Committee of the Whole · June 02, 2026 · Item 15.1
McQuillan’s Bridge Environmental Assessment be approved, and that staff be directed to issue a Municipal Class Environmental Assessment Notice of Completion to rehabilitate and strengthen the…
Main motion under the agenda item McQuillan's Bridge Municipal Class Environmental Assessment - 2026-248
Carried (8 to 5)
8 in favour, 5 against
What was voted on
The motion in its exact words, as recorded in the minutes.
That the McQuillan’s Bridge Environmental Assessment be approved, and that staff be directed to issue a Municipal Class Environmental Assessment Notice of Completion to rehabilitate and strengthen the bridge.
Moved by Councillor Caron, seconded by Councillor Downer.
How the room voted
In favour (8)
- Allt
- Busuttil
- Caron
- Caton
- Downer
- Goller
- Hauser
- Klassen
Against (5)
- Billings
- Chew
- Gibson
- Guthrie
- Richardson
Who spoke to it
Kyle Gibson, General Manager, Engineering and Transportation Services, Kate Berry, Project Manager, Transportation Planning, Jack Mallon, Planner 1, Heritage, David Cameletti, Member, Heritage Advisory Committee, and Piper Boyd Bell, Member, Heritage Advisory Committee, presented on the McQuillan's Bridge Municipal Class Environmental Assessment.
What council was given
The staff reports and correspondence attached to this item. The summaries are written automatically, so you can tell what a document is without opening a ninety-page PDF.
- McQuillan's Bridge Municipal Class Environmental Assessment - 2026-248.pdf
Staff ask Council to approve the environmental assessment for McQuillan's Bridge and to formally close out the study, choosing to repair and strengthen the heritage bridge rather than other options. The bridge was closed to the public in January 2025 because of its poor condition, and community feedback generally supported repair. Construction is targeted for completion by the end of 2028; the cost estimate holds only until September 2028.
- Attachment-1 McQuillans Bridge Municipal Class Environmental Assessment Presentation Slides.pdf
- Attachment-2 Executive Summary.pdf
- Correspondence - P. Brian Skerrett.pdf
- Correspondence - Kevin Puddister, Vice President, Guelph Historical Society.pdf
- Correspondence - Andrea Bidgood - 248.pdf
- Correspondence - Lynn Bestari and Susan Ratcliffe.pdf
- Correspondence - Mike Darmon, GCAT.pdf
A summary is this site’s description of a document, not the City’s. Open the document before relying on one.
What was said
18,044 words from the meeting recording, transcribed automatically. Times are from the start of the recording.
Read the debate(click to open)
2:59:44We have four items for discussion this afternoon
2:59:47and we are starting first with McQuillan's Bridge.
2:59:53We have a staff presentation as well
2:59:56as presentations from members
2:59:58of our Heritage Advisory Committee.
3:00:00And what I will say is that we know
3:00:04we have staff recommendations.
3:00:06We know I've heard of some alternatives as well.
3:00:09It's a bit of a complicated matter.
3:00:11So first what we're going to do
3:00:13is go to staff presentations
3:00:15and then we will get the recommendation on the floor
3:00:20and have a discussion
3:00:22and see how things progress from there.
3:00:24So I'd like to invite staff to start their presentation.
3:00:29And we have, well, I see Kyle Gibson
3:00:33stepping up to the podium.
3:00:36Welcome, Kyle.
3:00:41Welcome and good afternoon, Mayor Guthrie,
3:00:44members of council.
3:00:46My name is Kyle Gibson.
3:00:47I'm the acting general manager
3:00:49of engineering and transportation services.
3:00:52We are pleased to be here today
3:00:54to present the McQuillan's Bridge environmental assessment.
3:00:57At 110 years old, McQuillan's Bridge
3:00:59has been a feature of our municipal infrastructure
3:01:02and has served Guelph residents and businesses
3:01:05for multiple generations.
3:01:07Engineering staff have made the decision
3:01:09to close McQuillan's Bridge in January of 2025
3:01:12following a routine structural condition assessment
3:01:15that determined the bridge was no longer able
3:01:18to support public use.
3:01:21To support community access in the area,
3:01:23city staff established a temporary pedestrian route
3:01:26along Stone Road East by installing concrete jersey barriers
3:01:30and by reducing the speed limit on Stone Road East
3:01:33down to 40 kilometers per hour.
3:01:35These temporary measures will remain in place
3:01:38until a solution for McQuillan's Bridge can be implemented.
3:01:43Due to the findings of the condition assessment,
3:01:45the public use of the area and the urgency needed
3:01:48to identify a solution to move forward,
3:01:51the EA for McQuillan's Bridge was moved ahead
3:01:53in work plans to be completed as quickly as possible.
3:01:58This in conjunction with the Stone Road
3:02:00and Victoria Road EA.
3:02:03At this time, I'll now turn it over to Cape Erie,
3:02:05the city's project manager,
3:02:07to walk you through the environmental assessments,
3:02:09findings and results.
3:02:23McQuillan's Bridge is located in Ward 1
3:02:25south of Stone Road East at the Eremosa River.
3:02:28The land in this area, the floodplain and valley lands
3:02:31of the river have been inhabited by indigenous peoples
3:02:34for thousands of years, is located within the treaty lands
3:02:37of the Mississaugas of the Credit First Nation
3:02:39and forms part of the city's natural heritage system.
3:02:44The study areas were located entirely
3:02:46within the Grand River watershed
3:02:47and lands regulated by Grand River Conservation Authority.
3:02:52The bridge was built in 1916 and carried vehicle traffic
3:02:55over the Eremosa River for more than 80 years
3:02:57until Stone Road East was realigned
3:03:00and a new road bridge was constructed alongside in 2004.
3:03:05The aerial photo on this slide shows
3:03:07the arched McQuillan's Bridge in the foreground
3:03:10and the largest Stone Road East bridge in the background.
3:03:14The 2002 Stone Road East environmental assessment
3:03:19sought to address the problem
3:03:21that McQuillan's Bridge did not have capacity
3:03:23to carry increasing vehicle traffic.
3:03:26The recommendation of the 2002 environmental assessment
3:03:30was that the road should be realigned
3:03:32and McQuillan's Bridge should be maintained
3:03:34in its existing position to protect its heritage value.
3:03:38Subsequently, McQuillan's Bridge was designated
3:03:41as a cultural heritage resource by City Council in 2004.
3:03:46Following the realignment of Stone Road East in 2004,
3:03:50McQuillan's Bridge served as a pedestrian river crossing route
3:03:52for recreational use,
3:03:55providing an important link
3:03:56in the local third-party trail system
3:03:59used by hikers, cyclists, community groups
3:04:02and educational institutions.
3:04:05In parallel with this study today,
3:04:07a Schedule C environmental assessment is currently underway
3:04:10to identify improvements for Victoria Road South
3:04:13and Stone Road East
3:04:14and is expected to be completed by the end of this year.
3:04:18The preliminary results of that EA
3:04:19have been taken into consideration
3:04:21as part of the McQuillan's Bridge study.
3:04:28McQuillan's Bridge is a single span
3:04:30concrete boasting arched truss bridge
3:04:33and is both an early example
3:04:34and now a rare survivor of this structural form.
3:04:38Due to its age, the bridge is more vulnerable
3:04:40to corrosion from weather
3:04:42and from the many years of road salt use.
3:04:45Structural maintenance has generally been limited
3:04:48to wingwall repairs in 1992,
3:04:51vertical member repairs in 1995
3:04:53and regular structural inspections.
3:04:56A detailed condition assessment was undertaken
3:04:59in October 2025 to inform this EA study work.
3:05:04The condition of the bridge is characterized
3:05:06as paw condition
3:05:08and the photos on this slide
3:05:09exhibits some of the key issues.
3:05:12These include exposed and crowding steel reinforcement
3:05:14and bearing plates
3:05:16and cracking and overturning in the wingwalls.
3:05:19Overall, the arches are in fairer condition
3:05:21than the deck and the hangers.
3:05:27A problem statement was developed
3:05:29to identify the challenge
3:05:30that the EA process needed to resolve.
3:05:32It defines the scope of the project
3:05:34and sets a benchmark to be used
3:05:36in the evaluation of alternative solutions.
3:05:39The problem statement developed for this EA study
3:05:42is to identify a solution from McQuillan's Bridge
3:05:45that allows for safe use by pedestrians
3:05:47and non-motorized transportation
3:05:49and that minimizes environmental, cultural
3:05:51and social impacts while maintaining
3:05:54the bridge's cultural heritage value
3:05:56in accordance with bylaw 2004-17357,
3:06:00to the extent possible.
3:06:03This problem statement reflects the feedback gathered
3:06:05through the community engagement for this study.
3:06:12In proximity to the study area
3:06:14is the Guelph Junction Railway line to the west,
3:06:17the Unveterra reformatory lands to the north
3:06:21and to the south is the Barber Scout Camp.
3:06:24There are several existing trail connections
3:06:25within the study area
3:06:27shown on the map on the left of this slide.
3:06:30The existing hiking trails shown
3:06:33are operated by the Guelph Hiking Trail Club
3:06:36and are not part of a city installed
3:06:38and maintained trail system.
3:06:40The trails are frequented by numerous community user groups.
3:06:45The north-south hiking trail
3:06:46on the east side of the river from York Road
3:06:49is shown in blue on the map.
3:06:51It passes under Stone Road and uses McQuillan's Bridge
3:06:54to cross over the river and connect
3:06:56to the north-south hiking trail
3:06:58on the west side of the river, which is shown in orange.
3:07:02The two hiking trails are included
3:07:03in the city's trail network mapping.
3:07:05The Guelph Trail Master Plan recognises
3:07:07that third-party trails are an important piece
3:07:10of the greater Guelph Trail Network.
3:07:14The Guelph Innovation District Secondary Plan
3:07:16identifies the need for a river crossing at this location
3:07:19to support the future city trail network,
3:07:22shown on the map on the right side of this slide.
3:07:26McQuillan's Bridge connects the existing hiking trail
3:07:29on the east side of the Oramosa River
3:07:31to the future Stone Road to Cooksmo Road Trail,
3:07:35which has been identified as a priority project
3:07:38in the Guelph Trail Master Plan.
3:07:41This desired connection was discussed
3:07:42with city's park and trail development team
3:07:45and trail user groups and is planned
3:07:47as a future city trail segment.
3:07:54Key natural features within the study area
3:07:56include the Oramosa River and its floodplain and valley lands,
3:07:59the Oramosa Springs Creek
3:08:00provincially significant wetland complex,
3:08:03areas of significant woodlands, cool water fish habitat,
3:08:07and species that risk bat habitat.
3:08:10The Oramosa River together with the Speed River
3:08:12are the primary ecological linkages
3:08:15within Guelph's natural heritage system.
3:08:18Most of the study area is below the floodplain elevation
3:08:21and is regulated by the Grand River Conservation Authority.
3:08:24The abutments of the existing bridge
3:08:26are positioned within the river channel.
3:08:29This restricts the hydraulic capacity of the river
3:08:31and also affects fluvial processes
3:08:34including sediment transport and erosion.
3:08:38The hydraulic performance of the site
3:08:39is also affected by the downstream Stone Road Bridge.
3:08:43I'll now hand over to Jack Marlon,
3:08:45the city's heritage planner,
3:08:46to speak about the cultural heritage.
3:08:54Thank you, Kate.
3:08:56As was mentioned, City Council designated
3:08:59McQuillan's Bridge in 2004 under part four
3:09:02of the Ontario Heritage Act.
3:09:04Last month, Council further protected the bridge
3:09:07under part five of the Ontario Heritage Act
3:09:09by including it as an attribute
3:09:11of the Ontario Reformatory Heritage Conservation District.
3:09:17The bridge spans the Oramosa River,
3:09:19which was designated as a Canadian Heritage River in 1994.
3:09:24The bridge and the surrounding landscape
3:09:26is considered a significant heritage resource
3:09:29in the city of Guelph.
3:09:31It is known as McQuillan's Bridge
3:09:33because of its proximity to the lots queered
3:09:35and farmed by the McQuillan family.
3:09:38The bridge seen today replaced an older wooden bridge
3:09:41and was constructed in 1916 by Charles Mattiani,
3:09:44a local contractor and a native of Northern Italy
3:09:47who built over 50 bridges in the region.
3:09:51McQuillan's Bridge is the only example
3:09:53of a concrete bowstring truss form
3:09:55within the city of Guelph
3:09:57and is one of only a few remaining examples
3:09:59of this type in the country.
3:10:03As part of this EA, a cultural heritage report
3:10:06and a heritage impact assessment were completed
3:10:08and reviewed by heritage planning staff
3:10:10and the Heritage Advisory Committee.
3:10:14Restoration of the bridge will require a conservation plan
3:10:17to ensure that preservation of the bridge
3:10:19abides by conservation best practice
3:10:22and that heritage attributes are not impacted
3:10:24or are minimally impacted during restoration.
3:10:28The conservation plan will be reviewed
3:10:30by heritage planning staff
3:10:32and shared with the Heritage Advisory Committee.
3:10:37Any significant changes to the heritage attributes identified
3:10:40in the designation bylaw will require a heritage permit
3:10:44which will involve review by staff and the Heritage Committee
3:10:48and approval by the general manager
3:10:49of planning and building.
3:10:52If removal and replacement become necessary,
3:10:55an application to demolish the bridge
3:10:57would need to be submitted to heritage planning
3:11:01for review by staff and consultation
3:11:03with the Heritage Advisory Committee.
3:11:06In accordance with sections 34 and 42
3:11:09of the Ontario Heritage Act,
3:11:11council would have 90 days to consult
3:11:13the Heritage Advisory Committee
3:11:15and approve or refuse a demolition application.
3:11:19If all attributes of the bridge were removed,
3:11:21council would have to repeal the designation bylaw
3:11:24and amend the Ontario Reformatory
3:11:26Heritage Conservation District bylaw.
3:11:29I will now hand it back to Kate.
3:11:42Okay, so given the age of the McEwen's Bridge
3:11:45and its known cultural heritage value,
3:11:47an environmental assessment is required
3:11:49under provincial regulations
3:11:50to guide decision making for the structure.
3:11:54We have followed the municipal class
3:11:56environmental assessment process
3:11:57for Schedule B bridge projects.
3:12:00We have moved through these phases at an accelerated pace,
3:12:03recognizing the need to reach a decision
3:12:05both quickly and carefully.
3:12:07Phase one began with the development
3:12:09of the problem opportunity statement
3:12:10and a public open house in November 2025.
3:12:13This was followed by phase two,
3:12:15evaluating options to identify a preferred alternative,
3:12:19including a second public open house in February this year.
3:12:22We're now at the point of preparing
3:12:24the project file report for public review.
3:12:27Following an approval of the recommended solution
3:12:29by council, the notice of completion will be filed
3:12:32with the Ministry of Environment Conservation and Parks.
3:12:35This will trigger a 30 day public review period
3:12:38after which the environmental assessment
3:12:40will be considered complete
3:12:42and the project can move forward
3:12:44to the implementation phase.
3:12:49Extensive internal and external consultations
3:12:52have taken place to determine
3:12:53the preferred approach from McEwen's Bridge.
3:12:56Through two public open house events and online engagement,
3:12:59we have heard from residents and community groups,
3:13:02including the Guelph Trail User Committee,
3:13:04the Guelph Outdoor School
3:13:06and the Guelph Historical Society.
3:13:08Through the public engagement activities,
3:13:11we heard concern about the condition of the bridge,
3:13:14interest in preserving the heritage value of the bridge
3:13:17and support for its value as a trail connection
3:13:20across the river.
3:13:22The project team established consultation opportunities
3:13:25with First Nations partners in accordance
3:13:27with the requirements of the municipal class
3:13:29environmental assessment, all city policies
3:13:32and best practices and direction
3:13:35from the Ontario Ministry of the Environment,
3:13:37Conservation and Parks.
3:13:39Consultation included issuing project notification letters,
3:13:43offering meetings to discuss the project
3:13:45and providing copies of relevant reports for review,
3:13:48including a stage one archeological assessment.
3:13:52No significant technical concerns
3:13:54have been identified at this stage of the project.
3:13:57Further engagement and coordination
3:13:59with First Nations will be undertaken
3:14:01throughout the detailed design work.
3:14:04The project team received feedback
3:14:06on the EA preliminary findings
3:14:08from the Heritage Advisory Committee
3:14:10and the Planning, Environment and Water Advisory Committee.
3:14:13We also integrated feedback from internal staff
3:14:17and from review agencies,
3:14:18including the Grand River Conservation Authority
3:14:21and relevant Ontario government ministries.
3:14:29So six alternative solutions were identified
3:14:31from McQuillan's Bridge,
3:14:32and these were presented for feedback
3:14:34as part of the consultation and engagement work.
3:14:37Alternatives which would not meet
3:14:39modern safety and durability requirements
3:14:41were not considered.
3:14:43Alternative one is the do nothing scenario,
3:14:46which we always include in an EA study as a default option.
3:14:49Under this scenario, the existing bridge
3:14:51would continue to age in place
3:14:53and would eventually deteriorate to the point of collapse.
3:14:56This alternative has a lifespan of zero years.
3:15:00Alternative two, rehabilitate and strengthen
3:15:02would preserve the main bridge elements.
3:15:05It would involve reconstructing the bridge elements
3:15:07that have low concrete cover
3:15:09and upgrading the barriers to meet modern design codes.
3:15:13This may alter the appearance of some bridge elements,
3:15:16such as the thickness of vertical members
3:15:18or the height of the railing.
3:15:20This alternative has an estimated lifespan of 30 years.
3:15:25Alternative three encompasses rehabilitating
3:15:28the bridge arches and replacing the deck
3:15:31with a new steel bridge
3:15:32that would sit between the two arches.
3:15:35Under this alternative,
3:15:36the arches would no longer support life loads
3:15:39and would serve a primarily decorative function.
3:15:42In terms of lifespan, it's a hybrid.
3:15:44The estimate is 30 years for the rehabilitated arches
3:15:48and 75 years for the new bridge deck.
3:15:53Alternative four would involve removing the existing bridge
3:15:56and replacing with a prefabricated steel bridge.
3:15:59This alternative has an estimated lifespan of 75 years.
3:16:04Alternative five would replace the existing bridge
3:16:07with a new concrete bowstring arch structure.
3:16:10This alternative also has an estimated lifespan of 75 years.
3:16:14And finally, alternative six would involve removing the bridge
3:16:18and widening the adjacent stone road bridge
3:16:21to provide the river crossing
3:16:22for people walking and cycling.
3:16:24This alternative has an estimated lifespan of 50 years
3:16:27because the existing road bridge is currently 20 years old.
3:16:33As mentioned earlier in the presentation,
3:16:35the city is undertaking a Schedule C
3:16:37environmental assessment for improvements
3:16:40to stone road east adjacent to McQuillan's Bridge.
3:16:43The preliminary findings of the stone road EA
3:16:46have been taken into consideration
3:16:47in the valuation of the alternative solutions
3:16:50for McQuillan's Bridge.
3:17:01So the alternative solutions were compared
3:17:03using natural, cultural, social, financial
3:17:06and technical criteria.
3:17:09Equal weighting was applied to the evaluation categories.
3:17:12No category was prioritized
3:17:14as more important than any other.
3:17:18The evaluation process determined that alternative one,
3:17:21do nothing, should not be carried forward
3:17:23because it did not meet the problem statement
3:17:25and scored poorly for other criteria.
3:17:29Alternatives two, three, four, five and six
3:17:33all met the problem statement and were closely ranked.
3:17:36The alternatives vary in lifespan
3:17:38and that has been taken into consideration
3:17:40in the financial evaluation.
3:17:43I'll highlight some of the key considerations
3:17:45in the scoring for each of the alternatives.
3:17:48Alternative two, rehabilitate and strengthen,
3:17:51scored highest overall in the evaluation.
3:17:54It would preserve more of the heritage features,
3:17:57the designated heritage features of the bridge
3:17:59than any other alternative solution
3:18:02and would maintain trail connectivity.
3:18:04Alternative two has limited opportunities
3:18:06for natural environment improvements
3:18:09and scored lower for financial and technical criteria
3:18:13due to the higher capital costs, shorter lifespan
3:18:16and the complexity of the rehabilitation work.
3:18:19The second highest ranked alternative solution
3:18:22was alternative four, remove and replace
3:18:26with a prefabricated steel truss.
3:18:29The new bridge with a wider span
3:18:30would increase hydraulic capacity for river flow.
3:18:33This alternative offers the most economical solution
3:18:37but would result in the complete loss
3:18:38of the heritage structure.
3:18:41Alternative three, rehabilitate arches,
3:18:44incorporating a new bridge was ranked third overall.
3:18:48Although it would protect the appearance
3:18:49of the main heritage attributes,
3:18:52it would not preserve the full functionality of the arch
3:18:54and has higher costs, shorter lifespan
3:18:57and higher technical complexity.
3:19:00Alternative five, remove and replace
3:19:03with a concrete boasting arch was ranked fourth overall.
3:19:07Although the wider span
3:19:09would increase hydraulic capacity for river flow,
3:19:12this alternative had the second highest overall costs
3:19:16and would result in the complete loss
3:19:18of the heritage structure.
3:19:21The last ranked alternative was alternative six,
3:19:24remove the bridge and widen the adjacent bridge.
3:19:26This alternative presents an opportunity
3:19:29for naturalization of the area
3:19:30and would increase hydraulic capacity.
3:19:33However, alternative six would result
3:19:35in the complete loss of the heritage structure
3:19:38and the trailer user experience would be lower quality
3:19:41due to the grade changes and the proximity to road traffic.
3:19:48So based on that evaluation,
3:19:50the recommended solution from a Quillen's Bridge
3:19:53is alternative two, rehabilitate and strengthen
3:19:56with an estimated project cost of $2.9 million
3:19:59for detailed design and construction
3:20:01and a design life of 30 years.
3:20:04A feasibility study will be required
3:20:06when the bridge is nearing the end of the 30 years
3:20:09to determine future options.
3:20:11Maintenance of the rehabilitated structure
3:20:14is estimated at $5,000 per year
3:20:17for annual cleaning of the structure,
3:20:19routine inspections and periodic concrete repairs
3:20:23and seal and replacement during the remaining service life.
3:20:26The bridge is considered a recreational asset
3:20:30and as such will not receive winter maintenance
3:20:32consistent with the connecting hiking trails.
3:20:36The preferred alternative solution
3:20:38carries technical risks that will need to be managed
3:20:40throughout design and construction.
3:20:42Rehabilitation requires complex design analysis
3:20:45and repair work and involves significant risk
3:20:48to bridge stability during construction.
3:20:52Staging of the construction will be critical
3:20:54to successful rehabilitation.
3:20:56Design engineers and contractors
3:20:58with Heritage Bridge experience are recommended.
3:21:02The scope of work and costs for rehabilitation
3:21:05will increase as the structure continues to deteriorate.
3:21:09The scope of work identified for this recommended solution
3:21:13is valid until September, 2028.
3:21:16After which time the condition of the existing structure
3:21:19and the scope of rehabilitation work
3:21:21would need to be reassessed.
3:21:24Staff will develop an interim maintenance plan
3:21:26for the existing structure
3:21:27to be implemented for the duration of the period
3:21:29until construction starts.
3:21:32The findings of this EA will be confirmed
3:21:35through additional investigations as part of detailed design.
3:21:39If the preferred alternative solution
3:21:41becomes unviable for any reason,
3:21:43the EA study identifies second and third
3:21:46preferred alternatives.
3:21:48These alternatives address the problem statement,
3:21:51but overall were ranked lower than the recommended solution.
3:21:55I'll now hand back to Kyle to conclude the presentation.
3:22:05Thank you, Kate and Jack for that.
3:22:08So the next steps for completing the EA
3:22:10and moving forward to implementation will include,
3:22:14hopefully here today, Council's approval
3:22:15to finalize the project file report
3:22:18and to submit a notice of completion
3:22:20with the Ministry of Environment, Conservation and Parks,
3:22:24known as the MECP.
3:22:26The MECP will allow for a 30 day public review
3:22:30following the findings
3:22:31during which the public may comment
3:22:33on the recommended solution.
3:22:36In parallel with the EA completion process,
3:22:39we'll turn our attention to moving forward
3:22:41with detailed design work.
3:22:44This will involve completing a preliminary design work
3:22:47and procuring services for the detailed design
3:22:50with the intentions of undertaking construction in 2028.
3:22:56So today, along with our staff, Kate, Jack and Jennifer,
3:23:01we have invited our consultants from RJ Burnside Associates
3:23:06who are also here to help respond to any questions.
3:23:10So we have our consulting engineer, Jeremy Cober
3:23:13and our consultant environmental planner,
3:23:17Michelle Rizwan, should we have questions for them.
3:23:20And with that, we'd like to conclude our presentation.
3:23:23Next, I'll pass it over to members
3:23:26of our Heritage Advisory Committee,
3:23:29Piper Boyd-Bell and David Camilletti.
3:23:33Thank you.
3:23:34Oh, sorry, thank you, Kyle.
3:23:37I just, before we move forward
3:23:39with the members of our Heritage Advisory Committee,
3:23:42I just wanted to make a note that I did receive notice
3:23:44from Councillor Gibson that he would be called in
3:23:47for this portion of the meeting.
3:23:49And so I just wanted to state that publicly
3:23:52and check in with Councillor Gibson if he's there.
3:23:55And next up to the podium will be David Camilletti.
3:24:00Who's with us here in person?
3:24:10Good afternoon, members of council.
3:24:12I'm David Camilletti.
3:24:13I'm a member of the wealth Heritage Advisory Committee.
3:24:18I just wanted to give a brief background
3:24:20and my colleague Piper will give more of a,
3:24:24looking at the actual details.
3:24:26But Heritage, the Heritage Advisory Committee
3:24:29gave a lot of thought to this very important question.
3:24:34And ultimately we did come up with supporting option two
3:24:38with option three as our backup.
3:24:41What's important, but we'd like to bring to your attention
3:24:46is what the process seems to be,
3:24:49what other communities seem to be doing
3:24:51in this type of situation.
3:24:54The structure that we're dealing with,
3:24:55it's a reinforced, it's technically,
3:24:59it's called a reinforced concrete bow string
3:25:02or truss construction of a bridge.
3:25:05And these were really popular in the 1920s, the 1930s.
3:25:09And what we were very interested to find
3:25:14is that there's a few,
3:25:16there are these types of bridges
3:25:18where they are in surrounding communities.
3:25:21For example, the best example is in London,
3:25:24there's a bridge called the Black Friars Bridge.
3:25:29It was built in 1875.
3:25:31And it was designated by the London Heritage Committee in 1992.
3:25:39And approximately the same amount of time
3:25:42after this designation as we're appearing,
3:25:45that's happening here in roughly 2013,
3:25:50there was a lot of deterioration noticed on the bridge.
3:25:53And what the city of London did
3:25:55was engaged in a rehabilitation project
3:25:59that took a number of years.
3:26:00But rather than replace it,
3:26:02they decided to work with the heritage aspects
3:26:05and with the practical side of preserving the structure
3:26:12and the heritage attributes as much as possible.
3:26:16There was between 2013 and 2017.
3:26:19Now we're 10 years roughly beyond that.
3:26:22But the cost of that was approximately three million.
3:26:26Our neighboring city, Kitchener,
3:26:28has something called the Freeport Bridge.
3:26:30That was built in 1926
3:26:33and designated as a heritage property in 2001.
3:26:39In the past couple of years,
3:26:40they're just a little bit ahead of us.
3:26:42They have looked at rehabilitation as well
3:26:47and it's been decided that they are going to engage
3:26:51in repairing as much of the heritage properties
3:26:54and attributes as they can and preserving that as well.
3:26:58Now the cost for that,
3:27:00which is going to take place between 2027 and 2028,
3:27:05is approximately five million.
3:27:07Brantford, another neighboring city,
3:27:10has something called the Brant Boat String Bridge,
3:27:14built in 1931, designated in 2006.
3:27:18That's probably going to be the next city
3:27:21that's going to have to experience
3:27:23a project like you are experiencing.
3:27:28So what I wanted to do and bring to your attention
3:27:31is that for this type of rare property,
3:27:35the municipalities that have been dealing with this before us
3:27:39are taking the approach that being recommended
3:27:43by the Guelph Heritage Advisory Committee and your staff.
3:27:46So it's a very, what we're asking you to do
3:27:51is not unique.
3:27:54It seems to be what other communities are doing
3:27:56for this rare and very significant type of historical attribute.
3:28:02So I'll hang around for any questions as well, Piper,
3:28:07but I'm going to invite my colleague to address you virtually.
3:28:13Thank you very much, Mr. Camilletti.
3:28:16Do we have Piper Boyd Bell online?
3:28:20Yeah, thank you.
3:28:21Can everyone hear me okay?
3:28:24Yes.
3:28:26Thank you.
3:28:27So in January, the Heritage Advisory Committee
3:28:29had the privilege of receiving a very similar presentation
3:28:32on the environmental assessment of McQuillan's Bridge
3:28:34from project manager Kate Berry.
3:28:36At that time, our committee moved and passed a motion
3:28:38in support of alternative two,
3:28:40and also moved to advise that alternatives one, four,
3:28:42five, and six were not preferred.
3:28:45We are here today to reiterate our firm commitment
3:28:47to the rehabilitation and strengthening
3:28:49of the existing structure.
3:28:51There's a photo of McQuillan's Bridge archived
3:28:53at the Guelph Civic Museum that was taken in 2002
3:28:55for Guelph's 175th anniversary photography competition.
3:29:00So I'm compelled to wonder why,
3:29:01as we approach the bicentennial year in 2027,
3:29:04that the heritage value of the bridge
3:29:05is being so rapidly denigrated.
3:29:08Why should something that was just 24 years ago
3:29:10thought synonymous with the history of the city
3:29:12be cast aside?
3:29:13As discussed, its heritage value was affirmed in 2004
3:29:16under part four, and just three weeks ago,
3:29:18it received part five designation from this council
3:29:21as part of the Ontario Reformatory Heritage
3:29:22Conservation District.
3:29:25The HCD plan made special allowance
3:29:26for the inclusion of McQuillan's Bridge,
3:29:28and before that, Stone Road East was designed around it.
3:29:31For over 20 years, staff and local organizations
3:29:33have protected and valued McQuillan's Bridge
3:29:35as part of the city's heritage.
3:29:37Yet a refrain for the argument of demolition is utility,
3:29:41that the bridge itself is a means to an end.
3:29:43However, I propose that just as a hike through green space
3:29:45can't be replaced by a walk on a treadmill,
3:29:48the bridge that stands today cannot be effectively exchanged
3:29:50for what is proposed as immediate modern convenience.
3:29:54In bright orange lettering at the base of the bridge,
3:29:56the words demolition by neglect were painted in 2024
3:29:59as part of a street art installation.
3:30:01I don't want to mince words in expressing
3:30:03that should demolition be proposed,
3:30:05it would stain the history of the site
3:30:06by affirming that its closure was in fact
3:30:08an act of demolition by neglect.
3:30:10It would be a mistake to historicize the utility
3:30:13of a bridge that has only recently been forced
3:30:14into retirement.
3:30:16Bridges must be maintained.
3:30:17It is a simple and frustrating fact
3:30:19that infrastructure degrades,
3:30:20but the damage already done is not irreparable.
3:30:23The heritage of wealth is carried across
3:30:25McQuillan's Bridge as it is seen by the trail
3:30:26and by the road.
3:30:28As it stands today, the tangible and natural heritage
3:30:30of the site hold within them the opportunity
3:30:32to mutually reinforce one another.
3:30:34So I hope that council will hear our strong support
3:30:36alongside the other voices that are raising today
3:30:38in support of the rehabilitation
3:30:39and strengthening of the existing structure.
3:30:42Thank you.
3:30:45Thank you for your presentation, Piper.
3:30:49Are there any questions for the members
3:30:52of the advisory committee?
3:30:57I am not seeing any.
3:30:58Okay, so what I'd like to do is ask
3:31:03that the recommendation be placed on the floor.
3:31:07Councillor Kerran has agreed to
3:31:09and I've got Councillor Downer,
3:31:11who's beside me willing to second.
3:31:14With that, I'd like to ask my colleagues
3:31:16if you have questions for staff.
3:31:19Mayor Guthrie, Councillor Allt,
3:31:21Councillor Kerran, that Councillor Hauser,
3:31:25Councillor Caton.
3:31:27We'll start with you, Mr. Mayor.
3:31:29Okay, thank you and through you, Madam Chair, to staff.
3:31:33I just really have one question to clarity
3:31:37and I just wanna make sure I'm hearing it right.
3:31:39So about $3 million as the recommendation
3:31:46and that will last about 30 years
3:31:52versus about $1.2 million
3:31:58and it would last 75 years.
3:32:01And both of them would enact the ability
3:32:06to cross over that area.
3:32:13Through you, Chair, to the Mayor,
3:32:15that's a correct, your assessment is correct
3:32:18of those two options.
3:32:19Okay, thank you.
3:32:23Thank you for the question, Councillor Allt.
3:32:27Thank you very much, Madam Chair.
3:32:32I have a number of questions
3:32:34and I'll just direct them to staff generally.
3:32:37A comment was made that this particular bridge
3:32:41would not support public use
3:32:44and I was wondering if that could please be clarified.
3:32:47I was taken on a tour by a structural engineer
3:32:50who does have tremendous experience
3:32:52in concrete and bridges
3:32:54and he made mention that it was not structurally sound
3:32:58or he would not recommend it be structurally sound
3:33:01for automobiles but for pedestrians
3:33:04that it could very much be considered structurally sound
3:33:08but there was work to do.
3:33:10And not being an engineer,
3:33:12I'm hoping you can help me with that.
3:33:19Yeah, through the Chair, to Councillor Allt.
3:33:20I think what I can say is the city does
3:33:23structural inspections of our assets
3:33:25and so with respect to the bridge,
3:33:27we've been doing those
3:33:28through a third party structural engineer
3:33:29and they've done detailed analysis.
3:33:31In fact, for the EA, there was a more detailed analysis
3:33:34done on the bridge's integrity
3:33:36and so we rely on those third party structural engineers
3:33:39to help us inform the decisions
3:33:41on when we should prioritize these types of improvements
3:33:44and that's why the work is here today.
3:33:46And thank you very much
3:33:47and perhaps it is to the outside engineers
3:33:51that I need to address some of these then.
3:33:55Robert, the engineer that I'm talking about
3:33:57made reference to the superstructure
3:33:59and the infrastructure is being relatively sound.
3:34:03I was wondering if perhaps our consultants
3:34:05could comment upon that.
3:34:15Through the Chair to Clerks,
3:34:17can you confirm if our consultants are online?
3:34:22We're looking for Jeremy.
3:34:25Through you, Mr. Mayor,
3:34:26just give me one or two minutes to confirm.
3:34:27I think we can have some folks added in online.
3:34:31I might just need to turn their cameras on
3:34:33in order for us to see them.
3:34:35Thank you.
3:34:36Actually, I'll carry on then with another question.
3:34:38Ms. Berry made reference
3:34:40to Schedule C Environmental Assessment
3:34:42and I was wondering just for the public
3:34:44who are concerned about that,
3:34:45what precisely does a Schedule C Environmental Assessment mean
3:34:50and what are the obligations that are carried with that?
3:34:57Through the Chair to you,
3:34:58Councillor Allt to try to give a concise response,
3:35:02Schedule C
3:35:06is a more extensive process in the EA process.
3:35:09It takes it a further stage.
3:35:11So if you recall,
3:35:12the process diagram I showed you in the presentation,
3:35:16for this EA, we're doing a Schedule B,
3:35:19so we finish at what's,
3:35:22after the first two phases of work,
3:35:24we wrap up with our project report.
3:35:26In a Schedule C,
3:35:27you continue the work further to develop from,
3:35:31once you've chosen the preferred alternative solution,
3:35:34you then look at the options for design concepts
3:35:39and do further evaluation and engagement
3:35:42to determine the preferred design concept.
3:35:44So it takes it further, it does additional studies
3:35:48and you complete with an environmental study report.
3:35:53So the parallel Schedule CEA
3:35:56for the Victoria Road and Stone Road
3:35:58is following that process.
3:36:00It has a slightly longer timeline to reach its conclusion,
3:36:02which we expect at the end of this year.
3:36:05Thank you, that actually helps me as well.
3:36:08There are a couple of government's issues as well that I have.
3:36:12Reference was made to the difference
3:36:14between $1.7 million and $3 million, essentially.
3:36:19From a government's perspective,
3:36:21can we actually accurately predict what the costs of
3:36:26enhanced replacement will be at this point
3:36:30or are there other aspects and considerations
3:36:32that we must have?
3:36:39Through you, Madam Chair.
3:36:43So we have these cost estimates
3:36:45at this stage of study work.
3:36:49Those are all done to the same kind of level of detail,
3:36:53but we would, when we move to detailed design,
3:36:56we do further study work, we develop the design
3:37:00and the cost estimate would evolve
3:37:03and would be updated based on the next stage of work.
3:37:07So this is kind of the estimates that we have
3:37:10are appropriate to this level of study.
3:37:14Thank you very much, I appreciate that.
3:37:17Now, the other issue that is a governance issue
3:37:20is we are somewhat bound, I understand,
3:37:24by parts four and part five,
3:37:25protection under the Ontario Heritage Act.
3:37:28What does that actually mean
3:37:30for what we are doing here right now?
3:37:37Through the mayor, the Heritage Act instructs
3:37:41that council is bound by the guidelines
3:37:45of the Ontario Reformatory Heritage Conservation District.
3:37:51However, council is the approval authority
3:37:54and can make amendments to the district plan
3:37:59as well as approve a heritage permit
3:38:01to alter or demolish a designated structure.
3:38:05So within parts four and parts five,
3:38:09we could actually modify parts four and parts five
3:38:14without affecting parts four and part five
3:38:17and their applicability elsewhere,
3:38:19or do we need to rescind them and do it all over again?
3:38:25Through the mayor, depending on the extent of alteration,
3:38:31for example, if most of the heritage attributes
3:38:36were removed from the bridge,
3:38:37we would have to repeal the part four designation bylaw
3:38:42as well because the bridge is a heritage attribute
3:38:45of the part five bylaw,
3:38:46we would have to amend the Heritage Conservation District Plan
3:38:51which would reopen it to appeal.
3:38:54Just to clarify when you say reopen it,
3:38:56how extensive is that?
3:38:58Is it just a paper actor?
3:39:00Is it something that has a significant process to it?
3:39:05It would significantly impact heritage planning staff's
3:39:08work plan for the remainder of 2026.
3:39:11Thank you.
3:39:12Now the application to demolish contains
3:39:15within a review and a consultation
3:39:17that must occur within 90 days.
3:39:19I believe that's just the consultation
3:39:22and the review must occur within 90 days.
3:39:24Do we have an understanding
3:39:27of what the actual outside estimate is on the timeframe
3:39:30for something like that?
3:39:35If council directed staff to initiate
3:39:39a heritage permit application for demolition today,
3:39:45heritage planning staff could return to council
3:39:48at their September 9th council planning meeting.
3:39:53During the lame duck period.
3:39:55Okay, last question, I believe, Madam Chair.
3:39:59A question came to me from a resident
3:40:01who is somewhat perplexed by the city,
3:40:05requiring residents to adhere to the Ontario,
3:40:09to the heritage designations, but the city might not.
3:40:12I'm wondering if we could get any comment on that,
3:40:15on the veracity of the city actually determining
3:40:20not to adhere to its own heritage requirements
3:40:22when we require residents to do that.
3:40:29Under the Ontario Heritage Act,
3:40:31city council is the approval authority.
3:40:35So you are, you can determine whether or not
3:40:41you want to abide by a designation by law.
3:40:45And finally, then, do you have an opinion
3:40:46on the optics of that,
3:40:47or would you rather leave that for us councilors?
3:40:52No comment, respectfully.
3:40:53Thank you.
3:40:57Moving forward.
3:40:59Excuse me, Madam Chair.
3:41:00Yes. Through you to Councillor Allt.
3:41:03We do have our consultant online now.
3:41:06So if you had that one follow-up question.
3:41:09Thank you.
3:41:12And I don't know whether the consultant heard it,
3:41:15but I had, a person I know who takes great interest in this
3:41:20and is a structural engineer and a concrete and bridge expert
3:41:25believes that the superstructure and the infrastructure
3:41:27is, quote, relatively sound but needs some work,
3:41:30and that the bridge itself actually,
3:41:33while it could not take automobile traffic,
3:41:35is relatively sound with repairs for pedestrian traffic.
3:41:39I was wondering if you could comment on that, please.
3:41:43Good afternoon, Councillor Allt and Council.
3:41:46We concur with that assessment that the bridge itself
3:41:50is relatively sound.
3:41:53The main load carrying capacity being the arches themselves
3:41:56are in relatively good condition.
3:41:59The studies that we did confirm the concrete
3:42:01compressive strength is adequate for the loading
3:42:04that the bridge is expected to experience.
3:42:08The rehabilitation options, option two would look at
3:42:15repairing and replacing the elements that are currently
3:42:20in a state of disrepair, which would help to reestablish
3:42:23the load carrying capacity of the bridge.
3:42:27Thank you very much. And thank you, Chair.
3:42:31Thanks on the speaker's lift.
3:42:32We have Councillor Caron, please.
3:42:34Great, thank you, Madam Chair.
3:42:36A couple of questions and then you entertain comments
3:42:39at this time or should I wait for that?
3:42:41I'll just do my questions first and see how that goes.
3:42:45In the evaluation summary in the EA,
3:42:48option four and five were given points
3:42:50for cultural heritage.
3:42:51And I'm just curious about that if those are options
3:42:55that involve complete removal and no restoration
3:42:58of any elements of the architectural heritage,
3:43:01which is the designated property
3:43:05that we're talking about today.
3:43:07Can you give me an idea why that was given any points at all?
3:43:13Through you, Madam Chair, to Councillor Caron.
3:43:16Yes, I think it becomes more clear
3:43:20if you delve into the report and the appendices
3:43:23with the detailed evaluation matrix
3:43:25because there are several subcriteria
3:43:28that make up the score for cultural heritage.
3:43:32So there are three components.
3:43:34The first is temporary or permanent impact
3:43:37to cultural heritage landscapes.
3:43:40The second is temporary or permanent impact
3:43:42to built heritage resources and heritage value of the bridge.
3:43:47And the third was impact on archaeological resources.
3:43:51So alternatives four and five, the replacement options,
3:43:56they do score very low in terms of
3:44:02they score poorly because they do have impact
3:44:05on heritage landscape and on the heritage value
3:44:08of the bridge, but they score some points
3:44:10in the third category, which was impact
3:44:12on archaeological resources because it's been assessed
3:44:15that there's not expected, it's unlikely
3:44:18that there would be impact.
3:44:19So that's where those options are picking up some points
3:44:23if you like.
3:44:24Okay, that's helpful because I can see
3:44:26where they would get a sliver of points,
3:44:27but in the pie graph it looks like they got a 25% ranking.
3:44:31And yet I understand the heritage landscape for part five,
3:44:35but the part four designation is the structure itself.
3:44:38So I mean, I'm not gonna argue with the EA
3:44:41because that's not my area of expertise.
3:44:44The other thing about option two
3:44:46when you confirm that there was a 35 year horizon,
3:44:49you're not suggesting that the bridge would fail
3:44:52at 35 years, my understanding is that
3:44:54that is when a reassessment would occur
3:44:57given that it is no longer a vehicular bridge,
3:45:00it is a pedestrian bridge,
3:45:02there wouldn't be a suggestion
3:45:04that that's a failure point at 35 years, is that correct?
3:45:08Through you, Madam Chair, that's correct.
3:45:10Yeah, it's just the point at which
3:45:12is a typical service life or a rehabilitated structure
3:45:15of this type at what point it would be appropriate
3:45:17to look at its condition and decide on next steps.
3:45:21Right, including resurfacing.
3:45:24And I don't know if there's anybody here
3:45:26who can speak to this, but for me,
3:45:27it's a question of comparison.
3:45:29So we just spent approximately $6.4 million
3:45:34on the Emma Earl Bridge, and there was no demolition required,
3:45:39there was an EA required,
3:45:42and that was a steel pedestrian bridge.
3:45:45So I just wanna confirm that that is the type of bridge
3:45:48you're talking about in the other options
3:45:50because I think it's described as a steel footbridge.
3:45:54And my understanding is that the difference in span
3:45:57is that Emma Earl was 81 feet,
3:45:59and this span of the river is 70 feet,
3:46:02so we're talking about an 11 foot span difference
3:46:05between the two bridges.
3:46:06Can you help me understand why Emma Earl Bridge
3:46:10would have been 6.38 million?
3:46:14And the option for here is being priced at 1.2, I believe.
3:46:22If it's the same type of bridge with a similar span.
3:46:30Through the chair to Councillor Caron,
3:46:32that's something we could take back
3:46:34and get a little more information on for you
3:46:37off the top of my head.
3:46:39I do believe the spans are quite a bit different.
3:46:43Emma Earl is a two span bridge,
3:46:46or this would be a single.
3:46:47So I think we can take that back
3:46:49and provide some more information on that.
3:46:52Okay, great, I was just using the width of the river,
3:46:55so similar.
3:46:57Those are all my questions.
3:46:59I think I'll finish with comments.
3:47:02Is that okay, or would you rather me wait?
3:47:05Any other questions?
3:47:06Let's do comments after.
3:47:07We've started with questions, if that's okay with you.
3:47:09I would prefer we keep comments till after.
3:47:12Okay, thank you.
3:47:14Next on my speaker's list is Councillor Houser.
3:47:20Thank you, through the chair to staff.
3:47:22I just wanted to clarify one of the presenters' mention
3:47:27of demolition by neglect,
3:47:28and in the presentation from staff,
3:47:31it talks about $5,000 maintenance fee
3:47:33that will, or maintenance that it will cost
3:47:35to maintain the bridge going forward.
3:47:39What is it costing now, or is it costing nothing?
3:47:42Like what is the maintenance that's being done up to date
3:47:47at this point, like yearly?
3:47:54Through the chair to Councillor Houser.
3:47:57So currently we are continuing with
3:48:02bi-annual Housum inspections, regular inspections,
3:48:06to continue to look at and assess the bridge as a whole.
3:48:14When looking at a future maintenance cost,
3:48:18the $5,000 is an estimate.
3:48:20Some years may require more,
3:48:21some years may require less,
3:48:23depending on what work would be required in that given year.
3:48:29What I can say is engineering,
3:48:30working with our operations team
3:48:32has created a service level agreement
3:48:34that we would work together to determine
3:48:38via those Housum inspections
3:48:40what work would be required in those given years
3:48:43and have our operations team do that.
3:48:46Should they be in a position to do that?
3:48:52Thank you.
3:48:55Councillor Katelyn, please.
3:48:58Thank you, through you, Madam Chair.
3:49:01So I'm just gonna address my questions
3:49:03to whomever knows the answer,
3:49:04because you all know better than I will.
3:49:08So I've heard a lot about the 30 years to reassessment.
3:49:12This is like, this is 30 years to the reassessment, right?
3:49:15It's not 30 years till disintegration,
3:49:18it doesn't implode after 30 years.
3:49:20What is happening after the 30 years
3:49:22that we need to be aware of?
3:49:25Through you, Madam Chair,
3:49:27I think that's similar to the question
3:49:29from Councillor Clarana, what happens
3:49:32when we get to the 30 year mark?
3:49:34We don't expect the rehabilitated bridge
3:49:37to suddenly crumble at that point.
3:49:39It's the time when it would be appropriate
3:49:42to assess its condition and check on
3:49:45what is appropriate as next steps,
3:49:48as further rehabilitation needed,
3:49:51or just a few minor repairs.
3:49:55So we see that as an appropriate timeline
3:49:59for when that should happen.
3:50:02Great, it's through the chair.
3:50:05Does the, for the removal option,
3:50:10does the cost for the replacement
3:50:13include the cost for all the heritage planning work
3:50:16and appeals, any other further studies,
3:50:18feedback engagement required,
3:50:21and the demolition of the current bridge?
3:50:25Through you, Madam Chair,
3:50:26no, essentially it does not.
3:50:28The option one, do nothing, was not carried forward.
3:50:33So the sort of detailed financial evaluation
3:50:38was not pursued for that option.
3:50:41It does not meet the...
3:50:42To be clear, this is for the replacement.
3:50:45Oh, sorry.
3:50:46So within the replacement,
3:50:47I've heard that we have to redo all of these other plans,
3:50:51reopen things, do feedback engagement,
3:50:54contact heritage, planning,
3:50:57like our committees, everything else.
3:50:59Like there's a lot of process involved there,
3:51:01and then we can have appeals through citizen groups
3:51:04and other things like that.
3:51:05So I'm wondering, what would be the total cost
3:51:07should we have gone down that path?
3:51:09So that's not included.
3:51:10That's just straight up building the bridge costs.
3:51:16Through you, Madam Chair, that's correct.
3:51:17It does not include all of those what if scenarios.
3:51:23It is based on capital construction costs
3:51:27and future maintenance and replacement
3:51:30or rehabilitation costs and operation and maintenance.
3:51:36Great, thank you.
3:51:37Through the chair, sorry, I got a couple more.
3:51:40What work, you had mentioned that heritage work
3:51:44would be disrupted.
3:51:46So is that the only work that would be disrupted
3:51:48in order to go through all these heritage planning processes
3:51:50because I heard a lot of feedback engagement,
3:51:52I think that there's more teams involved with those.
3:52:04Through the chair, maybe I'll just jump in.
3:52:05I think the spirit of what you're suggesting there,
3:52:07Councillor Caden, is accurate.
3:52:09Certainly we have community engagement staff, HR staff,
3:52:12back of house staff that also have to support the teams.
3:52:15And so I think that's a fair comment.
3:52:18Okay, and with all the additional processes required,
3:52:25should council vote to remove the bridge,
3:52:29including the potential appeals and other things like that.
3:52:33Which of these two paths would be the fastest
3:52:35to regain access for pedestrians?
3:52:44Through the chair to Councillor Caden,
3:52:46I think that's a hard question to answer at the moment
3:52:50because we can't guarantee what sort of appeals
3:52:55or other issues we may run into during design
3:53:01and submission of our class EA,
3:53:04our submission of our heritage designation to remove.
3:53:10So that's a little hard to answer at the moment,
3:53:14not knowing those things.
3:53:16So is it hard to say that there's one path
3:53:19that kind of gives us a good schedule
3:53:21and one that is just kind of unknown?
3:53:23I would agree with that statement.
3:53:27Okay.
3:53:29And through the chair,
3:53:33is this about the same cost as the pedestrian bridge
3:53:37that we discussed in the Allen Street Bridge EA
3:53:40that would be about 15 meters away from the sidewalk
3:53:44that's on Allen Street Bridge?
3:53:52I'm through the chair to Councillor Caden,
3:53:55that might be another takeaway.
3:53:58And I remember being about three million,
3:54:01like so my memory is bad.
3:54:04So if, I don't know if anyone remembers.
3:54:06If I can remember correctly,
3:54:09I believe we're removing the Allen's Bridge and looking.
3:54:13It was a pedestrian bridge.
3:54:15So we're looking at the pedestrian.
3:54:17I think what I can say to that
3:54:19is we're somewhat comparing apples and oranges there.
3:54:22We have a bridge that will be being installed
3:54:26in close proximity to other structures downtown at Allen's.
3:54:31So I believe that would be hard to compare
3:54:33these two bridges at this time.
3:54:36Oh, I'm just looking for the cost.
3:54:41I don't have that available.
3:54:42I can take that back.
3:54:44I'll come back at you in an email.
3:54:46Thank you very much.
3:54:49Thank you, Councillor Caden.
3:54:50Councillor Goller, please.
3:54:53Thank you, and through you chair class in.
3:54:56Well, thank you for all the work that you've done on this.
3:54:59I wanted to ask about the certainty of the cost.
3:55:02The amateur old bridges was previously broad.
3:55:05It was quoted as $3.6 million.
3:55:07I heard from staff that the actual cost to build
3:55:10was $5.1 million.
3:55:11They're about what is the certainty
3:55:13that if we go down the road of $2.9 million for alternative two
3:55:18by the time that it's built,
3:55:20could we be looking at $4.1 million or higher?
3:55:25Through you, Madam chair to Councillor Goller.
3:55:28So the construction cost estimate in the EA study,
3:55:34in the reports and the presentation,
3:55:37those are what we call a class C estimate.
3:55:41And it includes 20% contingency
3:55:45and a further 10% for contract administration
3:55:48and inspection fees.
3:55:50So we do have some contingency built in
3:55:53to that estimate as it stands.
3:55:59I think, and at the moment,
3:56:02we have an approved budget that has some float
3:56:05above that amount, above that current estimate.
3:56:09Okay.
3:56:10Yeah.
3:56:11Okay, thank you for that.
3:56:12So with that in mind on page four of the report,
3:56:14it talks about risk management and it says,
3:56:17preferred alternative number two,
3:56:20second preferred, it's alternative four
3:56:23to remove and replace with the steel bridge for 1.2 million.
3:56:27What is the threshold that it becomes unviable
3:56:31for any reason?
3:56:33Is it that it hits $3.5 million, $4 million?
3:56:36What is that threshold that you go from the preferred
3:56:39alternative that we're approving
3:56:40to the second preferred alternative?
3:56:45Through you, Madam chair,
3:56:46I think the threshold would not,
3:56:51it could be financial, but it could be purely technical
3:56:55and that we find issues through further investigation,
3:57:00through the detailed engineering modeling
3:57:03that would be needed that identify that for some reason,
3:57:08it is no longer feasible to rehabilitate.
3:57:12So we are keeping that scenario in mind
3:57:16in terms of those comments in the report.
3:57:21Okay, so we don't actually have like a firm threshold.
3:57:23So it could be that we're approving $2.9 million
3:57:26for alternative two today and it ends up getting built
3:57:28for six or $8 million and that would still be okay
3:57:32and their alternative two.
3:57:34Through the chair to councillor Goller.
3:57:38As many of you know,
3:57:39we have very robust project management office tools.
3:57:43So if through detailed design,
3:57:45all of a sudden this project staff found
3:57:48that this project was significantly,
3:57:51the proposal was significantly over the cost estimate.
3:57:55At that time we would take further actions
3:57:57which would most likely include coming back to council.
3:58:04If I could add there through the chair,
3:58:06I do think councillor Goller,
3:58:07the uncertainty aspect that you're getting at here
3:58:10also applies to all of the alternatives.
3:58:11And so it's a fair question and line of thinking
3:58:14and we've seen that on some projects in years gone by,
3:58:18maybe an estimate was made,
3:58:19but also we can't control sort of external factors either.
3:58:23So the cost to design and construct a material bridge
3:58:26went up over time as the prices of steel went up
3:58:29or as other things occurred sort of outside
3:58:31of staff's control.
3:58:32Those things would always be monitored,
3:58:34they'd always be brought back to council through budget.
3:58:37And so you'd see those updated estimates,
3:58:38but if additional analysis was done
3:58:41and we found issues with the structural steel,
3:58:43maybe there's more corrosion,
3:58:44maybe there's more degradation
3:58:46than based on the work done now,
3:58:48then staff would have to come back
3:58:49and kind of have those conversations.
3:58:51And that's I think part of what the EA is trying to get at,
3:58:53which is there is a bit of time sensitivity
3:58:56to implement the recommended or preferred solution
3:59:00based on those types of factors.
3:59:02Okay, thank you very much for that.
3:59:05I really appreciate it.
3:59:07And one of my concerns through you, Chair Klassen,
3:59:10is that the city's facing increasing financial challenges
3:59:14for residents.
3:59:16We are actively looking for cost savings.
3:59:18Is this comments or is it a question?
3:59:20It's a question.
3:59:20Okay, excuse me, sorry.
3:59:21Yeah, no, it's good.
3:59:22It's good.
3:59:23We are looking for cost savings
3:59:27and there is a significant difference
3:59:30between alternatives two and three
3:59:33and then alternative four.
3:59:34So as you move forward,
3:59:36do you have opportunities to try to reduce the cost
3:59:39of the $2.9 million or is that really a floor
3:59:43and it can likely go up from there?
3:59:52Through the chair to Councillor Goller,
3:59:55I think given the current cost estimates,
3:59:59that that's what we would expect.
4:00:02Obviously, if we can find cost savings in any project,
4:00:05we would look to reduce those costs.
4:00:08However, given the current studies,
4:00:11this is the best estimate we have at the moment.
4:00:14Okay, thank you.
4:00:15And then my last question to your Chair Klassen.
4:00:18Councillor Caton talked about the potential of us
4:00:20being taken to a tribunal which extends the timelines.
4:00:23From our experience, if there are challenges,
4:00:26if we were to say, not go down the road of alternative two,
4:00:30but say we say we wanna go down the road of alternative four,
4:00:34we have to redo parts of the EA.
4:00:37And if there are challenges,
4:00:38how long in our experience would it delay a project
4:00:42to have to redo that EA?
4:00:45And as I understand it,
4:00:47could you tell me what it would take?
4:00:48Like what work would you need to do on your end?
4:00:51And if there's a challenge,
4:00:53when would we be looking at a bridge being built?
4:00:58Through the chair to Councillor Goller,
4:01:01through our experience as this has not happened,
4:01:04we have not had Council direct us to go back
4:01:07and look at the scoring criteria for our projects.
4:01:11So it is a little difficult to say,
4:01:14but what I can say is we would be looking at
4:01:18further engagement on the new,
4:01:20sorry, we would have to go back
4:01:22and look at the weight in scoring.
4:01:24We would bring that back to Council.
4:01:26If that results in a different alternative,
4:01:29we would have to do further engagement on that
4:01:33prior to submitting our completion notice to the MECP.
4:01:39There are always the potential for appeals
4:01:44through that process.
4:01:46As well as in the meantime,
4:01:48we would have to start the demolition process
4:01:54with our heritage planning staff and work through that.
4:01:58As Jack has indicated,
4:01:59we would bring that back our September 9th meeting,
4:02:04which again, and have Council vote on that,
4:02:07which again opens ourselves up to potential appeals.
4:02:12So not knowing what the outcome of those could be,
4:02:16it's hard to state what the exact timeline to get going
4:02:20on this project would be given
4:02:24if we were to go to a different alternative.
4:02:28I appreciate that,
4:02:29but we have been taken to tribunals in the past.
4:02:31What is the timeline that it usually takes
4:02:33us to resolve those cases?
4:02:36I'm thinking emittorial,
4:02:38that it was delayed by a significant period.
4:02:41Through the Chair to Councillor Goller,
4:02:45receiving information that OLT appeals
4:02:48could probably take six and nine months.
4:02:51Section 16 order from the MECP could take anywhere
4:02:57from six to 12 months.
4:03:01Those are sort of the timelines we would be looking at.
4:03:04Okay, thank you very much.
4:03:05Thank you, Chair.
4:03:06I do have comments for after.
4:03:08Thank you.
4:03:09Next on the speaker's list is Councillor Downer, please.
4:03:13Thank you.
4:03:14So I just want to confirm one thing.
4:03:16So the 1.2 million,
4:03:19and that's an estimate too right now,
4:03:22as well as the one on the preferred.
4:03:25That does not include the demolition
4:03:28of the existing bridge
4:03:29and what you would have to do with those materials.
4:03:38For the steel prefab,
4:03:39I'm talking about the steel prefab one,
4:03:41there's no demolition costs.
4:03:43Do we know what those demolition costs would be?
4:03:45Through the Chair to Councillor Downer,
4:03:48that would just be the design and construction costs.
4:03:52There would be additional demolition costs
4:03:54on top of that.
4:03:57We don't have any costs for that.
4:04:03And dispose of those materials.
4:04:05I don't know if there's kind of...
4:04:06Through the Chair, if our consultant is still on,
4:04:11Jeremy might be able to help us
4:04:14with a closer cost for that.
4:04:19Good afternoon.
4:04:20Demolition costs were included in the estimates
4:04:22for options four and five and six.
4:04:28So those are included.
4:04:30Okay, cause I thought we heard earlier that they were included.
4:04:32Through the Chair, I stand corrected on that.
4:04:34Thank you, Jeremy.
4:04:35Okay, that really does take a big gap then
4:04:37between the 1.2 and the MURL,
4:04:41which is kind of in price,
4:04:44which I think we'd like to hear a bit more about.
4:04:48The other thing, you could help me with this 30 years.
4:04:52So this bridge was built in 1916.
4:04:58Until 2005, which is 90 years,
4:05:01it was taking traffic.
4:05:03I remember in the last quite a few years,
4:05:05it was taking trucks over that bridge.
4:05:08So it lasted 90 years,
4:05:10and we're going to rehabilitate and strengthen it
4:05:16for pedestrians and cyclists.
4:05:20How does that go from 90 years with car and truck traffic
4:05:25to 30 years with people walking over it
4:05:28after it's been rehabilitated and strengthened?
4:05:32And so I just sort of wonder about that.
4:05:37The math is not like working in my head.
4:05:39It's like, okay, I'm gonna rebuild and strengthen my house.
4:05:43That's 100 years old,
4:05:44but it's only gonna last another 30 years.
4:05:47Like I'm just sort of,
4:05:50we're gonna have to reassess it.
4:05:52So are you suggesting that any other bridge
4:05:54we wouldn't reassess for 75 years in our city?
4:05:59Like just this one, if it was rehabilitated and strengthened.
4:06:02So I'm just trying to go from the 90 to 30 years,
4:06:05and it was 90 years with truck traffic and cars,
4:06:09and now at 20 years on top of that
4:06:11with pedestrian and cycle traffic.
4:06:14And now we're saying, oh no, only 30 years.
4:06:17So I'm just trying to think about this assessment issue
4:06:21because I would hope we'd be assessing all of our bridges
4:06:25more regularly than 75 years.
4:06:29Through the chair to Councillor Downer,
4:06:31we do owe some inspections on all of our bridges as required.
4:06:38I believe the length between those
4:06:41are dependent on the age of that infrastructure.
4:06:44So we do regular structure assessment
4:06:50on those structures.
4:06:52I believe, and I'll look to our consultant in a minute
4:06:56to maybe correct me, but I believe,
4:07:01yes, it lasted 90 years.
4:07:03We are not replacing all of the material of that bridge.
4:07:07We are strengthening what is there
4:07:09that 110 year old concrete is still 110 years old.
4:07:14It will continue to degrade over time.
4:07:19It's not that it is brand new,
4:07:21so it does not restart the lifespan of that bridge.
4:07:28So it's not that it's gonna last another 30 years
4:07:33or the other bridges are gonna last another 75 years.
4:07:35It's after 30 years, you will want to assess
4:07:39the concrete in that.
4:07:40Because I suspect the concrete in my house
4:07:42is gonna hopefully last in a heritage house
4:07:46last more than another 30 years.
4:07:48Through the chair to Councillor Downer, yes.
4:07:50So we will continue to owe some inspections
4:07:54on this bridge as required.
4:07:56So it's not as though we would wait 30 years
4:07:59to do another inspection.
4:08:00We will continue to do owe some inspections as required,
4:08:05which those inspections do provide us
4:08:08with some maintenance that may be required.
4:08:13So we will not be waiting the 30 years
4:08:16to do another assessment.
4:08:18And we will would obviously try to keep the material
4:08:25up and rehabilitate throughout as much as possible
4:08:30to extend the life cycle of that material.
4:08:33So this bridge, if we go with this option,
4:08:36could last another 100 years then.
4:08:42Is that possible with proper maintenance?
4:08:46Through the chair, I will defer that potentially
4:08:50to our structural engineer.
4:08:54I'm just thinking of my house with its concrete basement.
4:08:57Like is it gonna last?
4:09:00Because it's over 100 years old.
4:09:03Good afternoon.
4:09:05The 30 year timeline that we're talking about
4:09:09for option two is an idea of when we would need to go in
4:09:15and reassess the bridge for its structural capacity
4:09:21and basically complete another feasibility study to revisit.
4:09:26Is it feasible at that time to complete
4:09:28another set of repairs?
4:09:30Or at that time, has the deterioration got so much worse
4:09:34that that time we would decide,
4:09:36do we need to repair it again
4:09:38or does it need to be replaced at that point of time?
4:09:41That's typical in the bridge world.
4:09:44Around the 30, 35 year mark is when a bridge
4:09:47that's brand new needs to be repaired
4:09:51in order to get your full lifespan out of the structure.
4:09:55So then all the bridges would need to be,
4:09:58rather no matter what option we pick,
4:10:00would need to be reassessed in 30 years
4:10:02is what you're telling me now, is what you're saying.
4:10:05In the future costs for the bridge,
4:10:09for each of the bridge options,
4:10:10there's a cost placed at the 30 to 35 year mark
4:10:14to account for kind of a major rehabilitation to the bridge,
4:10:19major repairs to the bridge.
4:10:21And those costs vary with each different option,
4:10:23but that prices at that 30 to 35 year
4:10:26timespan were included for each option.
4:10:29Okay, so every bridge would need to be reassessed
4:10:32in 30 years.
4:10:34Is that what you're,
4:10:36because that's not what we heard earlier.
4:10:37So I'm just clarifying this
4:10:40because there's a narrative out here
4:10:42that this bridge is only gonna last 30 years
4:10:45and the others are gonna last 75
4:10:48and now we're hearing, well,
4:10:50they're all gonna be assessed at 30 years.
4:10:53And one, like who knows,
4:10:55this one could last another 30 years beyond that
4:10:58with rehabilitation, the other one's the same thing.
4:11:01Is that what I'm hearing?
4:11:10The options with the 75 year design lifespan
4:11:13is based on,
4:11:18it's their design lifespan based on how they've been designed.
4:11:21So they're designed to last for at least 75 years.
4:11:24Every bridge requires repairs
4:11:27and the typical timeline for when repairs are required
4:11:29is that 30 to 35 year mark
4:11:32so that you can get your full 75.
4:11:34If you don't complete your repair at 35 years,
4:11:36it may not last the full 75.
4:11:39So at that 30 to 35 year mark,
4:11:42every bridge should have repairs completed to it.
4:11:45They could be smaller, they could be larger in scope.
4:11:47Right, so the option that's before us,
4:11:50the recommendation, the reassessment at 35 years
4:11:54could mean it could last another,
4:11:56may not last or it could last another 10 to 20
4:11:59to 25 years beyond that, is that correct?
4:12:03Yes.
4:12:03With rehabilitation, okay, good, thank you.
4:12:08Thank you, Councillor Downer.
4:12:10Next I have Councillor Gibson.
4:12:15Thank you, through you, Chair,
4:12:19Claeson, I appreciate it.
4:12:21A couple of questions for staff
4:12:22and I'm gonna take a second to encourage staff to just,
4:12:26I know this debate is around a few subject,
4:12:29I'm just encouraging staff to just give us the answers
4:12:34and don't allow sort of this,
4:12:37I feel like some hurdles are being put in your way
4:12:39and I'm just asking, encouraging you to be courageous
4:12:41and just tell us the facts,
4:12:42because I remember the Allen's Bridge EA
4:12:45and there was a number of councillors that spoke against that
4:12:47and I think they voted against finalizing the EA on that as well.
4:12:52And at the time they were advised this is a gate
4:12:54and again, I accept that this is a gate
4:12:57that council is going through
4:12:58to finalize a notice of completion for an EA.
4:13:02The issue that I will take with this EA is the scoring.
4:13:06So I'm speaking to a planning concern I have
4:13:10and how the evaluations were done.
4:13:12Obviously everyone's talking about the financial
4:13:15and I think the evaluation is fair on life cycle renewal.
4:13:19We've heard it very clearly from staff,
4:13:2130 years and 75 years are the two expected timelines.
4:13:25The financial are apparent, thank you Mayor Guthrie
4:13:28for making that very clear.
4:13:29But my question is on the natural environment
4:13:32and how this was scored in the EA.
4:13:35And I have some concerns about the table
4:13:38that was presented to council
4:13:40and the table that was presented to the public
4:13:42around the hydraulic function of this bridge.
4:13:45And it was very clearly stated from staff
4:13:47that the hydraulic function of the river would improve
4:13:50if we installed a clear spam bridge from bank to bank.
4:13:53Currently the existing bridge creates hydraulic.
4:13:57It constricts the hydraulic function of the river
4:14:01and as such that impacts GRCA flood programming
4:14:05that impacts upstream and downstream hydraulic function.
4:14:08And it was a clear benefit to move
4:14:10to a clear spam bridge option four, bank to bank,
4:14:14which would again, you've stated it twice tonight,
4:14:16it would improve hydraulic function.
4:14:18But why in your table were they scored the same
4:14:21on natural environment?
4:14:22Because one is clearly an improvement over the other
4:14:25and option two, which is the preferred alternative
4:14:27is scored the same as option four.
4:14:30And so I'm struggling with that assessment.
4:14:34I think if you pulled up your table, you could see it.
4:14:36It's, they're both scored three out of four
4:14:38for a natural environment, I believe.
4:14:41Through you, Madam Chair.
4:14:45Thank you for the question, Councillor Gibson.
4:14:49I'm not sure if you've looked at the detailed evaluation table.
4:14:52It's one of the appendices.
4:14:53I have not.
4:14:54The report.
4:14:55So the natural environment criteria has seven
4:14:59sub criteria within it that make up that score.
4:15:03And it is quite an interesting picture
4:15:04because there is a lot of variation
4:15:07across those sub criteria and across the alternatives.
4:15:11But what happens is that the bottom line
4:15:13where it's aggregated, unaveraged,
4:15:16it, you know, we end up with quite similar scores
4:15:21for several of the alternatives.
4:15:23So I think you have to delve into that detailed evaluation
4:15:27to perhaps see the nuance a little bit.
4:15:29One of the criteria is impacts to hydraulic capacity.
4:15:34And so for that sub criteria, yes,
4:15:36the options that keep the existing structure score lower
4:15:41than the options that would replace it
4:15:44and with a wider span for the reasons that you mentioned.
4:15:47So that is captured in the evaluation, but it doesn't,
4:15:52you know, it doesn't tip the overall
4:15:54natural environment score because of the other,
4:15:57the other sub criteria that are being taken
4:16:00into account as well.
4:16:03Okay, so I have to ask the question,
4:16:05what, given the fact that they have the same footprint
4:16:07and the same process, it's the same design
4:16:10and construction timeline,
4:16:12what are the environmental,
4:16:15the natural environment benefits of option two
4:16:18that are superior to option four?
4:16:22Because we've identified one that's clearly superior
4:16:24under option four, but what are the,
4:16:25what are the items that are superior under option two?
4:16:28Because that would have,
4:16:29there would have to be a waiting of that
4:16:32that would equalize, correct?
4:16:34Again, I haven't delved into the detailed evaluation,
4:16:37it just became apparent when I saw your,
4:16:39when I saw the table in the presentation.
4:16:50Through you, Madam Chair, but apologies,
4:16:51I was just taking a glance at the detailed
4:16:55evaluation table here.
4:16:57The categories were alternative to the recommended solution
4:17:02to rehabilitate and strengthen,
4:17:04where it scores slightly higher for natural environment
4:17:09is sub criteria number four,
4:17:11which is temporary or permanent impact
4:17:14on the habitat of species at risk.
4:17:18And also sub criteria number five,
4:17:21which is temporary or permanent impact on aquatic habitat.
4:17:25And so because we're working on the existing structure,
4:17:29we don't need to work in the river channel
4:17:33or make changes to the river channel.
4:17:35We're not having big impacts on the river banks
4:17:39and the habitat there.
4:17:40That's where the rehabilitation options score higher
4:17:44because they have a lower impact.
4:17:51I will respectfully disagree, but that's okay.
4:17:54This is what the exercise is for.
4:17:55This is what the EAs are for.
4:17:58On the design and construction costs,
4:18:00if I can just ask a few more questions,
4:18:02there's been a lot of conversation about the disparity
4:18:05between this project and the Emerald Bridge.
4:18:08Is it possible that this project is slightly more affordable
4:18:12because the design is so simple?
4:18:16Like the Clear Spam Bridge from bank to bank,
4:18:19this is an engineered solution.
4:18:21I challenged staff this morning about this being a design build,
4:18:24whether or not we even needed a detailed design
4:18:26for such a project,
4:18:27we could simply just tender it out to three people
4:18:29and say who could build a bridge
4:18:32and do it a cost effective way.
4:18:34Is there savings in the detailed design
4:18:38and construction aspect that,
4:18:41are there savings in the engineering
4:18:42and the fact that we don't need to over engineer this site
4:18:45because of its simplicity?
4:18:46It's a Clear Spam Bridge from bank to bank under option four.
4:18:55Through the chair to Councillor Gibson.
4:18:59Although the engineering costs
4:19:04to maybe select a pre-designed structure
4:19:10might be cheaper than the other ones,
4:19:12however, we still need to do assessments.
4:19:16So we still would need to do a geotechnical assessment
4:19:20of the site to where we would be placing those footings.
4:19:25We also need to do other sort of design criteria
4:19:31and permitting that would be specific to the site.
4:19:35So we would still have to apply to,
4:19:37let's say the GRCA for permit to fully replace that bridge
4:19:44and that would have to,
4:19:45we would have to show a site detailed design
4:19:48for part of that.
4:19:51Okay, that's fine.
4:19:55I have spoken with staff
4:19:58about the design and construction costs being simplified
4:20:00or being more expedient than the,
4:20:02like the option to preferred option with the restoration,
4:20:06but that's fair.
4:20:06We can agree to disagree on that.
4:20:09On my last comment, the last question, I guess,
4:20:11on the heritage demolition front,
4:20:14there was a situation alluded to by Councillor Allt
4:20:16about a resident speaking to how ironic it is that,
4:20:20we're forcing residents to abide by this rules,
4:20:22we're considering not abiding by it ourselves.
4:20:24And I just wanted to ask the process is the same, correct?
4:20:27If a resident wants to demolish a heritage structure,
4:20:30they put forward a Council application.
4:20:33Staff generally reject it,
4:20:35but it comes to Council anyway for approval.
4:20:38Similarly, if Council wanted to demolish a heritage asset,
4:20:42the same process would take place,
4:20:44it would come to Council for approval.
4:20:45Is that correct?
4:20:47Through the chair, that is correct.
4:20:49Okay, and I appreciate that.
4:20:51I guess what I'm saying is that there are members
4:20:53of this Council that have read over
4:20:57and surmised that a demolition of a heritage asset
4:21:02by a private resident was permissible.
4:21:04I'm one of those people that have voted
4:21:06for the demolition of a heritage asset
4:21:08when a private residence comes forward.
4:21:10So whether it's a private residence or the city
4:21:13making a determination as to what they want to do
4:21:15with an asset, it still comes to Council for approval.
4:21:18So there is no,
4:21:20I just wanted to make sure the public understood
4:21:21there's no disparity in process.
4:21:24If Council wants to do this or for private residence
4:21:26wants to do this, it's the exact same process
4:21:28Council has to decide for ourselves.
4:21:31Those are all my, I guess,
4:21:33I'll save maybe if I mind,
4:21:37Chair Klassen, I'll be very quick with my comments.
4:21:40Can I go to you first?
4:21:42Sure, no problem.
4:21:44After questions, I've got one more
4:21:46on the list of questions.
4:21:48I appreciate it.
4:21:49Okay.
4:21:51Councillor Chew, please.
4:21:56Thank you, through you, Madam Chair.
4:21:59I'm just trying to be very objective
4:22:00with how I look at the options.
4:22:02And personally speaking, I do like option four
4:22:06if we're really trying to preserve that linkage
4:22:09in good faith.
4:22:11I think like respectfully,
4:22:13like if we go through that appeal process
4:22:17and we're successful,
4:22:19it gets us out of some of those heritage obligations
4:22:22and it allows us to find a way to commemorate
4:22:26the built heritage structure in a tasteful way
4:22:28through some options that are presented in that report.
4:22:37I'm just curious, like for the end of the month,
4:22:39would it be possible for staff to give me
4:22:42that cost estimate for the Class C?
4:22:45I'm not sure if I'm able to find it through the EA page,
4:22:48but you can correct me if I'm wrong.
4:22:50So that's my first question, if that's possible.
4:22:57Through you, Madam Chair,
4:23:00could we just ask for clarification
4:23:02on what cost estimate you're looking for?
4:23:06Councillor Chew?
4:23:07Yeah, just for all the options in your evaluation,
4:23:11if there's a way in which we can disseminate that
4:23:13with the information that you guys currently have.
4:23:17Yes, that information is available.
4:23:19The draft project file report
4:23:22and all of the appendices are published
4:23:24on the city's project webpage.
4:23:27We can provide the link to that.
4:23:31So there's a detailed evaluation matrix table.
4:23:33It's one of the appendices.
4:23:34It has some cost information in there.
4:23:37There's also cost information within the body of the report too.
4:23:43And is that pretty much up to date
4:23:45and reflective of this conversation
4:23:48and for the end of this month?
4:23:52It reflects, through you, Madam Chair,
4:23:55reflects everything that we've presented today.
4:23:58It's correct, yeah.
4:24:00And is it possible if it's not done already
4:24:04for there to be a life cycle comparison
4:24:07for the steel bridge and the concrete bridge?
4:24:10I know through the options that it was alluded to
4:24:16through that report,
4:24:17but do you think before the end of the month
4:24:20we could have a bit more insights
4:24:23as it relates to this project?
4:24:27Through you, Madam Chair, to Councillor Chew.
4:24:29Yes, that information is already built into the study.
4:24:32It's part of the report.
4:24:34There is a life cycle analysis
4:24:37within the project file report that you can take a look at.
4:24:40It's fairly detailed.
4:24:43If there's more kind of questions around
4:24:45we can certainly provide more information.
4:24:47But I think I mentioned in the presentation
4:24:49that we have alternatives that have different lifespans.
4:24:53But that is built into the financial criteria evaluation.
4:24:59Okay, yeah, I'll take a closer look.
4:25:00You don't get that to you by the end of the month.
4:25:03Thank you.
4:25:04Thank you, Councillor Chew.
4:25:05Councillor Billings, please.
4:25:08To you, Madam Chair.
4:25:11I'm still struggling with respect to this lifespan issue.
4:25:15So the comment was, it doesn't matter, 30, 35 years
4:25:20we could have technical issues
4:25:22and it would be no longer able to rehabilitate this bridge.
4:25:27So for example, in the report it says,
4:25:30okay, the bridge footings will remain the same
4:25:33and no work in the water.
4:25:35So do we know technically
4:25:39how long can these footings last for?
4:25:42And then we hear about, well,
4:25:43the concrete is gonna continue to deteriorate.
4:25:47So are we really looking at whether 30, 35, 40 years
4:25:52we would have to demolish this bridge
4:25:55because it just would cost too much to replace?
4:26:02Through you, Madam Chair, to Councillor Billings,
4:26:04I think it's difficult for us to forecast the future
4:26:09of where we would be at that point in time,
4:26:11but I will defer to structural engineer Jeremy
4:26:15of whether he has any comment to add on that
4:26:18in terms of what we might expect
4:26:22for the lifespan of the structure
4:26:24and beyond that 30 year mark.
4:26:31Thanks, Kate.
4:26:34Beyond the 30 year mark,
4:26:37it is possible that the bridge could be renewed
4:26:41and repaired at that point in time
4:26:43to get us another 30 year period.
4:26:47It's just unknown what those costs could be at that time.
4:26:52And then so do you now, through you, Madam Chair,
4:26:55again, the concrete, more of the footings,
4:26:58a typical bridge like this,
4:27:00how long would those footings actually last?
4:27:05Typically the footings are not of concern
4:27:09on a bridge like this because the concrete
4:27:14is strictly in compression in those areas
4:27:18to get a little technical.
4:27:21The concern with these bridges is the art shape itself.
4:27:25And as long as that art shape stays intact,
4:27:29the bridge is...
4:27:36Okay, so then what you said...
4:27:38Sorry, Jeremy, I don't know if you cut out,
4:27:40I didn't catch that last part.
4:27:43Sorry, I think I was muted, I apologize.
4:27:50Would you please, Jeremy,
4:27:52just clarify what your last sentence was
4:27:54just once again for us, please?
4:27:57I apologize.
4:27:59As long as the arch part of the bridge maintains,
4:28:03its shape and its condition,
4:28:06the bridge would be re-able,
4:28:08it's possible to re-able it for another 30 years
4:28:11beyond the 30-year period.
4:28:15Okay, and so at that point then,
4:28:17because the concrete keeps deteriorating,
4:28:20so it could possibly be then in 30 years,
4:28:23we would have to put a few more million into that arch.
4:28:27Is that what you're saying?
4:28:29Yes, but yeah, just that cost is unknown at this point in time,
4:28:35but we would be in 30 years,
4:28:37we could potentially be back at where we are today.
4:28:40Okay, thank you for that, Jeremy, appreciate that.
4:28:46Thank you, Councillor Billings.
4:28:48I'm just looking around at my colleagues
4:28:50to see if there's any more questions.
4:28:53No, okay, and to quote Cam,
4:28:56lucky you, it is now my turn.
4:28:59Okay, my first question,
4:29:06I have two questions with regard
4:29:11to the heritage designation of the bridge.
4:29:17The first question is with regard to,
4:29:19some of my colleagues just have brought up
4:29:21some of the concerns with regard to
4:29:25de-heritaging the bridge,
4:29:29and I made up that word and you can add it to your dictionaries,
4:29:34but my concern here is,
4:29:36we've talked a little bit about the impact
4:29:39of what that would mean for our work plan,
4:29:43but I just wanted to go a little bit further with that
4:29:47and ask about the staff implications.
4:29:49So a couple of weeks ago,
4:29:51passed a motion to ask the provincial government
4:29:55if they could extend our timeline
4:29:57for heritage designations
4:29:59to allow our staff to have more capacity to complete those.
4:30:03We don't know if that will be extended or not,
4:30:05but the problem remains that we asked for it
4:30:09because we need the timing.
4:30:10So I just wanted to clarify
4:30:12what the staff implications would be,
4:30:15not just for this project,
4:30:16but for all of our other heritage projects that are in queue.
4:30:23Through the chair,
4:30:25I think I can confidently say that
4:30:27because this would require a heritage permit
4:30:30as well as repeal of a part four designation
4:30:34and amendment of a part five designation,
4:30:36that we would likely not be able to work
4:30:38on any more individual designations
4:30:40until this matter was resolved.
4:30:46Okay, thank you for that.
4:30:48And then my next question, I hope, is appropriate,
4:30:52but I just had a question
4:30:53with regard to the maintenance of McWilliams Bridge,
4:30:55and with regard to the timing of...
4:31:00Did we stop maintaining the bridge
4:31:02after it was decommissioned as a vehicular traffic bridge?
4:31:17To the chair.
4:31:20After...
4:31:22Let me, I apologize.
4:31:24Let me just ensure I have my dates correctly.
4:31:26But after the bridge in 2002, 2004,
4:31:34when Stoner was reconstructed,
4:31:37the bridge was no longer part of an active roadway
4:31:40and therefore was not part of our necessity
4:31:50to continue to maintain to the same level
4:31:55as a bridge in an active roadway.
4:31:57However, we did continue to do OSIM inspections
4:32:04to see in some ad hoc minor repairs as necessary.
4:32:09Throughout the years.
4:32:13Okay, thank you for that.
4:32:15And I just, I'd like to go back to a question
4:32:19that counselor Hauser had asked earlier,
4:32:23just because I wasn't sure if there was a number.
4:32:27So the question was regarding the cost to maintain it.
4:32:31So I'm guessing that based on your answer,
4:32:33there has been some ad hoc repairs.
4:32:34So is there a number with regard to how much it costs
4:32:39to maintain, I guess it's not been maintained,
4:32:41maintain it currently?
4:32:45Sorry, can you please, to the chair,
4:32:47can you please clarify, are you talking to maintain
4:32:50until we get to a point of reconstruction
4:32:53or are you talking about once we've reconstructed,
4:32:56what is that maintenance cost?
4:32:59The current costs annually.
4:33:05Currently, I apologize, I don't have the exact budget
4:33:11at this moment, but we could get that
4:33:15in conjunction with our operations team
4:33:17and get some, get a number back to you.
4:33:22Okay, thank you.
4:33:25All right, that is my, those are my questions.
4:33:30And now I'd like to move on to comments.
4:33:33And I know that there were quite a few that had comments.
4:33:37I did have counselor Gibson already on my list,
4:33:40but I would also like to ask my colleagues
4:33:43who else would like to comment at this time.
4:33:46Counselor Gowler, looking up at the screen,
4:33:50Counselor Katen.
4:33:54Also, Counselor Billings and Counselor Gibson,
4:33:57I don't see you up on the screen,
4:33:58but I just wanted to check with regard to comments
4:34:02if you wanna be on the list.
4:34:08Yes, no, okay.
4:34:09Yes, please, yes, please.
4:34:11And how's there and Quran?
4:34:17Let's start with Counselor Gibson.
4:34:20I really appreciate it.
4:34:20Thank you, Chair.
4:34:22My final two comments are my number one priority
4:34:26through this process is aligned with a secondary priority
4:34:30of the project, which is to improve the corridor itself.
4:34:34Currently right now, I don't believe the corridor
4:34:36is functioning properly along Stone Road.
4:34:38I've stated, I think publicly that I think
4:34:40it's a bit of a speed trap as you come over the hill
4:34:42on Stone Road and down into the valley,
4:34:43you go from a 60 down to a 40 very easily.
4:34:47We all know what it means to go 75 and a 60.
4:34:49You are speeding, but in this case,
4:34:52over about a 50 foot section of road,
4:34:54a 40 kilometer an hour sign pops up.
4:34:56And if you are speeding at 75 miles an hour,
4:34:59you're almost going twice the speed limit immediately.
4:35:02And the biggest story that I had was a gentleman lost.
4:35:05The suspended license was fired from his job
4:35:08all because he was making delivery at four in the morning
4:35:10to one of the plants out there
4:35:11and was pulled over for stunt driving.
4:35:15That was the designation at the time.
4:35:17So I do have a deep concern about this corridor.
4:35:19I want it fixed and I believe that option four
4:35:23is the most expedient way from a design,
4:35:26detailed design and construction methodology perspective.
4:35:29I think it can be faster.
4:35:30Although staff have told me that both option two
4:35:32and option four would follow a similar timeline.
4:35:3527 budget, 28 construction.
4:35:38So in closing, my last comment is,
4:35:40I think in the most professional way possible,
4:35:43I'm going to disagree with staff
4:35:44and their evaluation of the alternatives.
4:35:48I think financial evaluation needs to be given
4:35:51a little bit more weight.
4:35:53And I also believe from an environmental performance
4:35:55perspective on hydrology,
4:35:56and we all know how important flood water
4:35:58and flood maintenance and prevention is,
4:36:00being able to create a clear span bridge
4:36:03is a clear win over a constriction in a riverway.
4:36:06So I believe that that should have been evaluated
4:36:09a little bit further in option four.
4:36:11If the motion recommendation fails,
4:36:14I will put forward a motion to either defer
4:36:18or reconsider to staff other evaluation of the process.
4:36:23But I will wait to see how council votes on this motion.
4:36:27Thank you.
4:36:29Thank you, Councillor Gibson.
4:36:31Let me just quickly find my list.
4:36:33I lost it for a second.
4:36:36Madam chair. Councillor Goller, please.
4:36:37Sorry, Madam chair, do you mind if I just add a comment
4:36:41in response to a couple of things
4:36:42I've just heard in the last little bit.
4:36:43Just want to clarify, we do through state's FCA work,
4:36:46we have equal weighting on all the categories
4:36:48in terms of the way that the EA was applied.
4:36:50So I just want to say that out loud.
4:36:52The other thing I just want to clarify,
4:36:53just kind of picking up on the threads
4:36:55of some of the questions and comments is,
4:36:57we have done maintenance on this bridge
4:36:59over the course of time.
4:37:00And our operations department
4:37:01certainly does do minor maintenance work.
4:37:03When we talk about maintenance,
4:37:04there's different categories.
4:37:05The more major sort of structural rehabilitation
4:37:08type maintenance is different
4:37:09than maybe more routine maintenance.
4:37:12And so that routine maintenance certainly
4:37:13has occurred over the years.
4:37:14Our operations department is out there
4:37:17doing that work each year.
4:37:19So whether that's, you know, maybe there's some cracks
4:37:21or maybe there's some graffiti removal.
4:37:23Maybe there's some cleaning to do,
4:37:24whatever the case may be, we do do that work.
4:37:26And so I just want to make that comment out loud publicly
4:37:28that certainly the city has been doing maintenance
4:37:31on the McClune bridge.
4:37:34Thank you. DCG.
4:37:37Councillor Goller, please your next fair comments.
4:37:40Thank you, chair.
4:37:41And if you beg my leave,
4:37:43may I ask one more question of staff?
4:37:47Okay. Thank you.
4:37:49Staff, I just want to clarification
4:37:51because we're considering possibly like,
4:37:53what if we go with alternative four under alternative four?
4:37:57There was a sentence that said
4:37:58that it would have the new school structure
4:38:01could integrate some heritage considerations
4:38:04through sympathetic design.
4:38:06Could you tell me what that means?
4:38:15Through you, Madam Chair.
4:38:18I think, and Jack, I will look over to you
4:38:21after I've made some comments.
4:38:24The sympathetic design would be in terms of echoing
4:38:27the shape of the existing bridge, right?
4:38:30You have that opportunity to do that
4:38:33with a steel trust could be a straight rectangular shape.
4:38:36It could be arched.
4:38:39You have the opportunity.
4:38:41But I think what we've seen in the
4:38:44heritage impact assessment for this study
4:38:46is that you can't replicate the,
4:38:49there's no ability to replicate the heritage features
4:38:53of the bridge in a steel material.
4:38:55So it would really be only kind of honoring
4:38:58the shape of the structure.
4:39:00Jack, do you want to add anything to that?
4:39:02You're happy with that? Great. Thank you.
4:39:05Okay. So before clarifying,
4:39:07it could be a bow style bridge.
4:39:10It would just be made of steel
4:39:11instead of the historic cement.
4:39:14Okay. Correct. Yeah.
4:39:16Okay. Thank you. Thank you very much.
4:39:19This is very, very difficult decision.
4:39:22I put it out on our newsletter on Friday
4:39:25to get some more feedback from our constituents.
4:39:28And I did, at that time here at about a ratio of four to one
4:39:32that my constituents asked me to maintain
4:39:36that historic bridge because of the impact
4:39:40to the culture of the city.
4:39:41And I do listen to that.
4:39:43I also heard from many of my constituents
4:39:45who are concerned about the cost increases
4:39:47to our community and the affordability.
4:39:50So I think at this time I am really torn.
4:39:53I will be voting in favor of the staff recommendation
4:39:57this time, but just to, yeah, thank you.
4:40:00Thank you for that.
4:40:01It is a difficult decision,
4:40:03but I think that I may change my mind later on.
4:40:07This will come back to us at the end of the month.
4:40:09Is that correct? Okay. Correct.
4:40:11So I will.
4:40:12And if I hear significantly different from my constituents
4:40:14between now and the end of the month,
4:40:15I may change my mind on that.
4:40:17Thank you.
4:40:19Thank you, Councillor Goller.
4:40:20Councillor Caiten, please.
4:40:24Thank you. Through you.
4:40:27So considering for me the speed to completion,
4:40:31which includes all processes and appeals,
4:40:34the environmental impact to the habitats,
4:40:36which would occur in all the options
4:40:38that involve rebuilding the base,
4:40:40the cost stall, the departments and impact to workflow,
4:40:44if we were to go the demolition route,
4:40:46risking our heritage plan,
4:40:48which is on a sprint right now,
4:40:49just to meet the provincial deadline,
4:40:52consistency of adherence to our heritage policies,
4:40:54the fact that we unanimously passed
4:40:57our part five designation on this just very, very recently.
4:41:01And the guarantee of the yearly maintenance funding.
4:41:05And also I attended the public feedback
4:41:07and the engagement that our group did.
4:41:11And it was really great.
4:41:12Like it was really well done.
4:41:14And everybody who walked through there
4:41:16wanted the bridge rehabilitated.
4:41:18And finally, just as a ward one Councillor,
4:41:20we deserve nice things too.
4:41:22We deserve some heritage.
4:41:24And the rest of the heritage covered under the policy
4:41:27we passed is owned by the province.
4:41:28And we saw how that went with the bridge
4:41:30that they just demolished in this area.
4:41:33So I'm very, very happy to support
4:41:37the staff recommendation and all the great work
4:41:39that you've all done.
4:41:40Thank you.
4:41:42Thank you, Councillor Caton.
4:41:44Councillor Hauser, please.
4:41:47Thank you.
4:41:48I would just like to echo Councillor Caton's
4:41:50mostly summed up what I was gonna say.
4:41:53What I really think is very valuable is,
4:41:55like this is 110 years old.
4:41:57It's very literally a bridge to history.
4:42:00The brand new bridge that we're gonna build,
4:42:01we're looking at longevity of 70 years.
4:42:04This one's already 100.
4:42:05And that's pretty remarkable.
4:42:06So I will be supporting as well.
4:42:09Thank you, Councillor Hauser.
4:42:10Councillor Caron, please.
4:42:12Yes, thank you.
4:42:14And I really, I appreciate the discussion.
4:42:17I know that there's been a discussion in the community.
4:42:19I know that their Councillor Goller initiated the question
4:42:23of whether the financial acumen balances out
4:42:28with all the other community aspirations.
4:42:30So I really appreciate that discussion.
4:42:32For me, this is a file that goes back
4:42:34so long and it won't come as a surprise
4:42:38that I'm passionately asking my Councillor colleagues
4:42:41to support preservation.
4:42:44This started for me in 2004.
4:42:46I wasn't even on council at that time,
4:42:48but I was the chair of Heritage Guelph
4:42:50at the time when this was designated.
4:42:52And the designation was at a time when, again,
4:42:55the reformatory lands were also being decommissioned
4:43:00or had already been decommissioned.
4:43:02There were some stone gates on Stone Road
4:43:04that led to this bridge that have since disappeared.
4:43:08I recall vividly standing at this bridge
4:43:12with members of Puslench Township Heritage Committee
4:43:16where we talked about this being their heritage
4:43:19because this was the township line
4:43:24prior to city boundaries expanding
4:43:27and a conversation about our obligation
4:43:29to protect their heritage as much as our own.
4:43:33In 2005, we had our Trails Master Plan
4:43:35identifying this connection.
4:43:37In 2016, again, the Trails Master Plan.
4:43:412004, I have an email from staff
4:43:44which I've circulated to members of council
4:43:47with a commitment to preserve.
4:43:49In 2019, we had our stranded asset report first tabled
4:43:53where a commitment to preserve was embedded in that.
4:43:56We've had commitments through three different CAOs
4:43:59that our heritage assets would be conserved.
4:44:02So for me, this is very much a matter of credibility.
4:44:05We have property standards bylaws for heritage assets.
4:44:09We have our part four and part five.
4:44:12There's very few individual structures like this
4:44:14that have both protections under the Heritage Act.
4:44:18I think we've created a community expectation
4:44:21when we passed those designations
4:44:23that preservation would be our priority.
4:44:26I wasn't gonna call a point of order,
4:44:28but I did hear my counselor colleague Gibson stating
4:44:32that counselors were somehow putting hurdles
4:44:36in the way of our professional staff
4:44:38and questioning the expertise of our structural engineer
4:44:42who's with us online and our professional staff here
4:44:45in the council chambers with us
4:44:49and questioning their assessment
4:44:51of their expert engineering advice.
4:44:52So I just want to point out that I have full confidence
4:44:55in your abilities and your advice
4:44:57as professional engineers in the delivery of this AEA to us
4:45:02and the final recommendation of option two
4:45:07was thoroughly assessed
4:45:08with lots of different parameters including financial
4:45:11and that maintaining the heritage rose above all of that,
4:45:15even including those financial.
4:45:17We've already lost the Trestle Bridge on the GID lands,
4:45:21losing a second bridge is just,
4:45:25when there's no need for that,
4:45:26there is no other opportunity for us
4:45:29to restore this once it's gone.
4:45:32I am sensitive to the financial limitations
4:45:35and I don't want anyone to believe
4:45:38that that isn't a factor in my decision making as well,
4:45:42but I know that this is a long game.
4:45:44I know that it has been a long game for 110 years,
4:45:49but I'm confident that we have a future generation
4:45:54well beyond us who will be able to enjoy this bridge
4:45:57just as earlier generations before we were born,
4:45:59unless any of us were born before 1916,
4:46:03that the stewardship of this asset
4:46:06will last well beyond our lifetime
4:46:09and that we have an obligation
4:46:10and I've heard the word obligation
4:46:12from many counselors including Councillor Chew,
4:46:16Councillor Goller, Councillor Gibson,
4:46:18I've heard the word obligations
4:46:20in a number of our narratives today,
4:46:22and so for me this obligation of stewardship
4:46:26extends well beyond the next term of council
4:46:29and into the next generation, so thanks.
4:46:32Thank you, Councillor Caron.
4:46:34Councillor Allt, please.
4:46:38Thank you very much, Madam Chair.
4:46:40First of all, I would like to thank staff
4:46:42for the tremendous work that is being done
4:46:45on this particular issue.
4:46:47Certainly your professional credentials
4:46:49and your integrity should not come into question on this.
4:46:52I believe that you have worked very solidly on this.
4:46:55Whether a heritage attribute is downtown
4:47:00in the inner city, word four, five, or six,
4:47:02I think it's incumbent upon us to research
4:47:04all of these to determine what the value is
4:47:07of preserving them.
4:47:08Similarly, I think we have a governance issue here as well.
4:47:11We have identified that this bridge is protected
4:47:14under the parts four and five
4:47:17of our heritage determination.
4:47:21I also note that I got an email from a bridge lover
4:47:26from Nova Scotia, pointing out that a preliminary search
4:47:30of the web has shown that this is the second oldest bridge
4:47:33of this type in Ontario.
4:47:36Now that begs two questions.
4:47:38Where is the oldest bridge, and why is it still standing?
4:47:42Should it not have come down as well?
4:47:44I also reflect on something that I'll bet you
4:47:47that most people here, I think maybe everybody except
4:47:50for me is too young to remember,
4:47:53and that's the monkey bridge on the Speed River,
4:47:56which is very similar that came down a long time ago,
4:47:59just below the dam.
4:48:01This particular bridge was lamented by many people my age
4:48:05because it was known as the monkey bridge
4:48:06because we hung off it and jumped into the river,
4:48:09which was pretty stupid, but we did it anyway.
4:48:12And I don't wanna see another one go.
4:48:15I'm gonna support the staff recommendation.
4:48:17I thank you for your work.
4:48:19I'm certainly gonna hold your feet to the fire
4:48:20on things like cost, but in terms of your professional
4:48:23integrity, I appreciate that, and I know that we will hear
4:48:27more from you as we look for heritage attributes
4:48:30in structures in word four, word six, word one,
4:48:35and elsewhere in Guelph, heritage is worth considering
4:48:39and preserving.
4:48:42Thank you, Councillor Allt.
4:48:43Councillor Chew, please.
4:48:48Yeah, through you, Madam Chair,
4:48:50thank you for facilitating this discussion.
4:48:53For me, I appreciate staff being able to point me
4:48:56to some of their work.
4:48:59$2,000 a year versus $5,000 a year.
4:49:03It's not about not spending money, it's about wearing how,
4:49:06and we're looking at an investment for a product
4:49:09that can last much longer than this concrete structure
4:49:12to maintain.
4:49:13So for me, it's very clear what the path is,
4:49:16but I also think there are very tasteful ways
4:49:19to preserve heritage and pay homage to the history.
4:49:24And I also value, I do see value in this linkage
4:49:27being preserved, and for those reasons,
4:49:30I personally would like to support options for,
4:49:33but I also see kind of where the world council is
4:49:36at the moment, so I'm just gonna leave my comments there
4:49:39and also say I won't be supporting the staff recommendations
4:49:42just for those reasons.
4:49:43Thank you.
4:49:45Councillor Downer, please.
4:49:48Thanks.
4:49:49So again, thanks to staff for the work
4:49:51that they've done on this and respecting
4:49:54and the way it was weighted and the criteria,
4:49:58taking into account the strong engagement that was had
4:50:05with people and their preference to keeping this bridge.
4:50:08So it went through a lot of public engagement,
4:50:10a fair amount to see what the community felt about it
4:50:15and the community recognized that the cultural value
4:50:18of this bridge that, and some of us may think,
4:50:21well, it's on the edge of town, it's not, you know,
4:50:24nobody sees it, all those types of things.
4:50:26You gotta remember there's 5,000, I forget if it's 5,000,
4:50:29but there's thousands of people moving into the GID lens,
4:50:32probably within the next 10 to 20 years.
4:50:35And these types of structures,
4:50:40these sense of place is important to a lot of communities.
4:50:44It ties us to our rural background
4:50:47and where we've been and where we've come.
4:50:50And those are very difficult to replicate.
4:50:54And the 30 years versus 75,
4:50:57it's kind of hypothetical in some ways
4:50:59because we don't know really in 30 years
4:51:01what this building would be like.
4:51:03I like to think that my house, my 100-year-old,
4:51:06110-year-old house is not done in 30 years
4:51:08when somebody does a reassessment of it.
4:51:11So, I mean, and that may happen, that maybe it will be,
4:51:16but I do think it's valuable to the community.
4:51:25And so I do think it's worth us preserving
4:51:27that heritage feature in that part of the city,
4:51:31where we're gonna have a growing population
4:51:33moving out that way as well.
4:51:35And not to say that people are not using it today,
4:51:38which sounds like it's getting a lot of use.
4:51:40People, the emails we're getting are recognizing
4:51:44and saying that we value this.
4:51:46We value it as a crossing,
4:51:47but we also value it as a heritage structure.
4:51:52Thank you, Councillor Kedana.
4:51:53Councillor Boustele, please.
4:51:56Thank you, and through you, Madam Chair,
4:51:58thank you for this report and also echo my colleagues.
4:52:01Thank you to the staff for this.
4:52:02I think as I've gone through the anniversary
4:52:05of the city of Guelph as a West Ender, Ward 4,
4:52:08I echo Councillor Catons, we like nice things too
4:52:12in Ward 4, and it would be nice to have some cultural,
4:52:15historical context there for the residents.
4:52:18What I take away from this, and I come from Italy,
4:52:20so Emilio Romagna, Porto De Fechio,
4:52:23and all those kinds of things,
4:52:24those are Christopher Columbus's doorknob on his house.
4:52:28History is really important in developing the culture
4:52:30of our community.
4:52:32And so what I heard is that this bridge is significant.
4:52:36It's one of the few remaining in the country.
4:52:38It's a heritage bridge on the Ontario formatory
4:52:41heritage district over a heritage river,
4:52:44like how much more.
4:52:46And to me, it screams of speaking our story
4:52:50in this community.
4:52:52So it's important to me,
4:52:53and I think it's important to future generations.
4:52:56So thank you to staff.
4:52:57I will be supporting the staff recommendation.
4:53:01Thank you, Councillor Abustel.
4:53:04Are there any comments from anyone who hasn't spoken yet?
4:53:08Councillor Gatheery again, but no, Mayor Gatheery.
4:53:14Excuse me.
4:53:15It's okay.
4:53:17Thank you.
4:53:18Yeah, I wasn't going to speak, but maybe I think I will.
4:53:21I appreciate it with Councillor Caron said right off the top,
4:53:24about like it's nice to have the discussion.
4:53:26And it is a passionate discussion.
4:53:28We're passionate in different areas.
4:53:30Like I'm not upset that this looks to me
4:53:32like it's going to pass and that's fine.
4:53:34Not an issue.
4:53:36But I, some people are passionate really heavily
4:53:40into the heritage side of things.
4:53:41I don't think it would be a surprise if people knew
4:53:43that I'm pretty passionate on their trying to save money
4:53:45side of things as well.
4:53:47And I feel that there is an option in front of us here
4:53:50where we can have a bridge that can be made,
4:53:54that gives attributes to the heritage and the history,
4:53:58and literally saves $1.8 million.
4:54:02That to me seems like the win that I would take,
4:54:06but I understand and respect the passionate debate
4:54:09on the other side of it,
4:54:10even though we're on two different sides of a bridge,
4:54:13I guess on this one.
4:54:15So just another thing too is that the decision to preserve
4:54:23is a budget decision.
4:54:25So every year at budget time,
4:54:30there is the backlog of asset renewal
4:54:33and assets that we have on the books.
4:54:35Any one of us has the opportunity to present
4:54:39an option to council to increase or shift
4:54:43or move other things around to accommodate
4:54:46the priorities that we're all passionate about.
4:54:49So that never happened on this one,
4:54:51which is why we're now here with a replacement
4:54:53versus restore sort of debate as well.
4:54:59I do feel like this is way too much money for what it is.
4:55:04And to me, it comes down to just the,
4:55:07to me, it's the issue of what are we trying to solve?
4:55:11It's to get from one side of the bank
4:55:13or the river to the other.
4:55:14That's where I'm at on this,
4:55:16and to do it in the cheapest way possible.
4:55:20I think this is a bridge too far for the taxpayers.
4:55:23And it concerns me, I've seen this sort of,
4:55:30historically I've seen when there's options
4:55:32in front of us, of council in the past,
4:55:35that sometimes it just feels like we're always kind of going
4:55:38for the more expensive options all the time.
4:55:42And this is just another one.
4:55:44And so to me, and maybe our CFO can correct me
4:55:49at the end of the month,
4:55:49but the differential in costs here is 0.5%
4:55:55of a tax increase.
4:55:59So that's what the differential in cost is.
4:56:021.8 million, 3.6 is equal to one approximately.
4:56:06So point, you know, we're,
4:56:08you just, the decision today,
4:56:12as much as people want to call it a cultural
4:56:14or a heritage decision is a budget decision.
4:56:19And I would rather do it at a new bridge
4:56:24that gives homage to the old one,
4:56:27at a way less cost and way less operating costs.
4:56:33And I guarantee a cost, it's going to last longer.
4:56:41It's going to last longer.
4:56:42So that's where I land.
4:56:44That's my passion on this side.
4:56:46And I appreciate you letting me kind of jump in
4:56:50on those reasons why I certainly will not support what this is.
4:56:55And frankly, you know, when engagement happens
4:57:00on these types of things, and it is good engagement,
4:57:02don't get me wrong, it is very good engagement
4:57:04with the public, but there, I don't think like actual costs
4:57:08are told at the time, right?
4:57:11Am I right, sorry, am I right on that?
4:57:13When engagement is happening on EAs and such,
4:57:16when you're doing the open houses,
4:57:18like do you also say to the public,
4:57:19and by the way, it might cost X or it might cost Y,
4:57:22is that stated, I can't remember?
4:57:26Through you, Madam Chair, I'm trying to recall
4:57:29if we had cost values in the most recent public open house,
4:57:34we certainly had the evaluation summary
4:57:36with the scoring for cost and financial criteria.
4:57:40So certainly for sure that was presented,
4:57:43we'd have to get back to you and check on.
4:57:45No problem, no problem.
4:57:46What I'm trying to say is that since this report
4:57:48has come out, you know, and we all have kind of different
4:57:51groups that might be closer to us, right?
4:57:53I'm hearing from kind of a bigger portion of the city
4:57:56saying, really, you're gonna spend that much money
4:57:59when there's an alternative option
4:58:01that's like under half of the price.
4:58:03So that's kind of, that's the consistency
4:58:05and the feedback that I'm receiving so far to date on this.
4:58:10So with that, you know, I appreciate the dialogue
4:58:14and appreciate wherever,
4:58:15I wanna respect wherever council wants to go on this,
4:58:18but I'm really concerned about the costs here,
4:58:23as you can tell.
4:58:24Thank you very much.
4:58:26Thank you, Mayor Guthrie.
4:58:28Well, that brings us to the end
4:58:31of a very passionate discussion.
4:58:35And I just, I would like to really thank staff
4:58:38for all of your effort in the EA
4:58:41and in preparation for this discussion.
4:58:44I spent a little bit of that time with you,
4:58:47and I know that that was just the tip of the iceberg
4:58:51when it comes to everything that you did,
4:58:53discussions with the public, discussions with staff,
4:58:56and all of the consultants.
4:58:58I really appreciate everything that goes into this,
4:59:00especially when it's a complex issue,
4:59:03when there are a lot of differing opinions
4:59:05around the horseshoe.
4:59:06I also wanted to just acknowledge that, you know,
4:59:10it is really good when we disagree on these issues.
4:59:14I think that it makes for a fulsome conversation,
4:59:17and it's part of this work as well.
4:59:20And so I just wanted to thank all of my colleagues.
4:59:23I had some interesting conversations
4:59:25with those of you who are interested in option number four,
4:59:28and those of you who are interested in option number two.
4:59:30And I thought there were some very compelling arguments
4:59:33on both sides, some of which were made here today.
4:59:36So I just wanted to say thank you
4:59:37for those respectful conversations.
4:59:39I also wanted to add that as far as,
4:59:44I don't want to add anything new.
4:59:45I think that we had some very compelling arguments today,
4:59:48especially with some of the knowledge and history keepers
4:59:51that are here on council who know about our city's past.
4:59:55And I really want to acknowledge, you know, that as well.
5:00:00I think that really adds to the storytelling of this place.
5:00:04I want to talk about value for money.
5:00:07As a city, we invest in economic development,
5:00:10wayfinding, and tourism.
5:00:12And part of those cultural assets include our down,
5:00:16we recently designated our downtown.
5:00:19We're looking at designating our ward west.
5:00:22As a council and as a community, we have identified
5:00:26that these are some of the reasons that make Guelph Guelph.
5:00:29And when I think about cultural heritage assets
5:00:33and infrastructure, sometimes I think
5:00:35that they are a bit at all.
5:00:37Because infrastructure needs to serve a purpose,
5:00:39which is typically to help us get from place to place.
5:00:42And old infrastructure sometimes needs to be replaced.
5:00:46And so I appreciate that the nuance in that discussion.
5:00:51But I want to go back to the investments
5:00:53that we're putting into tourism.
5:00:55Recently, I saw a grant that was available
5:00:57for cycle tourism.
5:00:59We're investing in various ways of getting people
5:01:02to commute, to visit, to see our city.
5:01:05And it is a big component of why people choose to live here,
5:01:08but then also why they choose to come here and to visit.
5:01:12And as we grow as a city, I think that we need to look
5:01:14at these as investments and not as expenses.
5:01:19And so I will be supporting the staff recommendation.
5:01:23And with that, I would like to call the vote.
5:01:26So I have Councillor Gibson who is phoned in.
5:01:30So first, I'd like to ask Councillor Gibson
5:01:34if you support, if you are for or against
5:01:37the staff recommendation.
5:01:39Thank you, Councillor Clausson.
5:01:41I'm against.
5:01:43Thank you, Councillor Gibson.
5:01:45And now for the rest of council,
5:01:48I would like to ask if you are,
5:01:50if anybody is against the recommendation.
5:01:54And I will call out the names Mayor Guthrie,
5:01:58Councillor Richardson, Councillor Billings,
5:02:01Councillor Chew, and that is all.
5:02:05We have four voting against, five voting against, thank you.
5:02:11And so that passes.
5:02:14Thank you everyone for the discussion.
5:02:16And we are now going to take about a 30 minute break
5:02:20for dinner and we'll come back to discuss
5:02:22the three remaining items on the IDE agenda.
5:02:26Thank you and we'll be back here at 6.15.
5:34:26Welcome back everybody.
5:34:28It is 6.15 and we are going to get started
5:34:31with the rest of our agenda items.
5:34:33So next up on the agenda is our outside water use bylaw.
5:34:42So before we get started, I would like to just take a moment
5:34:46to reflect on our role as responsible stewards
5:34:49of our community's water resources
5:34:51and thank staff for bringing this bylaw update forward to us.
5:34:56Before we get started on everything else,
5:35:00we've got a presentation from Heather Yates.
5:35:02So Heather, welcome to the podium.
5:35:05Thank you and good evening Chair class
5:35:12and members of City Council.
5:35:13My name is Heather Yates.
5:35:14I'm the manager of compliance, programs and performance
5:35:17in environmental services.
5:35:19It's my pleasure to present the details of the update
5:35:22to the outside water use bylaw.
5:35:24City of Guelph has long been an early adopter
5:35:32and lead in municipal water demand.
5:35:34As a groundwater based community, with finite supply,
5:35:37Guelph's success in managing seasonal water demand
5:35:40has assisted in securing water servicing capacity
5:35:43and ensuring compliance with our permitted water takings.
5:35:46With support from GEI Consultants Canada,
5:35:49staff initiated a review of the 2014 outside water use bylaw.
5:35:54This was to ensure alignment with updated regulation,
5:35:57policies and environmental protection since 2014.
5:36:00Most notably an update on our local water use bylaw
5:36:03and update on our local water bylaws
5:36:05for sewer use bylaw and water bylaw,
5:36:08as well as our source water protection
5:36:10and water quantity policies.
5:36:12We also needed to assess fee structure
5:36:14and enforcement practices to verify present day needs.
5:36:19We wanted to consider feedback of community members,
5:36:22including some of the feedback received
5:36:24on ease of use of the current structure
5:36:27and evaluate some of the comparator practices
5:36:29that exist since 2014,
5:36:31as well as our water changes in water using patterns
5:36:35since that time.
5:36:41You're likely familiar with the image you see before you.
5:36:44These are our current program levels
5:36:45associated with the outside water use bylaw.
5:36:48For context of the update,
5:36:50I'd like to describe the current bylaws program
5:36:52and how staff use data to support changes in the levels.
5:36:57Staff monitor and analyze several conditions
5:37:00that determine whether more cautious water use
5:37:02is required or appropriate.
5:37:04These conditions include temperature
5:37:06and quantity of rain,
5:37:08surface water body levels provided
5:37:09by the Grand River Conservation Authority,
5:37:13and overall tracking of water production.
5:37:15Water production is that of the amount
5:37:18of water water services pumps,
5:37:20treats and distributes in total
5:37:21to the drinking water system per day.
5:37:24Based on these factors,
5:37:25staff produce a weekly condition report
5:37:28indicating what level of outside water use is appropriate,
5:37:32protecting the supply within the parameters
5:37:35of our permits to take water.
5:37:38When a combination of factors are met or exceeded,
5:37:41staff make the data-driven decision
5:37:43to elevate or de-escalate a level.
5:37:46The levels have predetermined outside water
5:37:47using activities that are permitted or constrained
5:37:50based on the severity of local water conditions.
5:37:53Staff use our various communication channels,
5:37:56including the city's webpage, social,
5:37:58and the city's infamous roadside signs
5:38:00to inform residents and businesses