial and community uses that we think the community will really appreciate

6:41:59and finally as Susan said we're opening up the site bringing people into what we're creating here

6:42:05also allowing them simply to get through the site and in many ways that opening up the site I think

6:42:10will be as uh a significant a change to the neighborhood as the the development itself

6:42:15we're building here let me talk a little bit about those connections you see them in the

6:42:19orange lines here a pathway from Alice Street up through the site the crossing of the tracks

6:42:27so that people can go right up to Elizabeth Street there's a muse off of Duke Street allowing people

6:42:32to come in from that direction there'll be some private but publicly accessible streets with sidewalks

6:42:37on them you see in gray here so lots of porosity and can't forget the rail uh rail corridor um

6:42:46will have an extension of the multi-use path that one day we all hope will continue eastward

6:42:52eventually reaching all the way over to um the Guelph Innovation District uh three key open spaces

6:43:01I want to highlight here a new park in the rail corridor uh an enhancement to the Sacred Heart

6:43:09School Yard and what we're calling here on Square a new open space on here on street in front of the

6:43:14heritage building let me talk a little bit about the park here this is really going to be about

6:43:19bringing nature back into the city the idea is a heavily vegetated green space we have 50 meters

6:43:25between the future buildings on either side of the rail corridor to work with yes the tracks

6:43:30will run through it we'll keep those we're sure there's safety barriers against that but the green

6:43:35space we have on either side will be lushly planted there'll be opportunities for public art for

6:43:41calling recreation nodes where you might find a ping-pong table or or something for kids to climb on

6:43:48simply seating for people to hang out in places where we can interpret the site's heritage the

6:43:53ward's heritage you've heard so much about today the enhanced schoolyard is a really big idea we've

6:44:02had lots of discussions with the Catholic School Board about this to really see how we could actually

6:44:07not just expand the schoolyard which will be a great benefit to the students as you can appreciate

6:44:12but actually how the space that after school hours and in the summertime can actually be opened up

6:44:18and available to the community and the school board has agreed that we don't they don't need to

6:44:22build fences around the schoolyard it can be managed through landscaping to ensure that the

6:44:27kids are corralled during the school day but you can get into that space and really make it function

6:44:32like a park with flexible play play yard playground more space for basketball and other court sports

6:44:43here on square will actually be a private space privately owned but it will be landscaped and

6:44:48have amenities in it for the public as you can see from the rendering here trees will line it

6:44:54that will have seating under the trees or people can come and meet and socialize with their neighbors

6:44:59we do hope to have a cafe perhaps other uses in the base of this historic factory building

6:45:04that's spill out onto this space we may need a little bit of parking in the front to support

6:45:09those commercial uses but we also see an opportunity to remove those parking so that the space can be

6:45:16used for community events now I do need to speak about the buildings briefly and to really emphasize

6:45:21here what we've done to push the taller buildings toward the heart of the site and provide transitions

6:45:27down to the neighborhood we've varied heights they're all well under 24 stories one to 23 stories

6:45:32the remainder are at lower heights as as scott mentioned and i'll just kind of wrap up i do want

6:45:40this this image gives you a sense of how the development will blend with the neighborhood

6:45:47yeah so just just one just one just one second sorry your time is is up

6:45:56um i'm going to look to my colleagues just to just okay you've gone off screen there did the screen

6:46:03just go off can you put the screen back on yeah for me thank you so much um to my colleagues

6:46:13this is an important sort of i think is anyone as the chair i'm going to make a call just to

6:46:20allow this last slide to be talked about um does anyone want to challenge me on that

6:46:26no okay please like 20 seconds talk about this because we got to go to the next delegate okay

6:46:32go ahead and talk about this last slide thank you mr i appreciate i'd be less than 30 seconds i do

6:46:36have just a few slides but very quickly we go through them there are three images i want to

6:46:40show to really emphasize what we see as how people will experience this site and why the transition

6:46:46how the transitions and the design of the edges of the site will really contribute so the view you

6:46:51have of duke street today is this looking south i'm sorry i'm having trouble advancing the screen

6:46:58there we go um it will look something like that in the future these are renderings you have to

6:47:03take renderings with a grate of salt but what we've done is line duke street with three-story

6:47:07townhouses and then if you look at the rail corridor today imagine it being widened lushly planted

6:47:14and lined with buildings with units that face the space with winding paths and and so forth

6:47:20and then this is the favorite view really this is what looks like from here on street today

6:47:25but imagine something that looks like this with that restored building more green space

6:47:30taller buildings in the heart of the site at a distance and really a lot more space for the

6:47:35community to meet and gather and have a higher quality of life perfect thank you very much

6:47:42for wrapping that up i appreciate it uh go and take your seat and ian's going to come up and

6:47:49then all three of you can be ready for any questions okay so ian over to you um i gave a

6:47:53little bit of grace there but please know no more grace for the evening you got it you got to get

6:47:58in in your five minutes okay go for it thank you your worship members of council staff and

6:48:04members of the audience i'm just going to i'm trying to kind of try and truncate what i said

6:48:08because there's been a lot that i could repeat but just obviously council tonight is being asked to

6:48:14support the uh the urban design master plan which is a requirement of the secondary plan for these

6:48:18large sites within the area and at 10 acres almost we are the largest of those areas to be planned

6:48:25in this kind of collaborative way there has been a lot of work to date to get here

6:48:34a number of years multiple pre-consultations with staff and agencies an extensive community

6:48:40engagement program and along the way the navigation of provincial and city policy changes and

6:48:45evolutions including the opa 106 that the city undertook for the downtown heights and the

6:48:52mentioned downtown cpps developments over the last year this uh decision tonight this decision to

6:49:00support is the first step believe it or not in us solidifying a vision which then creates a whole

6:49:07myriad of projects for us to start really implementing the the site site-wide environmental

6:49:14and um other audits and approvals have to be undertaken for the infrastructure renewals

6:49:19the parks and school agreements for these open space land dedications and concepts

6:49:24all leading to individual block applications the site had a lot of input and analysis i won't go

6:49:33into it we've had a great team helping us to do this and set us up for success in the future there's

6:49:39been a lot of research to done to actually illustrate this to you what's possible and we know what's

6:49:45practical we uh as scott alluded to we had three um public meetings we kicked off in june 24 two

6:49:53years ago the first uh of that was an introductory session and a visioning session with the community

6:49:59and while we didn't show a concept that night we did talk about the need for additional density

6:50:03and heights that we'd be seeking and with all the events that we did there was an online component

6:50:08there was surveying and commenting periods much longer than those events the second meeting uh was

6:50:16in november of 24 which we did present a concept and took folks through the rationale for the

6:50:23density there's a tiny little picture there in the corner of all the inputs that go into

6:50:28reconfiguring a site like this susan mentioned them about brownfields and working in a railway

6:50:33corridor and replacing trunk infrastructure and making commitments to creating great public space

6:50:40and gifting public space all that goes into factor into the land value for this project we do not

6:50:46have access to brownfield community improvement plans we don't have access to downtown investments

6:50:51programs for replacing infrastructure all of it's being borne by the density and height

6:50:58but we did show a 24-story building in the center and the basic structure that tim alluded to in

6:51:02terms of opening up to all corners and that led to a second consultation session with a revised plan

6:51:14that you basically see today documented in the urban design master plan this one incorporated the opa

6:51:20106 heights that had happened in the meantime we did revise the massing and and move it slightly

6:51:28further west towards downtown it helped with shadowing and some of the the relationships between

6:51:35the heritage building and the the project on the north side of the tracks on elizabeth street got

6:51:45enlarged because of the direction the council set with opa 106 following that meeting there was

6:51:53protracted period to get to today we added 39 elizabeth street gratefully it allows us to have

6:52:00a consistent um frontage on that street that's now incorporated in the document we clarified and

6:52:07expanded the the land dedications and park distribution over the meantime we had been

6:52:13talking about a shared space between the school and the park department that became unwieldy

6:52:19and we are now showing clear dedications of lands for the neighborhood park and the gift to the school

6:52:27for which they can then operate and program these with our assistance and support with clarity and

6:52:33operation the flood proofing concept that was mentioned was included in the next iteration that

6:52:39you see and we've incorporated the updated policies on cpps and heritage districts and things like that

6:52:45so in summary we're very excited to present this tonight we believe it conforms to the secondary

6:52:51plan intent it supports the city's growth management objectives and ambitions and housing objectives

6:52:57it sets the stage for remedying a very large brownfield in the center of town and that's my time

6:53:05no no problem thank you very much to all three of you so maybe i could ask all three of you to

6:53:12maybe just come up to the microphone and then if there's any questions from my colleagues uh i

6:53:17know counselor downer i believe i saw you go up am i right i was going to ask about go ahead i was

6:53:24going to ask about the timelines but you put that up and but while you're up there i'll say

6:53:27congratulations on getting to this milestone well done thank you is there any questions i got karan

6:53:35and uh goller echoing those comments thanks for the sticking with us along this journey

6:53:44you've got such a complicated site everything from brownfields and heritage to parkland to

6:53:51low density to medium density and high density just just quite a complex site and the landscape has

6:53:59shifted considerably from beginning to today policy changes affordable housing incentives

6:54:07development charges parkland dedication provincial regulations with respect to

6:54:14incentives and infrastructure so much has shifted is there is there anything that is holding you

6:54:22back from proceeding like is there still that instability in the market and in the planning

6:54:27landscape that would prevent you from moving forward on this project in the timelines that

6:54:34you've established that's question number one and question number two is there anything you've

6:54:39heard in the policies locally that even tonight we talked about the ward west heritage conservation

6:54:45district is there anything we're doing right now at city hall that you have any concerns about

6:54:51as you move forward with the project while the landscape is still shifting around you

6:55:03through mr mayor i'll jump in there's a lot in that question it comes down to confidence

6:55:09there is a lack of confidence in the market uh real that has happened over the last uh at the

6:55:16time that we've been doing this project we were far more confident about starting four or five years

6:55:21ago than we are today when you see um de-escalation of prices real prices in the world when costs

6:55:31haven't come down for all manner of reasons that's what's happened in the in the blockage of market

6:55:38housing and that has to that has to work its way out still there's kind of predictions of a couple

6:55:45of years out will be in a more positive market again and uh as a group we need to collectively

6:55:52get a sense of that confidence building because we have a couple of years of work to do before we

6:55:57can actually entertain the cpbs applications that would have to come through we have to

6:56:04like you saw fusion do at metalworks we have to take the site apart and reconstruct

6:56:10trunk infrastructure that cuts through what was was ferguson street that went through the through

6:56:16the site and that's years in the in the works and actually getting the record the site conditions

6:56:22in place to entertain partners in the various projects so it's it's that's that will be the

6:56:29sense that there's there's a building confidence in uh guelph in the economy and in the market that

6:56:36will that will have us start going that said there's still a lot of planning work that actually has

6:56:43to happen from today to get some of these base agreements in place with the partners and um

6:56:50build that understanding before we can actually have development partners in place as well so

6:56:56we're not we're not idle when this is happening okay thank you for that summary and I really

6:57:02appreciated the opening comments from Susan about the legacy part of this that you know you over 30

6:57:09years you you really want to make sure that this project um it is successful because it I from what

6:57:16I've seen in my 20 years on council this is the singular largest kind of redevelopment in this area

6:57:24so it's quite a legacy piece and thanks for sticking with us I hope you'll stick with us a

6:57:30little bit longer get the shovels in the ground cranes in the sky thanks great thank you very much

6:57:39council goller is next okay uh and yeah and just just a reminder and I'm going to you as well

6:57:45councillor caton after goller and just a reminder that uh this is like the the urban design plan

6:57:55so if there's anything about that too just make sure we're referencing that okay council goller

6:58:00thank you through worship to uh to all of you thank you so much for for coming here today I'm

6:58:06presenting this plan it's I've mainly heard a good thanks from the community uh that are looking

6:58:12forward to to this development uh there was one one um concern resident that I wanted to bring

6:58:18some other questions about um in terms of what was proposed originally and what is proposed now

6:58:25can you clarify for me has there been a significant change I I know that some of the buildings moved

6:58:30around has the density increase decrease and the total heights um are we seeing more than what was

6:58:37originally proposed just for for clarity so what you saw in the original proposal that was up on

6:58:44the screen earlier we presented 24 stories uh right adjacent to the heritage building one of the

6:58:50things that we heard from the community was that that is a drastic change from five stories to 24

6:58:57stories it seems it is a lot and it seems like a lot um and so we took that information back we

6:59:04reconfigured the site in the process of reconfiguring the site the city also went through a downtown

6:59:09height study which then gave us greater density on the site um and in order to help the city achieve

6:59:17their downtown goals for um you know both residents and jobs um we made some changes to the site to

6:59:28both reduce the dramatic change between the five and the 24 stories um and also center

6:59:35the 23 story building that we now have on there um closer to the center of the building so that we

6:59:41also changed any of the shadowing on the site um so yeah there have been some changes there

6:59:47reflection of the density and the heights that the city gave us um as well as listening to

6:59:53community feedback and responding to that okay okay I really appreciate that clarification so

6:59:58so the changes were to to reduce the height a little bit and also to shift it away from uh

7:00:04from the edges to okay I really appreciate that uh for the uh for the shadow studies uh it points at

7:00:1110 a.m. 4 p.m. and then are those set by the city that the the times for those studies and then

7:00:18the fact that they were in the uh spring summer and fall and not in the winter is that is that a

7:00:23city restriction that that you were following or did you sort of you know pick times that worked well

7:00:30through you mr. mayor um yeah and frankly I'm any scots helped answer this because we did those

7:00:34shutters days a while ago but my my recollection is that those are the key times that they look at

7:00:40they may also look at other times in particularly in the summer like it's six o'clock but we did

7:00:46focus on that 10 to 4 period which I think is is the primary concern winter time December

7:00:52shadows are long everywhere it's a little hard to really you know evaluate a project based on

7:00:58winter shadows but I I did want to point out that I didn't have a chance to kind of go through those

7:01:02tiny little diagrams but you know we were careful and this is why with the north parcel one other

7:01:07change on the north parcel was what we had before 10 and 12 story buildings we now have one

7:01:1319 story buildings that rather than having two taller buildings we recognize pulling that in going

7:01:18a little taller if anything had less of a shadow we impact on those backyards and those impacts

7:01:23are very minor on a handful of properties and only in the morning so afternoon shadows really

7:01:29are well away from all private properties and none of the neighboring streets surrounding

7:01:33streets will be will be shadowed during during the daytime okay I really appreciate that and

7:01:39lastly with the wind study I noticed that there was a good section that talked about it

7:01:43how far does the wind study go I mean could you clarify will this have impact on the surrounding

7:01:48streets the wind created by by the buildings based through you mr. mayor based on the wind

7:01:54study that was done does not significant impacts that are expected on the streets or even within

7:02:01the site and this is part of the massing approach having those transitions putting taller buildings

7:02:06onto a podium really helps to mitigate wind impacts on the windy days I will point out though and

7:02:13you know at least when we go into a community planning permit application we will need to

7:02:17submit more detailed wind studies at that point for individual buildings so things will be looked

7:02:22at more closely then and measures may have to be incorporated into the design of the building to

7:02:27to mitigate an impact so we did a kind of high level initial study to understand what we could do

7:02:33with massing to mitigate any impacts detailed design will need to look at more closely at

7:02:38individual companies and their context perfect thank you very much for that and through your

7:02:43worship just one last question in terms of the facing I saw that face one you're removing the

7:02:49buildings and then face to you start building them what are your expected timelines for for you to

7:02:55get through face one the demolition part for us to see the face to begin through through you mr.

7:03:07mayor it largely will depend on you know how things go with the approval processes with the city

7:03:14change in market but we're looking like two to three years so we when we were talking about

7:03:21you know the market and and the fact that we've got it we're in a down cycle right now

7:03:25you know time is on our side in in that sense because we're coming to you with our urban design

7:03:29master plan now during the down cycle we're hopeful that as we do all of the work behind

7:03:34the scenes to get this project you know out of the ground that as we're you know getting there

7:03:41that the market will also return but you know even simply like things like the cpp being held up

7:03:47that you know plays havoc with our timelines as well okay okay and just so that I understand

7:03:54two to three years before you get into into the face where you're building but in the meantime

7:03:58you would be doing the demolition of the the existing warehouses is that correct or would

7:04:02you wait two to three years and then start the demolitions yeah a lot like I said a lot of it

7:04:07will depend on the timelines in the market um we I mean obviously us holding on to this site

7:04:14as I talked about before every year that we wait in this development this site becomes more complex

7:04:20you know the environmental um um regulations change and become more stringent um there are

7:04:28more stringent rules around rail um there are more rules around heritage buildings so every

7:04:33year we wait this site becomes more and more difficult to develop so it's not our intention

7:04:37to wait um but there will be lots of things that um barriers that we have to overcome in order to

7:04:42develop okay okay thank you for that thank you worship all right thank you uh kateen and then

7:04:48boosted up thank you through you mr mayor um first off I really like it I think it's a very

7:04:56cool concept I love the the kind of market common area and um I I've always moved too well from

7:05:06bigger cities so I'm not height adverse um I think that you've kind of done it in a very thoughtful

7:05:12way and I like the step how it steps up um I have questions about just the accessibility

7:05:18through this site I I saw within the the design that there was kind of like meandering pathways

7:05:24which looks really nice design wise but accessibility wise it's it's a lot better for

7:05:29folks to just kind of a straight path through and maybe have offshoots that are a little bit more

7:05:33wandering so I'm just wondering if that's something that you've considered when you kind of think of

7:05:37your flow through throughout the site thank you uh through you mr mayor it's a counselor

7:05:47it's um it's something that we've spent a lot of time on thinking about uh currently there's um

7:05:55flood lines that we need to maintain of the buildings outside of the flood um

7:06:01height and so some of the meandering paths that you're seeing us design are actually

7:06:08minor ramps to get us up and down to various levels because of the need to raise or lower the

7:06:14the habitable floor heights this is something that's happened late in the day is when we did that flood

7:06:19analysis and realized that the project on the Duke Street side could actually act as a levy and

7:06:25prevent everything eastward from actually being part of the flood area in the in the uh the future

7:06:34it changes our it will change our approach to some of the levels

7:06:39and grades inside the project itself if that's accomplished and so grading actually becomes

7:06:44much more simpler if if we can accomplish this initial levy of the floodway in the first phase of

7:06:51that south project and so it's it's a work in progress um but we're we're keenly aware and

7:06:59looking at the grades constantly some of those meandering paths are to accomplish accessibility

7:07:07on those grades i might just just add if i made that uh as Ian described the the site basically

7:07:15in the south parcel kind of comes up to deal with the flooding issue and the rail yard obviously is

7:07:20not moving and stays down so in particular we worked a lot with our landscape architect to

7:07:24really understand how we can have an accessible crossing safe and accessible crossing so there

7:07:30will certainly be a little zigzagging there there'll be stairs for those who want to use stairs

7:07:34but uh we gave a lot about there were i think a few back and forths to get that right okay thanks

7:07:42and i i'm sure i'm sure you'll be working with staff over stuff like that too but overall i think

7:07:47it's a great concept great thank you and last is busitil please thank you and through the

7:07:55marion to the delegations you've come a long way since the first public meeting that i went to

7:08:00so awesome and i will echo what uh councillor Caton said just love the design i did have a

7:08:06question i'm a little bit confused maybe i'm just tired it's been a long day um when you talk about

7:08:12and yes sacred hard needs additional playground space my kids have been there before it's not the

7:08:18greatest um i'm curious because it talks about an agreement between the wellington catholic

7:08:25district school board in the city for maintenance and program and things like that um was there an

7:08:30exploration about giving that strip to the city of guelph i think of gateway school that has uh

7:08:37you know um school board land and city land and programming space there or waverly or a whole bunch

7:08:44of other places can i was a little bit surprised by that yeah through mr mayor to the counselor

7:08:51this this has evolved since the initial unveiling of it a couple of of sessions ago

7:08:58um we had talked uh with parks and with the school board about an uh an actual shared

7:09:06facility where during the day it would be largely off limits and controlled by the school board

7:09:12and during the the evening and off off season it was fully public park and for which there would be

7:09:18this agreement for maintenance and operations of it uh that's different than some of the more

7:09:25suburban parks where you have school board lands and city lands adjacent but not overlapping

7:09:32and what it came down to was um parks came back to us with the need for um the technical need for

7:09:40the park dedication to be fully accessible i.e. like available to the public 24 hours a day they

7:09:47couldn't deal with the the legality if you like of receiving park land dedication that was not

7:09:56accessible 24 hours a day and hence the separation so where we were talking earlier about that

7:10:02strip of land contributing to a bigger park which would be shared it's now being given to the school

7:10:08board with the same intent that it's actually a recreational facility for the community off hours

7:10:13and off season and so there is an expectation that there's a a form of agreement between the

7:10:20city and the school board for that facility thank you okay and actually at clauson we'll

7:10:32bring us home here go ahead thank you mr. mayor and thank you for the presentations

7:10:38i liked a lot about the a lot a lot about it it looks really exciting from a space that i think is

7:10:46as we all know quite underutilized by the public it's not accessible really

7:10:50to something that is is going to bring a lot of new availabilities to the public so i i'm excited

7:10:57about that but i'm gonna get to my question um there were a couple of of core pieces of

7:11:01correspondence and i received a few emails from residents concerned about the heights and the

7:11:07massing and in one i think in one piece of the correspondence it's attached to the package there

7:11:14was a comment about the heights and if or maybe it was an email i'm not sure and i think that on

7:11:22page 37 you outline um when apartment buildings are greater than four stories they shall generally

7:11:29incorporate one to two story grade related units um and their comment was um they really liked the

7:11:36metalworks and how the metalwork towns on either side contribute to the streetscape and feels very

7:11:42walkable and very accessible and so that you don't have you know single story residential

7:11:48followed by you know a massing of a wall that is accommodating a 24-story 23-story building

7:11:55so i was just wondering if you could could speak to that a little bit um to talk about what that

7:12:00might feel like um at this street level uh through you mr. mayor to the counselor um yeah we we agree

7:12:10that metalworks looks lovely it faces out on the street um in in a beautiful way that helps make it

7:12:16feel uh very much like it fits into the residential neighborhood and so we took note of that um and

7:12:21it was one of the things that we incorporated into our plan so i don't know if they're misreading the

7:12:25plan um but if you look at um duke street um there are three stories running down there of you know

7:12:32townhouses along the rail we've tried to incorporate the same anywhere we face out onto the community

7:12:38we've tried to keep it as low rise as possible including on elizabeth street um to really try

7:12:44and keep that same feel of residential neighborhood and our tall buildings have been pushed into the

7:12:49center of the site to create that cascading effect down to the street that really um you know in 10

7:12:58acres um it really does kind of swallow up those big height buildings that are in the center um so

7:13:06i don't know if they're misreading the drawing or misunderstanding it um but we agree metalworks

7:13:11faces out into the street lovely it's two and a half to three and a half stories there

7:13:15ours are three so we we tried to capture that as best we could thank you i appreciate that response

7:13:25with that um nothing oh just i'm circling uh one one question from uh from councillor

7:13:31karan and then we'll go we just have three more delegations everybody just remember okay go ahead

7:13:36is a really quick question what would you like us to call it should we call it plant number two

7:13:40or should we be calling it midtown village what do you what do you folks call it through you mr

7:13:47man thanks thanks for the question we we um very carefully called it plant number two

7:13:54midtown village is our corporate name for the holdings the land holdings and that's what staff

7:13:59have picked up on because that is the legal ownership title of the property but it's plant

7:14:04number two to us as a working title to to eventual um building names let us know if there's a name

7:14:15change all right thank you very much we appreciate the three of you very much for coming and delegating

7:14:21mike darman from guelph community community for active transportation g cat i bet you we know

7:14:30what you're gonna say we appreciate you mike thank you for sticking around for the whole uh

7:14:37whole night and then michelle i see you oh you see you you're in the wings coming down next

7:14:42mike over to you um mayor guthrie city council and city staff my name is mike darman and i'm

7:14:49advocacy co-chair for the guelph community for active transportation g cat is is pleased to finally

7:14:55see the woods to plant to at this stage of the planning application process as the walking biking

7:15:01transit and neighborhood connectivity is finally being revealed through this urban design master plan

7:15:07i could basically read verbatim the introduction and vision for woods on the first page because it

7:15:12encompasses an exciting and carefully crafted urban design plan along with a once in a generation

7:15:17opportunity to transform the legacy industrial site into a new neighborhood that will integrate well

7:15:23with the historic ward neighborhood and our downtown personally i love the same patrick's ward

7:15:29and not just because i'm irish i back through it almost every day on my way to my son's on my grand

7:15:35kids house i'm quite familiar with the woods to plant site as it sits right beside where my grand

7:15:40kids attend school at at sacred heart and we ride our bikes or walk to school together quite often

7:15:47i'm excited to hear that the playground area in parkland will be expanded through the land

7:15:51transfer from the woods development and that we can explore more areas safely after school with

7:15:55the increased connectivity throughout the development affordable housing is arguably the most talked

7:16:01about concern of citizens of guelph gcat looks at development which by design and location make

7:16:06overall expenses cheaper by enabling a car light or car free lifestyle and more active transportation

7:16:12schools you couldn't be closer for catholic and king george public school is just a 15 minute

7:16:18walk up here in the street and up to 100 steps coffee shops including the ward neighborhood

7:16:24double rainbow cafe suga mercado for food and canada's smallest bar will be more accessible via

7:16:29brilliant new cut through connection to ala street and of course our downtown will be a major

7:16:34attraction to many other businesses that will benefit from this development's density and walk

7:16:38ability local and regional transit are also within a few minutes walk and with more frequent

7:16:43go trains including on weekends i took the the new 20 minute no stop go train to kitchens on

7:16:50saturday the work and pleasure possibilities are endless i kind of stress enough the importance of

7:16:56what this development will enable through the implementation of a protected minimum active

7:17:00transportation network grid similar to what to what the iron horse trail has achieved in k w in

7:17:06attracting high quality high density residential and commercial developments along its transit and

7:17:12protected active transportation minimum grid systems we can achieve achieve similar in guelph

7:17:18and extending our primary active transportation rail trail is one of the lowest cost safest and most

7:17:24enjoyable ways to achieve it when protected minimum grid networks are connected by safe

7:17:29crossings and connected to places where people need to shop work and play they will encourage

7:17:34people to try alternative mobility options like walking and biking transit the woods development

7:17:40design encourages this lifestyle shift within and expands active mobility options outward in many

7:17:47directions trail development i've delegated so many times for for an extension of the existing north

7:17:53of downtown trans canada g to g g ggr rail trail with the recent council approval of the macdonnell

7:18:00road and bridges structures ea along with the new ward to downtown bridge we now have the gateway

7:18:05to the extension from the macdonnell bridge to arthur street and with a much improved trail crossing

7:18:11design continuing from woods from the woods to plant on duke street we will have a more direct

7:18:17safer enjoyable active transportation connection to the ward to here on street the himico site and

7:18:23and the gid are just really up the tracks i would remind council that the current city budget for

7:18:29all new trail development is completely out of the tenure budget cycle forecast this development

7:18:33will get us to here on street but to continue the network trail connection to himico and gid

7:18:38we will need your support to fund this expansion to victoria road area we are working closely with

7:18:44woods on our vision for active transportation in out and throughout the development area and extremely

7:18:49pleased to see many of our ideas being incorporated but also thrilled to see even more than we could

7:18:53not envision like that 24 7 accessible public path and mallet street into the center of development

7:18:59enabled by woods g cat is fully in support of the staff recommendations to support the master plan

7:19:06i hope you agree that this is being very thoughtfully planned to integrate well into the historic

7:19:10ward neighborhood and will vastly improve this former industrial legacy site into a vibrant new

7:19:15community overall this development will make our city continue to achieve its ranking as one of the

7:19:20most livable cities to live work and play in i am truly excited to see it move to this stage of the

7:19:26planning application process thanks thanks mike thank you very very much so any uh any questions

7:19:35for mike today there is not so well done thank you very much thanks and uh michelle bowman's on

7:19:42her way down and then bringing us to the end is barbara and scott in the front row there here

7:19:47in the wings okay the two of you so michelle welcome again and over to you whenever you're ready okay

7:19:57is this working yet so as we have heard there are many advantages to the pros midtown

7:20:04village or plant to an active transport corridor a larger schoolyard built within the city's

7:20:11footprint and one of my favorites all the native plantings however the generally positive

7:20:19public reception in the community cited in the staff report largely came before the increased

7:20:26building heights so one b um building one b moved closer to existing housing

7:20:33one c doubled from eight to nineteen stories the heights fronting on duke street large part

7:20:41doubled from two to three stories two a from nine to fourteen and two b from sixteen to twenty three

7:20:49um so we're glad that the twenty four decreased to sixteen but there were a lot of increases

7:20:55as well when the newest plan was presented in the i live or lived in the ward group not by me by the

7:21:03way um there were about 40 very negative comments and 10 positive ones and the positive ones came

7:21:10from outside the ward so concerns included the height increases low demand for condos traffic

7:21:18loss of heritage and affordability all of which i'll talk about but i'd like to start with the park

7:21:24land so um proposed building 2d sits on land that was slated for parks and open space in the downtown

7:21:33secondary plan um so building it would add to our parkland deficit instead 0.4 acres was donated

7:21:42to the school which residents appreciate um and the rest of the half acre came from required setbacks

7:21:52so in the bylaw 2071710 b um it says an 800 unit development would require about

7:22:011.6 hectares of parkland but they're only providing 0.9 and so that's 56 of what's required

7:22:11the existing schoolyard makes up the rest to get to the minimum requirement

7:22:18um so as i mentioned there's concern that condos are not in demand we see in bc that the federal

7:22:24government is buying empty condos traffic was also a big concern for local residents um feeding

7:22:34on to elizabeth is manageable but feeding on to huron which is directly adjacent to the school is

7:22:40problematic and i'm not sure about the idea not to fence um a schoolyard that is directly adjacent

7:22:48to a laneway that um hundreds of residents will be using um main four commercial spaces are also

7:22:57important for a walkable neighborhood there's very minimal one cafe and i think one other um

7:23:07so i was glad to see staff are looking to secure more non-residential uses but i think we should

7:23:13ensure that these make it into the final plan so we heard about the ward heritage conservation

7:23:19district earlier and um this plan doesn't conform to some of those recommendations so again heritage

7:23:29plan emphasizes commercial uses which are traditional in the ward it directs that a maximum

7:23:38height of one or two stories or suggests hopes that there'll just be one or two stories adjacent

7:23:45to streets like duke and huron um and the last and maybe most important thing is that the ward

7:23:53residents care deeply that the neighborhood remain affordable for the working class that built it

7:24:00so wealth affordable housing strategy says we need 33 percent of all new builds to be affordable

7:24:07and that definition is the provinces um which is only affordable for the top 40 percent of our city

7:24:18so um i think the community is asking that the developers make as much of these as many of

7:24:28these units as affordable as possible and i think it's a fair ask that if the developers say they

7:24:35just can't meet this they they can't make it work with higher levels of affordable units that it's

7:24:43fair for us to ask about their profit margins so show us how it's not possible to get more affordable

7:24:52units in this development um but i'd like to end where i started and that there is lots of advantages

7:25:00to this development thank you okay thank you is there any follow-up questions for this delegate

7:25:09there isn't so thank you very much and last is barbara man and scott frederick on behalf of the

7:25:15ward residents association come on down thank you go again and thank you for having us and thank you

7:25:31for all the hard work that you guys have done with the community and with staff um michelle mentioned

7:25:36a lot of things that we've heard and we hear often about developments so i'm going to throw some

7:25:41some ideas for solutions at it while this has a 1.2 spaces per unit of parking which is more than

7:25:49the minimum that's required it still doesn't mean that as we've said to you over and over people

7:25:55move here from cities like montreal they move here from toronto and they end up buying a car

7:26:00so what we're saying to you today is that the leadership of guelph which is in front of us

7:26:06has a couple years to fix our public transit and bring it up to the state that is expected for this

7:26:12day and age if you're looking at kitchens i don't know if you've seen their transit hub that they're

7:26:17building but it's incredible and it's our time to join into that any of us who've been anywhere else

7:26:23in the world we come home and go i'm going to get on the bus and then we go but it's going to be

7:26:28such a hassle to get where i'm going and that also means that i think it's up to the developers

7:26:34to start demanding that now as well so that that doesn't create the chaos that we all know is going

7:26:41to come as michelle was just describing about congestion about parking problems in in a neighborhood

7:26:49that's already very very challenged uh the second part is about the heights that is a huge concern

7:26:56because the plan has changed a lot but another idea was how about what we in ontario call micro

7:27:02units to bring the height down but what everybody else in europe new york city etc considers a normal

7:27:09smile apartment um i think these are things that we can be looking at to try and bring

7:27:15breast practices to guelph to negate some of the challenges that we see in the future

7:27:24so i'm talking about the parkland now um sorry we're pleased that um the dedication

7:27:34i thought it was more than a minimum but michelle thought it was less i don't have to look at the

7:27:38numbers again but it's good to have linear parks it's also important to have larger tracks and

7:27:44accommodate sports field which we're short of and we're losing opportunities to create that

7:27:49um and on the eco park rail trail this is most of the parkland dedication and it's about 50 meters

7:27:59wide including the guelph junction railway right of way which is about 20 meters wide the drawings

7:28:06show this corridor to be mostly fenced off this means that possibly up to half of the eco park

7:28:13will be fenced off from public access now currently there's no fence and is free access to the whole

7:28:19corridor and have been for many decades uh we would like to see these fences to be as close to

7:28:26the rail line as possible we could take as an example the kent street rail corridor or even better

7:28:33the trans canada trail that's parallel to uh dufferin street um that seems to have worked

7:28:40perfectly safely and so i don't see why we couldn't have that kind of set back to the fence and then

7:28:48we'd have much larger uh public space available it's not much of a public space that's fenced off

7:28:55and you can't go there and that is it okay um one thing that i'm very confident about having met

7:29:03one of the tenants at nine elizabeth street is that well the affordability is a challenge with this

7:29:10the accessibility of the units i think is going to be above standard because i understand that

7:29:15that tenant had took five years to find somewhere where she could shower with in her wheelchair

7:29:22and that um susan and her team has asked her to be a consultant on these on the development with

7:29:30this the affordability part is huge our neighborhood is known for being affordable from rent gear to

7:29:37income through to luxury accommodation and that's one of the big things that i fear with this is

7:29:42that there won't be that within this partial community uh within the ward and i hope that

7:29:48that's something that can be looked to and we we keep reminding you we have one of the oldest

7:29:52best examples at victor davis park right on neve street great thank you both thank you very much

7:30:01is there any follow-up uh questions for the representatives from the award residents association

7:30:08and nobody thank you again all right everybody it is back to us there is a recommendation

7:30:17for this midtown village concept plan be supported um i would imagine the counselors would love to

7:30:28maybe do that okay i'll go clausen and and galler i will move in second that is there anything more

7:30:36i'm again this is this is an urban design master plan it's not like the applications we had earlier

7:30:40at all um all that stuff comes way later as the staff and the proponents both said so this is just

7:30:47saying yep they're on the right track right but all the detailed stuff comes later so is there

7:30:52anything about this that we need to say anything more on call her thank you through worship i have

7:31:02a couple follow-up questions for step for staff because we did ask the developer but i just wanted

7:31:06to verify just confirmation from you that the the wind impact the shadow studies

7:31:13and they were all done in accordance with the city guidelines and then they meet your requirements

7:31:18is that is that correct that is correct uh those precise dates that the applicant identified are

7:31:28also within our terms of reference for sun and shadow studies with the city of guelph so okay yeah

7:31:36just wanted to clarify that that um and the the traffic impact study i believe that there was a

7:31:40reference to a baseline in 1995 okay can you can you help me understand um when we when we look at

7:31:47that what did we use a such an early date for for for the baseline um just so that i that i understand

7:31:56that you know that doesn't fully meet the city's requirements um the traffic study and you we believe

7:32:02i just need the verbal confirmation so they would have completed their uh traffic study

7:32:07requirements in accordance with the requirements that were provided with the direction and guidance

7:32:10given by our transportation engineers and transportation planning staff in house so i would

7:32:16have to speak to our transportation planners in house to get a precise answer on that but i

7:32:21could certainly get back to you okay no but that is right i mean they're following your

7:32:24requirements i i appreciate that um and as each phase gets built and each building gets built will

7:32:30there be more detailed studies to confirm that the streets can indeed take that capacity that's

7:32:35correct okay okay so one at a time um and lastly the question about parkland will that be addressed

7:32:42when does that get addressed and when does the parkland dedication when do we confirm that we're

7:32:48getting what we require in terms of whether it is green space or in new payments at what

7:32:54stage of the process do we confirm that so we will take the parkland dedication as the phase

7:33:06has come in and we will ensure that the overall parkland um based on the entire site um is received

7:33:12ultimately but it would be assumed to be taken um within each phase okay and where there's not enough

7:33:19green space available then the city would take payment in lieu is that correct that's correct

7:33:25okay okay i really just wanted to to appreciate that and i'm just you worship comments if i may

7:33:31um i i know that projects like this can be divisive when there's a big change in the community but

7:33:37i i ultimately believe that the work that this developer is doing between putting up the the

7:33:43flood barriers to get a large portion of the work out of the flood plain is going to be very positive

7:33:50as the active transportation advocates mentioned i really appreciate that they're bringing in the

7:33:55connection from the downtown all the way to here in street i think that's going to be a very big

7:34:00positive for for the community um and i i like the thoughtfulness that they have taken to to

7:34:07include the more apartments into the word which ultimately will increase affordability um i think

7:34:14that it is it is well designed and well thought through um and i'm happy to support this uh

7:34:20design guidelines great thank you councillor Goller can i call the the vote then on the support for

7:34:30this urban design master plan great i'm going to do that right now um all i'm going to say is um i love

7:34:39it there you go so is there anybody against nobody that's unanimous all the best in the next steps

Automatic transcription is imperfect. Treat quotes as a guide and check the recording before relying on exact wording.

Check this against the City’s official minutes

The motion, the vote and the debate come from the City of Guelph’s published record, reproduced rather than interpreted. The document summaries above are the exception: those words were written for this site.

See the rest of this meeting